a160 port of immingham improvement scheme
play

A160 Port of Immingham Improvement Scheme Feb 2017 Craig Snow - PowerPoint PPT Presentation

A160 Port of Immingham Improvement Scheme Feb 2017 Craig Snow Costain Contract Lead Richard Pickup - Jacobs Engineering Manager Tiago Magalhaes Jacobs Geotech Site Representative Introduction to A160 Project Overview Health and


  1. A160 Port of Immingham Improvement Scheme Feb 2017 Craig Snow – Costain Contract Lead Richard Pickup - Jacobs Engineering Manager Tiago Magalhaes – Jacobs Geotech Site Representative

  2. Introduction to A160 • Project Overview • Health and Safety • Project Delivery • Community and Society • BIM • Engineering Challenge • Geotechnical Challenges • Possession activities

  3. PROJECT OVERVIEW

  4. Project Overview 4

  5. HEALTH AND SAFETY

  6. SAFE WORKING 1,200,000 Man-hours worked Full project to date without a reportable accident

  7. Health and Safety Environment Each other Empowerment

  8. PROJECT DELIVERY

  9. Statutory planning process • A160 Accelerated Delivery Planning Act 2008 Nationally Significant Infrastructure Project • Input • Prep Application • Legal Notices • Stats and Stakeholders • Represent at the Hearing 9

  10. COMMUNITY AND SOCIETY IMPACT

  11. Community and Society • Deep water Estuary – Land Development • STEM

  12. Community and Society

  13. BIM

  14. Technology – Early Adopter BIM 3D 4D 6D 14

  15. Embrace Technology Aerial Solutions – Digital Survey • 3D/4D Sequencing and Phasing

  16. Technology – Early Adopter BIM FME – Feature Manipulation Engine

  17. Interactive Stats Drawing

  18. 4D Animation – Bridge Slide 18

  19. Longer Duration Planning 19

  20. 4D Animation – Cofferdam Construction 20

  21. ENGINEERING CHALLENGE BRIDGE SLIDE

  22. Bridge Slide

  23. Bridge Slide

  24. Bridge Slide

  25. Strand Jacks 25

  26. Catenary bridge 26

  27. Possession Planning • Temp Works • Staff planning • Works Package Plans • RAMS • ITP’s • Detail Planning • Logistics • QSRA 27

  28. Staff Planning 28

  29. Video 1 – Bridge Construction 29

  30. GEOTECHNICAL CHALLENGE

  31. Ground Conditions • Glacial Till • Potential for granular lenses • High groundwater level 31

  32. Ground Conditions Encountered – Soft Spots • Soft Spots – 5m x 4m and 10m x 3m • Groundwater at formation level • Excavate and replace with Class 6N Fill

  33. Ground Conditions Encountered – Instability of Excavation • Collapse of Excavation Slopes • Bulk Fill – Telecomms Mast • Removal of loose material and Class 6N backfill

  34. Ground Conditions Encountered - Mitigation • Monitoring Regime • 12No. Monitoring targets on bridge structure • 12No. Monitoring points on Backfill

  35. POSSESSION ACTIVITIES

  36. Lifting Rails 36

  37. Excavation 37

  38. Kingpost Wall Removal 38

  39. Kingpost Wall Removal 39

  40. Installation of Nosings & Final Trim 40

  41. Jacking Operation 41

  42. Strand Jacks 42

  43. Checking Alignment 43

  44. Backfill 44

  45. Backfill 45

  46. Track Replacement 46

  47. Tamping the Ballast 47

  48. Welding 48

  49. GO PRO

  50. THANK YOU

Recommend


More recommend