cac temporary terminal presentation terminal presentation
play

CAC Temporary Terminal Presentation Terminal Presentation July 13, - PowerPoint PPT Presentation

CAC Temporary Terminal Presentation Terminal Presentation July 13, 2010 July 13, 2010 Program Status Program Status Finalizing Temporary Terminal construction Striping and traffic changes in progress p g g p g SFMTA and


  1. CAC Temporary Terminal Presentation Terminal Presentation July 13, 2010 July 13, 2010

  2. Program Status Program Status • Finalizing Temporary Terminal construction • Striping and traffic changes in progress p g g p g • SFMTA and other operators move to Temporary Terminal on August 7 th Terminal on August 7 • Demolition of existing ramps and Terminal begin on August 14 th on August 14 th • Seven year schedule for construction of the new T Transit Center it C t

  3. Temporary Terminal Access

  4. Temporary Terminal

  5. 41 38 38 38L 38L 108 5 71 71 71L 82X Phase 1 Temporary Temporary Terminal Operation Operation August to August to November 2010

  6. Temporary Terminal

  7. Phase 2 Temporary Temporary Terminal Operation Operation

  8. Key Outreach Dates Key Outreach Dates July 1 st • Install banners & re-launch website y July 7 th • Handouts available at Terminal J l 20 th July 20 th • Launch ambassador program L h b d July 30 th • Commemoration Event August 3 rd • Open House at Temporary Terminal August 7 th • Begin Operations at Temporary Terminal Begin Operations at Temporary Terminal August 7 August 11 th t 11 th • Transit Center Groundbreaking Event T it C t G db ki E t A

  9. Outreach Signage

  10. Signage

  11. Wayfinding Signage Wayfinding Signage

  12. Signage

  13. Questions?

Recommend


More recommend