unit 11 contract administration ending the contract and
play

Unit 11: Contract Administration: Ending the Contract and - PowerPoint PPT Presentation

...last week (or things you should now understand) Claims for loss and/or expense Claim submission procedure Claim assessment procedure Heads of Claims 1 Image: Endemoniada on flickr. Some rights reserved. Unit 11: Contract


  1. ...last week (or things you should now understand) • Claims for loss and/or expense • Claim submission procedure • Claim assessment procedure • “Heads of Claims” 1

  2. Image: Endemoniada on flickr. Some rights reserved. Unit 11: Contract Administration: Ending the Contract and Subcontractors D39PZ: Procurement and Contracts 2

  3. 1. Ending a construction contract 2. Remedies 3. Subcontractors and suppliers 4. Transferring rights and obligations to another party 5. Third party rights and collateral warranties D39PZ: Procurement and Contracts 3

  4. Ending a construction contract (1) Frustration/impossbility • Frustration arises when a party is unable to fulfil its obligations under the Contract, but is not in breach • Frustration occurs without the liability of either party • Circumstances change, preventing the project from being completed • Frustration typically occurs in two ways:  Supervening illegality o legislation may outlaw the Works  Supervening impossibility: o the site may no longer exist (landslip, flooding). D39PZ: Procurement and Contracts 4

  5. Ending a construction contract (2) Termination • Section 8 of SBC/Q governs Termination  Defines the processes that parties must follow to “determine” the Contract - i.e. bring it to an end • Termination does not completely end the Contract  After termination: o Principal obligations can no longer be enforced e.g. Contractor no longer obliged to complete the Works; Employer no longer obliged to pay for the Works. o Remaining obligations continue to have effect e.g. Dispute resolution methods continue to exist D39PZ: Procurement and Contracts 5

  6. Termination by the Employer • The Employer can terminate the Contract if: (i) the Contractor defaults (cl. 8.4); “Specified defaults” are defined by cls. 8.4.1.1 to 8.4.1.5 o o Employer must provide notice of intent to terminate Contractor due to default (cl. 8.4.2) o Contractor has 14 days to correct the default o If not done, Employer can terminate within 21 days (cl. 8.4.2). o Employer must send a final notice that Contract is determined (ii) the Contractor becomes insolvent (cl. 8.5) o The Contractor is automatically terminated if it applies for bankruptcy, liquidation or receivership o The Contractor must notify the Employer if this occurs (cl. 8.5.2) o The Employer must still notify the Contractor that the Contract has been determined (cl. 8.5.1) o The Contractor can be reinstated if terms can be agreed with the liquidator (cl. 8.3.2) (iii) the Contractor commits acts of corruption (cl. 8.6) D39PZ: Procurement and Contracts 6

  7. Termination by the Employer • Consequences of termination under cl. 8.4, 8.5 and 8.6: o The Employer may employ another Contractor to complete the Works (cl. 8.7.1) o The new Contractor can use all tools and plant left on site (if the Employer did not request their removal under cl. 8.7.2.1) o Any unwanted equipment left on site by the insolvent Contractor can be sold by the Employer o The Employer must give any profit to the insolvent Contractor The original Contractor’s subcontracts may be assigned to the o Employer o An insolvent Contractor is not entitled to further payment until the Works are completed.  The Employer’s direct loss and expense incurred as a consequence of appointing a replacement Contractor will be deducted from any payment due (cl. 8.7.4.1)  If these costs exceed the payment due, the insolvent Contractor will owe the difference to the Employer (cl. 8.7.5)  Cl. 8.8 governs the payment of any outstanding sums if the Employer D39PZ: Procurement and Contracts 7 does not continue with the Works after terminating the insolvent Contractor

  8. Termination by the Contractor • The Contractor can terminate the Contract if: (i) the Employer defaults (cl. 8.9); or o The Contractor can determine its own employment under the Contract if:  the Employer causes certain “specified defaults” (cl. 8.9.1); or  certain “specified suspension events” arise (cl. 8.9.2). The Contractor’s notification procedure mirrors the Employer's o (cls. 8.9.1; 8.9.2; 8.9.3). (ii) the Employer becomes insolvent (cl. 8.10) o The Contractor can determine the Contract if the Employer become insolvent. Cl. 8.10 defines the Contractor’s procedure, and mirrors cl. 8.5, o which the Employer must follow to determine the Contractor. The definition of “insolvency” provided by cl. 8.1 dictates when o the Employer or the Contractor can determine the Contract D39PZ: Procurement and Contracts 8

