DOMAIN COMMUNITY REFERENCE GROUP Meeting #18 Wednesday 16 October, - PowerPoint PPT Presentation

DOMAIN COMMUNITY REFERENCE GROUP Meeting #18 Wednesday 16 October, Seasons Botanic Gardens 1 ST KILDA ROAD REALIGNMENT UPDATE 2 ST KILDA ROAD REALIGNMENT OVERVIEW 3 TIME-LAPSE SEPTEMBER 1 TO OCTOBER 15 4 5 NORTH VIEW 7AM MONDAY 14


  1. DOMAIN COMMUNITY REFERENCE GROUP Meeting #18 Wednesday 16 October, Seasons Botanic Gardens 1

  2. ST KILDA ROAD REALIGNMENT UPDATE 2

  3. ST KILDA ROAD REALIGNMENT OVERVIEW 3

  4. TIME-LAPSE SEPTEMBER 1 TO OCTOBER 15 4

  5. 5

  6. NORTH VIEW 7AM MONDAY 14 OCTOBER 6

  7. NORTH VIEW 6.45AM WEDNESDAY 16 OCTOBER 7

  8. SOUTH VIEW 7AM MONDAY 14 OCTOBER 8

  9. SOUTH VIEW 6.45AM WEDNESDAY 16 OCTOBER 9

  10. MAP OF CURRENT WORK ZONES 10

  11. WORKS LOOKAHEAD 11

  12. ENVIRONMENT UPDATE 12

  13. NOISE SO FAR – SUNDAY 13 OCTOBER Building Unmitigated predicted Night-time measured noise level dB dB The Domain <65 64 The Botanica <65 64 Hallmark Apartments <65 56 Domain Hill <65 62 13

  14. NOISE SO FAR – MONDAY 14 OCTOBER Building Unmitigated predicted Night-time measured noise level dB dB The Domain >75 79 The Botanica >75 79 Hallmark Apartments >75 73 Domain Hill >75 75 14

  15. NOISE SO FAR – TUESDAY 15 OCTOBER Building Unmitigated predicted Night-time measured noise level dB dB The Domain >75 70 The Botanica >75 70 Hallmark Apartments >75 66 Domain Hill >75 66 15

  16. WORKS UPDATE 16

  17. ANZAC STATION PROGRAM Melbourne cup site shut down 2-6 November 2019 17

  18. CURRENT AND UPCOMING WORKS NORTHERN SECTION • Excavation through the voids • Base slab construction • 24 hour works under the roof slab Under the roof slab 18

  19. EXCAVATION 19

  20. STRUTTING, LOOKING SOUTH 20

  21. UPCOMING WORKS BASE SLAB CONSTRUCTION 21

  22. BASE SLAB CONSTRUCTION • Start at southern end and move north in seven sections over two stages • Similar methodology as roof slab • First stage of base slab construction will require protection of the South Yarra Main Sewer • 24 hour works under the roof slab Northern section of the station box layout Illustration of sewer protection works 22

  23. UNCOVERING THE SEWERS 23

  24. SEWER PROTECTION WORKS 24

  25. MIDDLE BOX 25

  26. DIAPHRAGM WALL AND PILING Works in the southern section of the station box 26

  27. SITE LAYOUT After realignment map Artists impression Indicative only 27

  28. UPCOMING WORKS TUNNEL BORING MACHINE DELIVERY 28

  29. DELIVERY LOGISTICS • Deliveries must be made overnight to minimise impacts on traffic and trams • 40 oversized deliveries starting from between late November and May • Working with Yarra Trams and VicRoads on best route options as tram wires need to be lifted to allow for some pieces to be delivered. Tunnel boring machine cutterhead delivery western precinct 29

  30. CREATIVE PROGRAM UPDATE 30

  31. METRO TUNNEL CREATIVE PROGRAM ARTWORK Watercolour herbarium By Caitlin Klooger, 2019

  32. DOMAIN ROAD POP-UP PARK UPDATE • Fabrication of the Domain Road Pop-up park currently occurring offsite. • Structure will be transported in a series of modules and installed on site. • Planting consistent with Royal Botanic Garden’s ‘Landscape Succession Strategy’. • Images provide reference to the look and feel of planting for the Domain Road Pop- Up Park.

  33. METRO TUNNEL CREATIVE PROGRAM POP-UP PARK PROGRESS Domain Road Pop-up Park • Installation for later in the year. • Built offsite to minimise disruption with planting to occur onsite. Albert Road Reserve Pop-up Park • Ongoing work occurring offsite • Installation anticipated for early 2020.

  34. THANK YOU 34