constant terminal voltage
play

Constant Terminal Voltage Working Group Meeting 3 19 th June 2014 - PowerPoint PPT Presentation

Constant Terminal Voltage Working Group Meeting 3 19 th June 2014 Overview Options Study results Theoretical Analysis Summary 2 Options Option 1 Constant Terminal Voltage controlled to 1 p.u with full Transformer Tapping


  1. Constant Terminal Voltage Working Group Meeting 3 19 th June 2014

  2. Overview � Options � Study results � Theoretical Analysis � Summary 2

  3. Options � Option 1 – Constant Terminal Voltage controlled to 1 p.u with full Transformer Tapping � Option 2 - Adjustable Terminal Voltage with a limited Transformer Tapping Range � Option 3 – Limited Transformer Tapping Range only 3

  4. Advantages / Disadvantages Option Advantages Disadvantages 1 i) Generator Terminal voltage i) Potentially more expensive than other options (eg continuously controlled to 1p.u Transformer required with wider tapping range). ii) Maintains current Dynamic ii) References to BCA – Loss of Transparency Reserve provision post fault. iii) Does not fully address Derogation issue iii) Maintains Stability margin 2 i) Potentially cheaper Generator i) Less dynamic MVAr reserve provision post Transformer with lower tapping fault. range. ii) Lower Stability Margin ii) Preserves the total reactive iii) More complex to define minimum requirements of capability (ie operating envelope still Generator transformer tapping range and Generating maintained) Unit target voltage range. iv) Wider System implications would need to be understood eg would more reactive compensation equipment be required on the System or would enhanced excitation performance requirements be necessary. 3 i) Potentially cheaper Transformer i) As per option 2 in particular iv) which is likely to result with lower tapping range in potentially greater costs to both NGET and Generators 4

  5. Summary from Previous Meeting � Each option does have an effect on the terminal voltage of the Generator and the System Operators ability to control system voltage � Impact on Excitation voltage and MVAr reserves � Whilst impact on a machine basis is small this would be more significant across the total System � National Grid’s preferred approach is Option 1 Constant Terminal Voltage controlled to 1 p.u with full Transformer Tapping. Applies to new plant with relaxations permitted for existing plant who are unable to meet the current GB requirements 5

  6. Multi Machine Study 6

  7. Study Statistics � Winter Peak 2014 Study � Peak Demand = 54.4GW � MVAr Demand = 14.8 MVAr � Double circuit fault applied to Canterbury – Kemsley, Canterbury - Cleeve Hill � Test Station – Marchwood - run at maximum reactive output - full lag (0.85 PF lag). � Generator limits not modelled

  8. Options – Test Generator - Marchwood � Option 1 - Full Generator tapping range ( ± 13 taps) – 1.25% tap step size on transformer voltage rating � Option 2 - Limited tapping range ( ± 6 taps) and terminal voltage adjusted to 1.0118 p.u – 1.25% tap step size on transformer voltage rating � Option 3A – Limited tapping range ( ± 6 taps) and terminal voltage adjusted to 1.0 p.u – 1.25% tap step size on transformer voltage rating � Option 3B – limited tapping range and 1.0 p.u voltage ( ± 6 taps) – 2.5% tap step size on transformer rating 8

  9. Reactive Power Output - Marchwood Option 1 9

  10. Marchwood – Terminal Voltage Option 2 Option 3B 10

  11. 400kV Voltage - Marchwood Option 3B Option 2 Option 3A 11

  12. 400kV Voltage - Bolney Option 1 Option 3B 12

  13. 400kV Voltage - Canterbury Option 1 Option 1 Option 2 Option 3B Option 3A 13

  14. Theoretical Analysis � Single line diagram � Equivalent circuit � Data from a typical Generator Transformer � Copper losses neglected � Generator not modelled 14

  15. Machine MVAr Output 2 2 � � V V V P � � g s g = g − − Q � � g � � X aX a tr tr Increase Tap 400 300 Position 10 200 100 Position 6 Qg (MVAr) 0 Position 0 -100 -200 Position -6 -300 Decrease Tap Position -10 -400 0.94 0.96 0.98 1 1.02 1.04 1.06 System Voltage (pu) 15

  16. Setting the terminal voltage � Point 1: 400 300 1 3 � 1.05pu Voltage at the GEP 200 � 1.0pu Generator Terminal Voltage 100 � Tap position 9 Q (MVAr) 2 0 � Point 2: -100 � Change to tap position 6 -200 -300 0.94 0.96 0.98 1 1.02 1.04 1.06 Voltage (p.u.) � Point 3: � Increase the machine terminal to 1.031pu 2 4 2 � � � � � � 1 1 V V V ( ) � � � � � � 2 = s + + s + s − V X Q X Q X P g tr g tr g tr g � � � � � � 2 4 a a a 16

  17. Response to a step change in voltage � Reactive power output 2 2 � � V V V P � � g s g = g − − Q � � g � � X aX a tr tr � Rate of change of reactive power output for a step change in voltage at the Grid Entry Point 2 � � V � � g V � � s ∂ � � Q aX g tr = − ∂ V 2 � � V V P s � � g s g − � � � � aX a tr 17

  18. Response to a step change in voltage � Point 1, 2, and 3 correspond to the same initial operating points as per previous slide � Diagram shows increase in reactive power injected in response to a 5% step drop in voltage at the Grid Entry Point. � Results seem to suggest an improvement which is not evident from study work 115 Tap Position 9 Tap Position 6 110 Point 1 ∆ Q (MVAr)/5% drop in Vs Point 2 Point 3 105 100 95 90 85 0.9 0.92 0.94 0.96 0.98 1 1.02 1.04 1.06 1.08 1.1 18 Vg(pu)

  19. Summary � Results of multi machine studies (South Coast) show an second order effect but difficult to draw exact conclusions � Theoretical analysis suggests that an improvement in performance could be obtained if terminal voltage contributes to the HV voltage � This needs to be re-assessed in Digsilent / Power Factory to confirm the theory � Further feedback from working group required 19

  20. Discussion 20

Recommend


More recommend