Beechworth Sewer Project Update Presented by Misty Howard 7 October 2019
Agenda for tonight’s meeting Introductions • Recap of the problem being solved • New sewer main (pipeline) – recap and where we are up to • Final al align gnment in detai ail • Questions • Wastewater Treatment Plant Upgrade • Next Steps • Questions • 2
Beechworth Sewer Project Background The The Problem? • Infiltration results in sewer overflow and spill into Beechworth Historic Park. Wh What are we doing? g? • Increasing capacity of the sewer system to address environmental risks and provide for growth of the town. How? w? • › Increasing the size of the sewer main (pipeline) that transfers sewage to the WWTP; and › Upgrading the WWTP to treat the increased flows and load. 3
Pipeline
Pipeline background Beechworth’s sewer main runs through the Historic • Park (constructed 1967) Heavy rain events in 2016 led to a number of sewer • spills at the Church Street inlet EPA issued a Pollution Abatement Notice to North • East Water, requiring capital works solution Two preliminary options were identified – a large tank • at top of the Park or a new, larger pipeline North East Water commenced discussions with • stakeholders in late 2016 5
The Stakeholder Process ACTIO TION Indigo DELWP Council NEW Advise se Ad IEAC Parks Vic Cons nsul ult Inform rm DELW LWP: Department of Environment, Land, Water & Planning Beechw hworth h EPA EPA PA: Environment Protection Authority Communit ity IEAC AC: Indigo Environment Advisory Committee 6
Our engagement journey Detailed design complete & ready to present th Communit 4 th ity M y Meetin ing: to community st Comm 1 st mmunity Meet eeting: Results of MCA • Community values • rd Community M Old Chiltern Rd • 3 rd y Meet eeting: identified preferred option Review criteria & Regular email 2 prelim options • • Flora & fauna weightings for MCA • updates as T ank least preferred • presentation by Biosis project Met with IEAC • progressed Oct/Nov 2019 4 April 2017 Sept 2017 March 2018 20 April 2017 Oct 2017 September 2019 Nov 2016 Old ld C Chil iltern Rd Rd Walk T Thru: nd Communit 2 nd ity M y Meetin ing: Door K or Knoc ock – Old d Walked the proposed • Community values • Chilt iltern R Rd: alignment with residents workshopped Update residents • Submit Planning Construction methods • 3 pipeline options Clarify • • Permit discussed miscommunications application to Council 7
Options presented to community MULTI-CRITERIA ASSE SSESSM SSMENT OPT PTIO ION DESCRIPTIO ION RANK NKING ING New gravity-fed pipeline • 2 Additional pump stations • Malakoff Road & Historic Park Built mainly along Malakoff Rd • Route partially through Park • New ew p pip ipel elin ine • 1 1 Thro rough town n and nd O Old Chi hiltern Rd Rd • Old Chi hiltern Ro Road Ro Rout ute i is s along f fring nge of the he Park • New p pump ump st station r requi uired • 3 New gravity-fed pipeline • Historic Park No additional pump stations • New tank (3.5 million litre capacity) • 4 T ank at Church Street Below existing site in Church St • In Historic Park • 8
Final Alignment 9
What have we done since we last met? Since March 2018, we have: • Consulted with regulatory stakeholders – Indigo Shire Council, DELWP , Parks Vic, EPA • Completed preliminary designs • Gained Board endorsement for final alignment • Engaged external consultant to provide detailed design of pump station and pipeline • Internal review of detailed design • Commenced discussions with WWTP neighbours 10 10
Detailed Design Difficulties overlaying an aerial photograph on to a flat map – pipeline alignment on crown land not not private • property Churc rch Stre reet – new pump station within existing site, open trench • Last Street – open trench and backfill along road reserve • Sydne dney y Road – under bore • Old Chilt ltern n Road: • › Under bore › Follow utilities corridor and power lines Pine Trac ack: • › Under bore › Follow Parks Vic Management track › Avoid sharp bends 11 11
Next Steps Liaise with approval authorities (EPA, DELWP , Parks • Vic, Council) Submit Planning Permit to Council • Construction of Church St pump station February • 2020 Commence pipeline construction mid 2020 • Continue to inform the community and residents as • project progresses 12 12
Questions? 13 13
Wastewater Treatment Plant Upgrade
Background Built in 1960s • Located on McFeeters Road, 3.5km north- • west of Beechworth Consists of 3-step treatment process: • – primary anaerobic treatment lagoon – series of secondary lagoons – Final polishing prior to discharge 15 15
Purpose of Upgrade Increase capacity: • – Additional flows due to new sewer main capturing stormwater infiltration – Accommodate town growth Reduce risk of odours • Minimise noise • Maximise effluent reuse • 16 16
Upgrade design process Design addresses environmental and growth needs of community • Informed by regular meetings and discussions with neighbours for past 12 months • 2 independent consultant peer reviews of design • Will include: • – New inlet structure – New treatment process – new lagoons and aerators – Wet weather buffering 17 17
18 18
Next Steps Consultant has been engaged to develop a preliminary design • EPA Works Approval application November 2019 • Upgrades expected to commence in 2020 • Will continue to meet with neighbours on-site • 19 19
Questions 20 20