Congress Avenue Road Rehabilitation Project City Council City of - PowerPoint PPT Presentation

Congress Avenue Road Rehabilitation Project City Council City of Pacific Grove Daniel Gho, dgho@cityofpacificgrove.org Recommendation Authorize the City Manager to enter into an agreement with Monterey Peninsula Engineering for the Congress


  1. Congress Avenue Road Rehabilitation Project City Council City of Pacific Grove Daniel Gho, dgho@cityofpacificgrove.org

  2. Recommendation Authorize the City Manager to enter into an agreement with Monterey Peninsula Engineering for the Congress Avenue Road Rehabilitation Project in an amount not to exceed $959,377 and a 15% contingency. Daniel Gho, dgho@cityofpacificgrove.org

  3. Congress Avenue Sunset Drive Congress Avenue between Sunset Dr. and David Ave. Amenities:  Pacific Grove High School  Forest Grove Elementary School  2 entry/exit gates to Pebble Beach  Road in/out of town David Avenue Daniel Gho, dgho@cityofpacificgrove.org

  4. Project Scope  51,000 SF of reconstruction  67,000 SF of asphalt concrete overlay Reconstruction AC Overlay Daniel Gho, dgho@cityofpacificgrove.org

  5. Project Scope  Installation of 12 access ramps & 4 ADA ramps  Construction of a continuous 5’ wide AC pedestrian walkway  Construction of 210 linear feet of curb and gutter and 1,120 SF of sidewalk  Stormwater improvements Daniel Gho, dgho@cityofpacificgrove.org

  6. Bidding Process  On April 5 the city distributed a call for bids  3 bids were received: Contractor Bid Amount Monterey Peninsula Engineering $959,377 Teichert Construction $975,079 Don Chapin Co. $1,026,625 Daniel Gho, dgho@cityofpacificgrove.org

  7. Funding Budgeted in the FY18/19 Capital Improvement Program Funding Source Amount Road Maintenance and Rehabilitation (Senate Bill 1) $257,361 Measure X $530,000 Regional Surface Transportation Program (RSTP) $121,000 General Fund $250,000 Total Project Budget $1,158,361 Daniel Gho, dgho@cityofpacificgrove.org

  8. Project Benefits  Creates safe routes to school  Formalizes complete street elements (AC path)  Completes necessary pavement improvements  Enhances storm water capacity  Increases access Daniel Gho, dgho@cityofpacificgrove.org

  9. Recommendation Authorize the City Manager to enter into an agreement with Monterey Peninsula Engineering for the Congress Avenue Road Rehabilitation Project in an amount not to exceed $959,377 and a 15% contingency. Daniel Gho, dgho@cityofpacificgrove.org

  10. Questions? City Council City of Pacific Grove Daniel Gho, dgho@cityofpacificgrove.org