winner
play

WINNER http://communitymeeting.ocps.net/ Site 205-K8-SW-6 40% - PowerPoint PPT Presentation

Orange County Public Schools Welcome! Please sign in on your mobile device: WINNER http://communitymeeting.ocps.net/ Site 205-K8-SW-6 40% Construction Community Meeting September 25, 2017 1 Orange County Public Schools Orange County Public


  1. Orange County Public Schools Welcome! Please sign in on your mobile device: WINNER http://communitymeeting.ocps.net/ Site 205-K8-SW-6 40% Construction Community Meeting September 25, 2017 1

  2. Orange County Public Schools Orange County Public Schools Site 205-K8-SW-6 40% Construction Meeting Agenda September 25, 2017 – 6:00pm – Kaley-Lake Como Elementary Cafeteria • Welcome – School Board Member Nancy Robbinson • Introductions • Project Update – Architect: Harvard Jolly Architects Construction Manager: Williams Company • Questions and Answers • Adjournment 2

  3. Orange County Public Schools N Lake Como ES Aerial 3

  4. Orange County Public Schools Project Data Capacity Gore St 1,335 Student Stations Building Area 161,762 Gross SF Media Center Admin Gym Parking Provided Art Music 136 Spaces Parent Pick Up/Drop Off 15 Ft Buffer Courtyard Multi Lockers Car Queuing Provided Purpose Bus Loop Bumby Ave 132 Cars Kitchen Site Area CEP +/- 12 Acre 3-Story Classroom Bldg Tot Future Portables Youth Soccer Field/6 Lane Track Hardcourt Baseball Field Stormwater Exfiltration N Beneath Field Master Site Plan 15 Ft Buffer 4

  5. Orange County Public Schools View from Gore St 5

  6. Orange County Public Schools Bird’s -Eye from Gore Street 6

  7. Orange County Public Schools Bird’s -Eye from Bumby Ave 7

  8. Orange County Public Schools Construction Update and Milestones  Notice to Proceed (NTP) was issued February 7, 2017.  Tilt wall panels were completed on June 30, 2017.  Structural Steel Erection was completed on July 24, 2017.  Roofing work has started and will be completed by October 13, 2017  Window installation started and will be completed by September 30, 2017  Exterior painting to start mid-October.  Interior work is in progress.  Project will be 40% complete as of September 30, 2017.  Project remains on schedule for Substantial Completion on May 14, 2018. 8

  9. Orange County Public Schools Aerial Photo- Late January 2017 9

  10. Orange County Public Schools Aerial Photo- Late April 2017 10

  11. Orange County Public Schools Aerial Photo- Late May 2017 11

  12. Orange County Public Schools Aerial Photo- Late July 2017 12

  13. Orange County Public Schools Aerial Photo- Late August 2017 13

  14. Orange County Public Schools Aerial Photo- Late September 2017 14

  15. Orange County Public Schools Tilt Panel Rebar Slab On Grade Pour 15

  16. Orange County Public Schools Tilt Panel Erection Steel Erection 16

  17. Orange County Public Schools Lightweight Installation Roofing Installation 17

  18. Orange County Public Schools QUESTIONS? 18

Recommend


More recommend