work in progress
play

WORK IN PROGRESS August 2011 Masonry and Concrete Improvements - PowerPoint PPT Presentation

A UBURN S CHOOL D ISTRICT N O . 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS August 2011 Masonry and Concrete Improvements Status: Contractor: Pioneer Masonry Restoration Inc., Seattle WA. Construction contract: $87,931 Work


  1. A UBURN S CHOOL D ISTRICT N O . 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS August 2011

  2. Masonry and Concrete Improvements Status: • Contractor: Pioneer Masonry Restoration Inc., Seattle WA. • Construction contract: $87,931 • Work being performed at eight facilities. • The work is substantially complete. School sign being rebuilt at Hazelwood Elementary School.

  3. Masonry and Concrete Improvements Existing mortar at top of concrete New mortar bearing pad at top of column at Cascade Middle School. concrete column at Cascade Middle School.

  4. Masonry and Concrete Improvements Removal of deteriorated mortar joints at the Pioneer Elementary School playshed.

  5. Masonry and Concrete Improvements Mortar joint removal at the Pioneer Elementary School chimney.

  6. Masonry and Concrete Improvements Filling mortar joints at the upper walls of Pioneer Elementary School gymnasium.

  7. Masonry and Concrete Improvements Mortar joint restoration at Pioneer Elementary School.

  8. Energy Improvements Status: • Design / Build Contractor: Ameresco Quantum, Inc, Renton, WA under an ESCO (Energy Service Company) contract. • ESCO contract: $2,273,646 with partial funding from a $1,300,000 grant from OSPI. • Work being performed at 11 facilities and includes lighting, plumbing, irrigation system, and mechanical equipment upgrades. New lighting at classroom at Lake View Elementary • Project 95% complete. School.

  9. Energy Improvements New low-flow toilet fixtures at Rainier Middle School.

  10. Energy Improvements New air handling unit being lifted onto roof at Alpac Elementary School.

  11. Energy Improvements New heat pump chillers at Rainier Middle School.

  12. Hazelwood Elementary and Rainier Middle Schools Modernization Status: • Contractor: Lincoln Construction, Inc., Spanaway WA. • Construction contract: $1,796,800. • Work includes architectural, food service, mechanical and electrical improvements at Hazelwood Elementary and Rainier Middle Schools. • Project is 80% complete. New hot water heaters at Hazelwood Elementary School.

  13. Hazelwood Elementary and Rainier Middle Schools Modernization New fire sprinkler system at Hazelwood Elementary School.

  14. Hazelwood Elementary and Rainier Middle Schools Modernization New ramp for disabled access to stage at Hazelwood Elementary School.

  15. Hazelwood Elementary and Rainier Middle Schools Modernization Wall framing at Storage Room addition at Rainier Middle School.

  16. Hazelwood Elementary and Rainier Middle Schools Modernization Concrete floor patch where new electrical conduit was installed for computer lab in Library at Rainier Middle School.

  17. Hazelwood Elementary and Rainier Middle Schools Modernization New carpeting in main office at Rainier Middle School.

  18. Hazelwood Elementary and Rainier Middle Schools Modernization Installation of new sound system in Main Gym at Rainier Middle School.

  19. Hazelwood Elementary and Rainier Middle Schools Modernization Installation of new roof shingles at Rainier Middle School.

  20. Hazelwood Elementary and Rainier Middle Schools Modernization Roof at Rainier Middle School with new shingles.

  21. Pool and Stadium Improvements Status: • Contractor: Jones & Roberts Company, Olympia WA. • Construction contract: $2,369,500. • Work includes a new building addition and modernization of Auburn Pool; and miscellaneous improvements at Auburn Memorial Stadium. • Project is 90% complete. Installation of new sound system at Auburn Memorial Stadium.

  22. Pool and Stadium Improvements New discus throw pad at Auburn Memorial Stadium.

  23. Pool and Stadium Improvements Storage room and mechanical room addition at Auburn Pool.

  24. Pool and Stadium Improvements Work being done to improve the electrical system at Auburn Pool.

  25. Pool and Stadium Improvements New cabinets in staff area at Auburn Pool.

  26. Pool and Stadium Improvements New overhead ductwork at Auburn Pool.

  27. Pool and Stadium Improvements New pool surface material being installed at shallow end of Auburn Pool.

  28. Pool and Stadium Improvements Installation of new pool surface material at Auburn Pool.

  29. Pool and Stadium Improvements Auburn Pool filled with water that is being filtered and cleaned.

  30. Auburn High School Modernization and Reconstruction Status: • Architect: NAC Architecture, Seattle WA. • Estimated Construction Cost: $76,000,000. • Work includes replacement of existing buildings except Auto Shop and PAC. Auto Shop, PAC and site will be modernized. • Work continues on soil investigations, utility surveying, and review of Drawing of existing sanitary sewer lines at Auburn High Design Development School. documents.

  31. Auburn High School Modernization and Reconstruction Ground penetrating radar equipment being assembled for use in identifying the depth of underground pipes.

  32. Auburn High School Modernization and Reconstruction Ground penetrating radar being used to identify the depth of underground pipes at Auburn High School.

  33. Auburn High School Modernization and Reconstruction Underground utility investigations at East Main Street.

  34. Auburn High School Modernization and Reconstruction Preparation for film interview for the project information video.

  35. Auburn High School Modernization and Reconstruction Film interview for the project information video.

  36. Auburn High School Modernization and Reconstruction Design development drawing being reviewed by the Capital Projects Department.