your future campus
play

YOUR FUTURE CAMPUS OPEN SPACE + COMMUNITY INTEGRATION A range - PowerPoint PPT Presentation

YOUR FUTURE CAMPUS OPEN SPACE + COMMUNITY INTEGRATION A range of spaces: from active plazas to natural contemplative areas Opportunities for the public as well as the campus community Plaza Amphitheater Recreation Field


  1. YOUR FUTURE CAMPUS OPEN SPACE + COMMUNITY INTEGRATION • A range of spaces: from active plazas to natural contemplative areas • Opportunities for the public as well as the campus community Plaza Amphitheater Recreation Field Innovation District Informal Recreation Active Recreation Hiking/Biking Trails Refmective Space Key Campus Art Opportunity Key Outdoor Performance Space Key Outdoor Social Space Early Learning Center

  2. NET ZERO GOALS ENERGY WASTE WATER • Passive Building Design • Social and Tech Solutions • Low water volume plumbing fjxtures • Solar Panels • Per Capita Goals • Reuse of non-potable water • Effjcient Lighting • Recycling, Compost, Trash • Native landscaping • Geoexchange Sorting Stations

  3. PHASE 1A CAMPUS INFRASTRUCTURE SYSTEMS SUMMER 2019-2021 • Pumped Sewer • Condenser Lines • Water Mains • Storm Water Management • Amphitheater • Gravity Sewer • Data Conduits ACADEMIC • Curb/Gutter BUILDING 2 • Sidewalks • Oval Green • Electrical Conduits • Parking • Streets

  4. INVESTING IN CITY TRANSPORTATION INFRASTRUCTURE New Simpson Ave. pedestrian/bike path to Century Dr. New roundabout at SW Colorado Ave. and Columbia St.

  5. COMING FALL 2021 ACADEMIC BUILDING 2 FEATURES • 50,000 sq. ft. • 10 Classrooms • 2 Flex Labs • Clinical Skills and Treatment Classrooms • Makers Spaces for Media, Engineering, Outdoor Products • Capstone Project Space • Event Space • Study Space

  6. 30,000 TRUCK TRIPS SAVED Estimated one-way truck trips saved during campus development Phase 1A as a result of landfill reclamation. Maul Foster & Alongi 2017 landfill reclamation study. 1,000 = TRIPS

  7. SW SIMPSON AVE PHASE 1 PHASE 1 (6.2 ACRES) REMEDIATION (10.3 ACRES) AREA 3 PHASE 1 AREA 1 RELOCATED MT WASHINGTON DR WASTE FUTURE PHASE RELOCATED WASTE FUTURE PHASE AREA 2 REMEDIATION SW CENTURY DR (23.2 ACRES) PHASE 1 RECLAMATION SW CHANDLER AVE (44.2 ACres) REMEDIATION & RECLAMATION PHASING OREGON STATE UNIVERSITY - CASCADES

  8. SW SIMPSON AVE AREA 3 - 39.4 AC WASTE = 838,000 CY COVER SOIL = 245,900 CY MT WASHINGTON DR AREA 1 - 23.2 AC CONSTRUCTION & WASTE = 1,133,500 CY DEMOLITION DEBRIS LANDFILL AREA 2 - 10.3 AC COVER SOIL = 258,000 CY SW CENTURY DR WASTE = 456,000 CY COVER SOIL = 24,000 CY PUMICE MINE (44.2 AC) SW CHANDLER AVE EXISTING CONDITIONS OREGON STATE UNIVERSITY - CASCADES