  9. Termination by Employer or Contractor • Cl. 8.11 governs determination of the Contract by either party • Cl. 8.11.1 defines the events that can cause either party to determine the Contract  These are events that frustrate the Contract.  Neither party is liable for causing them e.g. supervening illegality or supervening impossibility make it impossible to complete the Works. D39PZ: Procurement and Contracts 9

  10. Ending a construction contract Remedies Subcontractors and suppliers Transferring rights and obligations to another party Third party rights and collateral warranties D39PZ: Procurement and Contracts 10

  11. Remedies A remedy is the device provided by the Contract to compensate an innocent party for the loss or expense it incurs as a consequence of the other party’s breach. (1) Rescission • In certain circumstances, a material breach of contract by one party may entitle the other party (the innocent party) to terminate the contract • If the breach constitutes a repudiation of the contract, the innocent party has a choice o They can accept the repudiation and rescind the contract or o alternatively they may elect to ignore the repudiation and continue with the performance of the contract D39PZ: Procurement and Contracts 11

  12. (2) Specific implement or damages?  Allows the innocent party to compel the party in breach to fulfil its obligations  Only possible when the innocent party must be able to insist on the Works being completed  It is seldom possible to prove this requirement, causing most remedies to be in the form of damages. D39PZ: Procurement and Contracts 12

  13. (3) Interest • Late payment of sums is a common thing in the construction industry • One way in which this has been addressed is by way of interest • The entitlement to interest in respect of interim certificates is dealt with by Clause 4.12.6 – in addition to the amount not properly paid – simple interest thereon for the period until the payment is made • Clause 4.15.7 makes similar provisions in respect of sums due under a final certificate D39PZ: Procurement and Contracts 13

  14. (4) Interdict • Where a legal wrong is continuing or it is reasonably anticipated that such a wrong will be committed, innocent party is entitled to seek interdict against the wrong D39PZ: Procurement and Contracts 14

  15. (5) Withholding payment • Construction Act 2009 clearly defines the circumstances in which payment due under a construction contract can be withheld. • Before withholding payment, a party intending to do so must give notice of this intention to withhold payment, sating:  the amounts that will be withheld; and  the grounds justifying each withholding • Cl. 4.12 and 4.13 defines the process the Employer must follow if intending to deduct from the amount due under an Interim Certificate D39PZ: Procurement and Contracts 15

  16. (6) Suspending performance • The Construction Act 2009 clearly gives a party the right to suspend work if:  payment has not been made by the final date for payment; and  notice explaining why payment is being withheld has not been received • The Contractor’s statutory right of suspension is accommodated by cl. 4.14 in SBC/Q. D39PZ: Procurement and Contracts 16

  17. (7) Recourse under delict (tort) • A party can owe a duty to another in the absence of a contract • In construction, liability under delict is most likely to arise due to negligence  All other possibilities are governed by standard contracts • A claim for recompense under delict requires:  a duty of care to not be fulfilled; and  the innocent party to suffer loss D39PZ: Procurement and Contracts 17

  18. Ending a construction contract Remedies Subcontractors and suppliers Transferring rights and obligations to another party Third party rights and collateral warranties D39PZ: Procurement and Contracts 18

  19. Vicarious performance • “delegated” or “taking the place of another” Vicarious = • Vicarious performance = a new party other than that in the Contract fulfilling the Contracted party’s obligations  The contracted party remains liable/legally responsible for the new party’s performance • Vicarious performance is only possible for “impersonal” obligations (obligation which would not be considered “ personal ”)  Any obligations requiring specific skills of the contracted party can not be performed vicariously • In construction contracts, the principal of vicarious performance is more commonly know as ‘sub - letting’ D39PZ: Procurement and Contracts 19

Recommend


More recommend