Banedanmark Tenders, and upcoming projects in Banedanmark Senior Market Consultant Cathrine Carøe at Nordiska leverantörsdagen 2017.11.21 1
Find tenders at www.bane.dk – also in English https://uk.banedanmark.dk/Supplier/Procurement_-tender_-invoicing https://banedktenderplan.tricommerce.dk/#/list/incoming Online Tender Plan is updated – continuously. Find new tenders published at TED – (Tender Electronic Daily). Attend quarterly supplier dialogue – meetings. Attend market dialogue meetings – held in English. 2
Tender Plan Future, current and completed tenders at online Tender Plan Overview and description of each project in these 5 categories: Renewal & construction – Operations & maintenance – Technical advisory – Consulting – Goods and other services – What, where, when, who 3
Details in Tender Plan – also in English Subscribe to changes to the selected tender. Forward tender to others. Tender & project descriptions contact info, category, size of project 4
Budgets Projects for 1,64 Billion Euro (12,3 Billion DKK) 2018-2020. Annual maintenance of approx. 170 Million Euro (1,3 Billion DKK). Major track possessions for – works on tracks, platforms, and bridges: Projects in 2018. – Projects in 2019. – Projects in 2020. – Projects in 2021. – 5
Construction projects in 7,8 Billion DKK for 2019 and 2020 6
#467 Track renewal Høje Tåstrup-Roskilde Station Budget: +250 M DKK. When: 2019 Where: East Project: 10 km track renewal per track – (= 40 km). – Drainage. – 12 switches. – Station with works: Høje Tåstrup – Derived works, interlocking, and – adjustment of catenary system. 7
#467 Track renewal Cph-HT Station. Budget: 150 M DKK. When: 2020 Where: East Project: 18 km per track. – Station works. – Drainage. – Sleepers. – Ballast. – 27 switches. – Catenary. – 8
#468 Sporfornyelse Ringsted – Korsør Budget: +600 M DKK. When: 2019 Where: East Project: 22 km new track. – 36 km new sleepers. – 51 km ballast cleaning. – 32 km new sub layer. – 33 new switches. – 23 removal of switches. – New track layout. – 3 km drainage. – Track lowering on 8 different locations. – Earth issues at Tjæreby and Forlev. – Interlocking and catenary works due to track renewal. – 9
# Track renewal Fyn Budget: TBD When: 2019 Where: East Project: 22 km renewal of sleepers. – 39 km ballast cleaning. – 9 km renewal of sub layer. – 2 switches. – 1,3 km drainage. – 3,5 km replacement of track cable. – Associated works regarding catenary, interlocking and – ATC. 10
#121 Udskiftning køreledningsanlæg bane 82 Budget: 100 M DKK. When: 2019 Where: East Project: Renewal of the catenary system on the Urban – DC-Rail of Copenhagen. 46 km 1:1 replacement of the catenary system – between Holte and Østerport Station. The project includes replacement of approx. – 700 poles, and masts, wires. Derived works; equally bonding and power – supply cables The work is planned to be done in mostly train – free intervals of 4 hour duration during the night. 11
# Favrholm, new station south of Hillerød. Budget: 140 M DKK for the main proposal. Besides an Option. When: 2019 Where: East Project: The main proposal includes establising – an interchange station for S-banen and Frederiksværkbanen; 2 new side platforms at the existing – S-bane. 1 new platform at Frederiksværkbanen. – Establishment of access routes and – a forecourt with commuter parking. A proposal for compensating for – facilities that will be affected. 12
#473 (Hobro)-Aalborg. Budget: 200 M DKK. When: 2020 Where: West Project: 51 km track renewal. – 44 switches renewal + 27 closure – 65 km sleepers renewal. – 102 km ballast cleaning + some – sublayer. Drainage. – HS upgrading. – Moving track up to 1.5 meter sideways. – 13
# Track renewal Fredericia-Aarhus. Budget: 140 M DKK. When: 2020 Where: West Project: 45 km track renewal. – 10 km drainage. – 16 km renewal of sleepers. – 64 km ballast cleaning + some – sublayer 29 switches. – Catenary. – Interlocking. – ATC. – 14
# NF/SI/0275 Fixed Transmission Network (FTN) Passive Budget: DKK +100 mill. When: 2018- Where: Denmark - Project: - Renewal/redesign of FTN Passive infrastructure - Approx. 1,900 km. - Building supplies: Tubing ▪ Fiber optic cables ▪ Cable wells, ODF , etc. ▪ - Tender published on TED 18.th November 2017 15
# 2017-9130 Manuelle Spor. Budget: +100 M DKK. When: 2018-2020 Where: Denmark Project: Manual works on sleepers. – Manual works on rails. – Welding. – One contract divided into six lots. – Tender form; public tender with – actual costs. Tender deadline 11. December 2017. – Work March 2018-2019. – 16
# 2017-10787 Outsourcing of Forestry services. Budget: 20-50 M DKK When: 2018-2012 Where: Denmark Project: Forestry; manual and machine works – on greenery (cut and crush). Along 4,000 km track side. – Outsourcing Q4 2017. – One contract divided into three lots. – Contract type: actual costs. – Tender form is restricted invitation to – tender. Work from September to May. – 17
# Line tamping – outsourcing of maintenance. Budget: TBD When: 2019-2020 Where: Denmark Track analysis. – Ballast maintenance. – Line tamping 250 km per year for – 2-3 years Line tamping at stations. – Tender form to be decided. – Tender in Q1 2018. – 18