Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Comparison of Air Distribution Comparison of Air Distribution Systems Systems Underfloor Air vs. Ceiling-Based Systems 2002-2003 AE Senior Thesis Allison M Clarke Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Presentation Outline Existing Building � Existing Building & Systems & Systems � Underfloor Air Distribution Underfloor Air � Ceiling-Based System System � Comparison Ceiling-Based Conclusion & Recommendations � System Comparison Recommendation Conclusions Allison M Clarke 2002-2003 AE Senior Thesis 1
Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Project Team Existing Building Owner - Capital One Financial Corporation & Systems Underfloor Air Owner’s Rep - Jones Lang LaSalle System Ceiling-Based Architect - Ai Architecture System Comparison GC - James G. DAVIS Construction Recommendation Structural Engr - Rathgeber/Goss Associates Conclusions MEP Engr - Ai Engineering Allison M Clarke 2002-2003 AE Senior Thesis Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Architecture Existing Building & Systems Underfloor Air System Ceiling-Based System Comparison Recommendation Conclusions Allison M Clarke 2002-2003 AE Senior Thesis 2
Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Location & Site Existing Building � 1600 Scotts Crossing Road & Systems McLean, VA � 26 Acres Underfloor Air � Borders I-495 Capital Beltway System Ceiling-Based Structure System � Base Building – Floors 1 & 2 Comparison � Cast-in-Place Concrete with Post Tension Beams Recommendation � Tower – Floors 3 – 14 � Steel Structure Conclusions � Concrete Slab on Metal Deck � 18” Raised Concrete Core � Typical Floor Space Allison M Clarke 2002-2003 AE Senior Thesis Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Mechanical Existing Building � Underfloor Air Distribution System in Tower & Systems � Four 600 ton Chillers Underfloor Air � 4-Cell Cooling Tower System � Two 22,000 cfm AHU’s per Typical Floor Ceiling-Based System Comparison Recommendation Conclusions Allison M Clarke 2002-2003 AE Senior Thesis 3
Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Underfloor Air Distribution Existing Building � Background Information & Systems System Components � Underfloor Air � Construction Methods/Schedule System � Energy Use Ceiling-Based � Costs System � Lessons Learned Comparison Recommendation Conclusions Allison M Clarke 2002-2003 AE Senior Thesis Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Background Information Existing Building Alternative to conventional ceiling-based air distribution � & Systems systems Underfloor Air � Previously used for spaces with high heat loads System � Introduces air at floor level Ceiling-Based � Occupied Zone – floor to head level System � Unoccupied Zone – head level to ceiling Comparison Recommendation Unoccupied Zone Conclusions Occupied Zone Allison M Clarke 2002-2003 AE Senior Thesis 4
Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Background Information Existing Building Benefits & Systems Improved thermal comfort for occupants � Underfloor Air � Improved ventilation efficiency & indoor air quality System � Reduced energy use from mechanical systems Ceiling-Based � Reduced life cycle building costs System � Reduced floor-to-floor height in new construction Comparison � Improved occupant satisfaction and productivity Recommendation Conclusions Allison M Clarke 2002-2003 AE Senior Thesis Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Background Information Existing Building Barriers & Systems � New & unfamiliar technology Underfloor Air � Perceived higher costs System � Lack of information & design guidelines Ceiling-Based Limited applicability to retrofit construction � System � Problems with applicable standards & codes Comparison � Problems with spillage and dirt entering underfloor plenum � Concerns of condensation and dehumidification problems Recommendation Conclusions Allison M Clarke 2002-2003 AE Senior Thesis 5
Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction System Components Existing Building Typical Floor & Systems Two 22,000 cfm AHU’s � Underfloor Air � 28 fan powered terminal boxes supply System perimeter � Static pressure sensors Ceiling-Based System � 22,500 sf Access floor panels � Passive & VAV floor diffusers Comparison Source: Tate Access Floors Recommendation Conclusions Typical Mechanical Room Section Allison M Clarke 2002-2003 AE Senior Thesis Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Construction Methods/Schedule Existing Building � Local Jurisdiction Code Requirements & Systems � Underfloor is a plenum Underfloor Air System � Supply Air Diffusers Ceiling-Based � Redundant installation System � Underfloor Air Space Comparison � Moisture concerns Recommendation � Above Ceiling Air Space Conclusions � Suspended ceiling not absolutely necessary Allison M Clarke 2002-2003 AE Senior Thesis 6
Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Construction Methods/Schedule Existing Building Typical Floor Schedule & Systems Underfloor Air System Ceiling-Based System Comparison Recommendation Conclusions 219 Work Days Allison M Clarke 2002-2003 AE Senior Thesis Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Construction Methods/Schedule Existing Building Tower Schedule & Systems Underfloor Air System Ceiling-Based System Comparison Recommendation Conclusions 289 Work Days Allison M Clarke 2002-2003 AE Senior Thesis 7
Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Energy Use Existing Building Typical Floor Design Loads & Systems Typical Floor Load Total Tower Load Underfloor Air (tons) (tons) System 60 720 Ceiling-Based System Design Load Distribution Comparison 8% OA Load (tons) 10% Recommendation Lighting Load 39% (tons) Equipment Load 14% Conclusions (tons) Envelope Load (tons) Occupant Load 29% (tons) Allison M Clarke 2002-2003 AE Senior Thesis Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Energy Use Existing Building Annual Energy Consumption & Systems � Binmaker Weather Data Underfloor Air � 3,120 hours System Ceiling-Based Typical Floor Total Tower System Total Ton-hours 58,446 701,352 Comparison Recommendation Conclusions Allison M Clarke 2002-2003 AE Senior Thesis 8
Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Cost Existing Building Construction Costs & Systems $ 13.66 per square foot $ 5,136,160 Tower Cost � Underfloor Air System Operating Costs Ceiling-Based � Energy Consumption 2,912,721 kWh System � Annual Cost $ 206,803 Comparison Lifecycle Cost Recommendation � 30 years $ 9,084,118 Conclusions Allison M Clarke 2002-2003 AE Senior Thesis Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Introduction Lessons Learned Existing Building � Moisture detection in underfloor plenum & Systems Underfloor Air � Outdoor air load oversized System � 20 cfm/occupant needed Ceiling-Based � 43 cfm/occupant used System � “Green” technology Comparison � Recognized by USGBC Recommendation Conclusions Allison M Clarke 2002-2003 AE Senior Thesis 9
Recommend
More recommend