Enabling Works Update Area North – Fusion Carley Richards
Southam and Windmill Hill : Archaeology update • In late March, Fusion the HS2 Area Central Enabling Works Contractor, will start the archaeological investigation work. This will involve excavating trenches and recording any finds • The Southam site is located on the south-western outskirts : Access to the site will be along Leamington Road, Kineton Road and Banbury Road. • The Windmill Hill site will be accessed along Windmill Hill. • This work will be carried out by Connect, Fusion’s archaeology subcontractor. The investigations will be done by small teams of archaeologists assisted by an excavator. There will be a maximum of two teams on each site. • These works are scheduled to complete by the end of June 2020. • An Advanced Works Notice has been issued to the Community with further details for each site
Archaeological Trial Trench • Trial Trenches are undertaken at pre identified locations • Further investigation works are undertaken within the trial trench at encountered locations of interest • Archaeological works are then planned to investigate the area further based upon initial findings
Archaeological trial trench areas Southam
Archaeological trial trench areas – Windmill Hill
Fencing to the south of the B4451 Kineton Road • Works are due to commence in the area from the start of April 2020 until mid June • 8.5km of fencing required • A compound will be established utilising the former Cubbington Saw Mills site at Harp Farm, with direct access to the A423 Banbury Road • The fencing to be installed is typically stock proof fencing with agricultural gates • Public Rights of Way are incorporated into the design
Fencing to the north of the B4451 to the A425 • Works are due to commence in this area from late March to the end of April 2020 • 2km of fencing required • A compound will be established alongside the A425 Leamington Road. This site access is subject to highway authority approval • The fencing to be installed is typically stock proof fencing with agricultural gates • Public Rights of Way are incorporated into the design
Enabling Works Update Area North – LM Melanie Ryan Adam Brookes
Summary of LM current/future 4 works • TBM Utilities Works. (Detailed on next slide) Fosse • Way Long Itchington Compound Bellmouth construction. (1) • Long Itchington Compound Construction. 2 (2) 1 • Ridgeway Lane Widening. (3) • Fosse Way Highway Works & Compound (4) Welsh • Vegetation Clearance for access points Road 3 and for route of HS2. • Community Engagement events including local drop-ins, forums and parish council meetings • Notifications and news updates sent out via post and also put on to the HS2 commonplace website.
TBM Utilities Works • Installation of ducting along Bascote Road is ongoing and will be finished mid-March 2020. • Cabling works will follow after to duct installation has been completed. - By June 2020 • Welsh Road will close from mid- February to mid-March to allow for installation of 11kv cable. • Bascote Road will close from mid- February to mid-April to allow for installation of 11kv cable. • The B4452 will close from mid- March to mid-May to allow for installation of 11kv cable.
Long Itchington Compound and Ridgeway lane
Long Itchington Compound Spine Road and Compound Construction – Complete by Mar 2020 Bellmouth Construction- Completed re-opened dependent on TBM Supply works
Ridgeway Lane Widening Construct Ridgeway lane widening to facilitate TBM Access – Feb 2020 to June 2020 Construct New Pedestrian Crossing – April 2020
Fosse Way Highway Works Apr 20 – Sep 20 Construction of the northern Existing Fosse Way roundabout with utility works and tie ins to existing roads. Oct 20 – Mar 21 Construction of the southern roundabout along with utility The Dates shown are works and tie ins to existing subject to the design roads and coordination development
Ecological Mitigation
Cubbington March 19
Finham June 19
Hedgerow Planting Hibernacula Basking Banks
Main Works Update Area North – BBV Andy De Bell Gurcharan Singh
Main compounds What to expect First main compounds: • 6-months work to establish the compound Long Itchington Wood • We will erect hoardings / fencing around the Compound to ensure the site is safe and Occupancy from November 2019 • secure. Occupancy Date Main Office 11/20(BBV) • • There will be a nominal increase in vehicle movements during the delivery of equipment, machinery, materials and portacabins. Other significant main compounds: • Traffic arrangements to manage flows during Fosse Way construction and to receive deliveries . • • Utility works in and around the compound for A46 • the supply of water, electricity and Occupancy early 2020 • telecommunications. • Long Itchington wood: from March 2020 prep work will start on the north portal tunnel which Additional compounds will be set up during 2020 includes installation of plant equipment , grout and slurry plant. Overall, fewer compounds than allowed in the Environmental Statements
Long Itchington Wood Tunnel Main Compound Start occupancy from 03/19 Complete main office 11/20 North Portal Office setup Approx. 70 Staff and 170 Workforce Site Containing: Site Clearance ▪ Compound Fencing ▪ Access Roads ▪ Cadent Gas protection ▪ Utility supply water - comms - power ▪ Compound at North Portal ▪ EWC Scope: Site Clearance and Compound Fencing ▪ Access Roads ▪ Cadent Gas protection ▪ Utility supply water - comms - power ▪ Compound at North Portal ▪ Installation of balancing pond and ▪ outfall
LIWT – North Portal Const. Sequence
Programme of activity • First delivery of components for the Tunnel Boring machine(TBM) will be delivered to the compound from August 2020. • TBM initial delivery at North Portal using the A425 Leamington Road via the upgraded Ridgeway Lane to the compound. • TBM ready to bore from December 2020, with approximate one years of tunnelling to follow . • Breakthrough bore 1 at South Portal / Polo Club • TBM to be transferred fromSouth Portal to North Portal using the A425 Leamington Road. • About 12 week period to transport and reassembly the entireTBM back to launch. • Breakthrough bore 2 at South Portal/ Polo Club.
Sublot 2 – Fosse Way Compound Occupancy Date Temporary 04/20 Occupancy Date Main office 09/20 Approx. 57 Staff and 155 Workforce Site Containing: Main offices (with utilities) ▪ Installation of balancing pond and outfall ▪ Temporary Stockpiles ▪ Storage area ▪ New Roundabout ▪ Temporary Balancing Pond ▪ Sewage plant ▪ Early Works Contractor Current Scope: Site Clearance ▪ Part of the Working platform ▪ Compound Fencing ▪ Access Roads ▪ Utility supply water - comms - power ▪
Routes to Compound TBM delivery Operational deliveries
Routes to South Portal TBM delivery Operational deliveries
Ufton Roundabout Current View Post works View
A425 Leamington Road
Mass Haul Surplus Deficits Deficit Surplus Deficit
Main Works Update Area Central – EK Chris James
Heave Trial 3
Main Works Main Compound Possession in April • 4 months Fusion works • Site clearance, drainage • access road, Main compound •