FBC LID 7 Update NTRCA Annual Meeting January 21, 2019 Directors Jim Grotte, Cindy Picazo, Gerald Kazmierczak, Jeff Hanig & Michael Pincomb
FBC LID 7 Projects Brazos River Erosion Expanded Pump Station Expanded Internal Detention North Levee Enclosure External Channel Erosion
Brazos River Erosion Est Cost: $60 MM Est Grant: $45 MM* Est LID 7: $15 MM Est Completion: 2021-22 *Approved at TX State level. FEMA approval required.
Expanded Detention & Pumpage Detention Est Cost: $5-10 MM Timing: 2020-22 Pumpage Est Cost: $5-10 MM Timing: 2019-20 Design protection to 71.5 ft * (Lowest home foundations 73.0) ft) (Peak Harvey 73.3 ft) * True elevation **Diagram from Costello Internal Drainage System Hydrologic and Hydraulic Analysis
2018 Accomplishments FEMA Brazos River Funding o Received Texas Division of Emergency Management (TDEM) approval for up to $45 MM Federal Hazard Mitigation Grant funding for Brazos River erosion project. Major milestone, though still requires FEMA technical review and approval. Internal Drainage System Hydrologic and Hydraulic Analysis (Costello) o 508 Acre-ft internal existing detention. o Additional 150 acre-ft required to protect for Harvey type event. o Additional 160,000 GPM required to protect for Harvey type event. o Purchased five 10,000 GPM gator pumps for short-term protection. Interviewing New District Engineering Firms o Interviewing two candidate firms. Regional Coordination o On-going discussions with FBC on joint flood protection for 90/99 intersection. o On-going discussions with City of Sugar Land on land acquisition required for Brazos River access, pump station expansion and external channel erosion control. o Coordinating with US Army Corp of Engineers on permitting and river boundaries for Brazos River project.
2019 Goals Select new District Engineer (1 st Qtr 2019) Hire outside General Manager (1 st Qtr 2019) Assist with project coordination & contract negotiation o Shift work load from legal team. Brazos River Erosion o Complete FEMA funding approval process (3 months). o Complete 30% design. o Seek passage of bill in 2019 State legislative session allowing for Design-Build project procurement. o Finalize design and plan for construction (late 2019). Expanded Pumpage & Detention o Finalize detention approach (3 options under consideration). o Begin detention excavation (late 2019 – early 2020). o Complete 160,000 GPM pump station expansion design. o Begin pump station construction (late 2019 – early 2020). North Levee o Evaluate options. o Seek outside financial support.
Financials Developed Cash Flow Proforma o Forecasts required for project funds over 18 month horizon. Strong Cash Position o $2.5 MM liquid cash balance. Sold $12.15 MM in bonds o Provides initial funding for Brazos River project. o Provides initial funding for expanded internal detention and pumpage. Identified low cost bond funding available through Texas Water Development Board