beechworth sewer project update
play

Beechworth Sewer Project Update Presented by Misty Howard 7 - PowerPoint PPT Presentation

Beechworth Sewer Project Update Presented by Misty Howard 7 October 2019 Agenda for tonights meeting Introductions Recap of the problem being solved New sewer main (pipeline) recap and where we are up to Final al align


  1. Beechworth Sewer Project Update Presented by Misty Howard 7 October 2019

  2. Agenda for tonight’s meeting Introductions • Recap of the problem being solved • New sewer main (pipeline) – recap and where we are up to • Final al align gnment in detai ail • Questions • Wastewater Treatment Plant Upgrade • Next Steps • Questions • 2

  3. Beechworth Sewer Project Background The The Problem? • Infiltration results in sewer overflow and spill into Beechworth Historic Park. Wh What are we doing? g? • Increasing capacity of the sewer system to address environmental risks and provide for growth of the town. How? w? • › Increasing the size of the sewer main (pipeline) that transfers sewage to the WWTP; and › Upgrading the WWTP to treat the increased flows and load. 3

  4. Pipeline

  5. Pipeline background Beechworth’s sewer main runs through the Historic • Park (constructed 1967) Heavy rain events in 2016 led to a number of sewer • spills at the Church Street inlet EPA issued a Pollution Abatement Notice to North • East Water, requiring capital works solution Two preliminary options were identified – a large tank • at top of the Park or a new, larger pipeline North East Water commenced discussions with • stakeholders in late 2016 5

  6. The Stakeholder Process ACTIO TION Indigo DELWP Council NEW Advise se Ad IEAC Parks Vic Cons nsul ult Inform rm DELW LWP: Department of Environment, Land, Water & Planning Beechw hworth h EPA EPA PA: Environment Protection Authority Communit ity IEAC AC: Indigo Environment Advisory Committee 6

  7. Our engagement journey Detailed design complete & ready to present th Communit 4 th ity M y Meetin ing: to community st Comm 1 st mmunity Meet eeting: Results of MCA • Community values • rd Community M Old Chiltern Rd • 3 rd y Meet eeting: identified preferred option Review criteria & Regular email 2 prelim options • • Flora & fauna weightings for MCA • updates as T ank least preferred • presentation by Biosis project Met with IEAC • progressed Oct/Nov 2019 4 April 2017 Sept 2017 March 2018 20 April 2017 Oct 2017 September 2019 Nov 2016 Old ld C Chil iltern Rd Rd Walk T Thru: nd Communit 2 nd ity M y Meetin ing: Door K or Knoc ock – Old d Walked the proposed • Community values • Chilt iltern R Rd: alignment with residents workshopped Update residents • Submit Planning Construction methods • 3 pipeline options Clarify • • Permit discussed miscommunications application to Council 7

  8. Options presented to community MULTI-CRITERIA ASSE SSESSM SSMENT OPT PTIO ION DESCRIPTIO ION RANK NKING ING New gravity-fed pipeline • 2 Additional pump stations • Malakoff Road & Historic Park Built mainly along Malakoff Rd • Route partially through Park • New ew p pip ipel elin ine • 1 1 Thro rough town n and nd O Old Chi hiltern Rd Rd • Old Chi hiltern Ro Road Ro Rout ute i is s along f fring nge of the he Park • New p pump ump st station r requi uired • 3 New gravity-fed pipeline • Historic Park No additional pump stations • New tank (3.5 million litre capacity) • 4 T ank at Church Street Below existing site in Church St • In Historic Park • 8

  9. Final Alignment 9

  10. What have we done since we last met? Since March 2018, we have: • Consulted with regulatory stakeholders – Indigo Shire Council, DELWP , Parks Vic, EPA • Completed preliminary designs • Gained Board endorsement for final alignment • Engaged external consultant to provide detailed design of pump station and pipeline • Internal review of detailed design • Commenced discussions with WWTP neighbours 10 10

  11. Detailed Design Difficulties overlaying an aerial photograph on to a flat map – pipeline alignment on crown land not not private • property Churc rch Stre reet – new pump station within existing site, open trench • Last Street – open trench and backfill along road reserve • Sydne dney y Road – under bore • Old Chilt ltern n Road: • › Under bore › Follow utilities corridor and power lines Pine Trac ack: • › Under bore › Follow Parks Vic Management track › Avoid sharp bends 11 11

  12. Next Steps Liaise with approval authorities (EPA, DELWP , Parks • Vic, Council) Submit Planning Permit to Council • Construction of Church St pump station February • 2020 Commence pipeline construction mid 2020 • Continue to inform the community and residents as • project progresses 12 12

  13. Questions? 13 13

  14. Wastewater Treatment Plant Upgrade

  15. Background Built in 1960s • Located on McFeeters Road, 3.5km north- • west of Beechworth Consists of 3-step treatment process: • – primary anaerobic treatment lagoon – series of secondary lagoons – Final polishing prior to discharge 15 15

  16. Purpose of Upgrade Increase capacity: • – Additional flows due to new sewer main capturing stormwater infiltration – Accommodate town growth Reduce risk of odours • Minimise noise • Maximise effluent reuse • 16 16

  17. Upgrade design process Design addresses environmental and growth needs of community • Informed by regular meetings and discussions with neighbours for past 12 months • 2 independent consultant peer reviews of design • Will include: • – New inlet structure – New treatment process – new lagoons and aerators – Wet weather buffering 17 17

  18. 18 18

  19. Next Steps Consultant has been engaged to develop a preliminary design • EPA Works Approval application November 2019 • Upgrades expected to commence in 2020 • Will continue to meet with neighbours on-site • 19 19

  20. Questions 20 20

Recommend


More recommend