A160 Port of Immingham Improvement Scheme Feb 2017 Craig Snow – Costain Contract Lead Richard Pickup - Jacobs Engineering Manager Tiago Magalhaes – Jacobs Geotech Site Representative
Introduction to A160 • Project Overview • Health and Safety • Project Delivery • Community and Society • BIM • Engineering Challenge • Geotechnical Challenges • Possession activities
PROJECT OVERVIEW
Project Overview 4
HEALTH AND SAFETY
SAFE WORKING 1,200,000 Man-hours worked Full project to date without a reportable accident
Health and Safety Environment Each other Empowerment
PROJECT DELIVERY
Statutory planning process • A160 Accelerated Delivery Planning Act 2008 Nationally Significant Infrastructure Project • Input • Prep Application • Legal Notices • Stats and Stakeholders • Represent at the Hearing 9
COMMUNITY AND SOCIETY IMPACT
Community and Society • Deep water Estuary – Land Development • STEM
Community and Society
BIM
Technology – Early Adopter BIM 3D 4D 6D 14
Embrace Technology Aerial Solutions – Digital Survey • 3D/4D Sequencing and Phasing
Technology – Early Adopter BIM FME – Feature Manipulation Engine
Interactive Stats Drawing
4D Animation – Bridge Slide 18
Longer Duration Planning 19
4D Animation – Cofferdam Construction 20
ENGINEERING CHALLENGE BRIDGE SLIDE
Bridge Slide
Bridge Slide
Bridge Slide
Strand Jacks 25
Catenary bridge 26
Possession Planning • Temp Works • Staff planning • Works Package Plans • RAMS • ITP’s • Detail Planning • Logistics • QSRA 27
Staff Planning 28
Video 1 – Bridge Construction 29
GEOTECHNICAL CHALLENGE
Ground Conditions • Glacial Till • Potential for granular lenses • High groundwater level 31
Ground Conditions Encountered – Soft Spots • Soft Spots – 5m x 4m and 10m x 3m • Groundwater at formation level • Excavate and replace with Class 6N Fill
Ground Conditions Encountered – Instability of Excavation • Collapse of Excavation Slopes • Bulk Fill – Telecomms Mast • Removal of loose material and Class 6N backfill
Ground Conditions Encountered - Mitigation • Monitoring Regime • 12No. Monitoring targets on bridge structure • 12No. Monitoring points on Backfill
POSSESSION ACTIVITIES
Lifting Rails 36
Excavation 37
Kingpost Wall Removal 38
Kingpost Wall Removal 39
Installation of Nosings & Final Trim 40
Jacking Operation 41
Strand Jacks 42
Checking Alignment 43
Backfill 44
Backfill 45
Track Replacement 46
Tamping the Ballast 47
Welding 48
GO PRO
THANK YOU
Recommend
More recommend