Dale Drive Pedestrian Facilities Improvements Project Facility Planning Study
Life of A Transportation Project Facility Planning – Phase 1 Facility Planning – Phase 2 Final Design and Construction •Collect data, obtain •Develop 35% design •If approved for full public input, develop plans funding and is included concept plans in CIP, complete final •Refined project design and construction •Evaluate and select schedule & cost preferred •Mandatory Referral alignment/typical •Submittal to County section Council for Approval to •Obtain Director’s and include in Capital Montgomery County Improvement Project Council’s Transportation (CIP) Infrastructure, Energy and Environment Committee (T&E) Approval Legend Currently Not Funded Funded
Project Overview
Potential Concept Alternatives Alternative 0 – Sidewalk or Shared Use Path on 1 side
Potential Concept Alternatives Alternative 1 – Sidewalk on both side
Potential Concept Alternatives Alternative 2 – Sidewalk on north side, SUP on south side Alternative 3 – Sidewalk on both side with separated bike facilities
Potential Concept Alternatives https://platform.remix.com/streets/plan/48e52cc5?latlng=39.00747,-77.03206,z16.471,p0,b0
Tentative Milestones Schedule • Preliminary Engineering (30%) Design Jul ’18 • Project Kickoff • SWM Concept Submittal Jan ’19 Aug ’18 • Base Mapping & Topographic Survey • Mandatory Referral Submittal to MNCPPC Mar ’19 Sept ‘18 • Conceptual (15%) Design • Mandatory Referral Hearing (Estimated) May ’19 Oct ’18 • Public Workshop • Revised Preliminary Engineering (35%) Design • Environmental Coordination & Jun ’19 • End Facility Planning Submittal Dec ’18