unit 7 contract administration instructing certifying
play

Unit 7: Contract Administration: Instructing & Certifying - PowerPoint PPT Presentation

...last week (or things you should now understand) Structure of the JCT Standard Building Contract With Quantities (SBC/Q) 2011 Purpose of each part of JCT SBC/Q 2011 Required contents of the Contract Documents Employers


  1. ...last week (or things you should now understand) • Structure of the JCT Standard Building Contract With Quantities (SBC/Q) 2011 • Purpose of each part of JCT SBC/Q 2011 • Required contents of the Contract Documents • Employer’s obligations JCT SBC/Q 2011 • Contractor’s obligations under JCT SBC/Q 2011 • The contractual role of the Employer’s “agents;” who they are; and the Employer’s liability arising from their action (or inaction). • Clerk of Works’ Directions D39PZ: Procurement and Contracts 1

  2. Unit 7: Contract Administration: Instructing & Certifying D39PZ: Procurement and Contracts 2

  3. • Contract Administrator’s role • Contract Administrator’s instructions • Instructions vs. Variations • Certification • Certificates governing money • Certificates noting events (or non-events) • Key events in project progression D39PZ: Procurement and Contracts 3

  4. CA’s role • The CA applies (“administers”) the contract to the project • The CA issues formal documents (Clause 1.8), which serve a contractual purpose, e.g.:  tell others to do / not do something  update documents to reflect a change in the agreement  tell others to make payments  signify key events  make judgments about progress, completion, breach • These formal documents comprise: Instructions; Variations; Notices; and Certificates D39PZ: Procurement and Contracts 4

  5. CA’s role • To direct the Contractor in the completion of the Works e.g. identifying and responding to work “not in  accordance” • To stimulate payment from Employer to Contractor  e.g. by regular issue of Interim Certificates • To denote achievement (or otherwise) of a planned event e.g. does the CA think the Works are “practically  complete?” D39PZ: Procurement and Contracts 5

  6. • Contract Administrator’s role • Contract Administrator’s instructions • Instructions vs. Variations • Certification • Certificates governing money • Certificates noting events (or non-events) • Key events in project progression D39PZ: Procurement and Contracts 6

  7. CA’s instructions • Traditionally called “Architect’s instructions” (or “A.I.s”)  Now that any suitable organisation can adopt the Contract Administrator role, instructions are also called “Contract Administrator’s instructions” • The purpose of an instruction is to direct the Contractor’s work. An instruction may:  require site practice to be changed  require the Contractor to correct its mistakes  vary the definition of the Works - i.e. issue a “Variation” (‘Variation’ is an alteration of the Contract Document) • To achieve this, Contract Administrator’s Instructions are issued by the CA to Employer (Clause 1.8) D39PZ: Procurement and Contracts 7

  8. CA’s powers to instruct • The CA can only issue instructions where allowed by JCT SBC/Q 2011 • All instructions must be in writing (cl. 3.12.1)  Verbal instructions must be confirmed in writing within 7 days, or  Contractor’s written acceptance of a verbal instruction becomes a CA’s instruction if a CA’s instruction is not issued within 7 days of the Contractor’s acceptance D39PZ: Procurement and Contracts 8

  9. CA’s powers to instruct • A Variation is required cl. 3.14 • The Works are to be postponed cl. 3.15 • A Provisional Sum is to be spent cl. 3.16 • Inspection of the Works is required cl. 3.17 • Work not in accordance must be corrected cl. 3.18 • Workmanship not in accordance must be corrected cl. 3.19 • The work is otherwise not satisfactory cl. 3.20 • A person is to be excluded from the site cl. 3.21 • Antiquities have been discovered cl. 3.22 D39PZ: Procurement and Contracts 9

  10. Contractor’s right to query instructions • The Contractor has the right to “reasonably object” to an instruction if:  the Contractor believes the CA cannot issue it, or has done so in error  it would change the working conditions as given in clause cl. 5.1.2 under which the Works are to be completed (cl. 3.10.1) • The Contractor can ask the CA to prove that it has the right to issue the instruction (cl. 3.13)  The CA must notify Contractor of the SBC/Q provision that empowers the instruction “forthwith” D39PZ: Procurement and Contracts 10

  11. CA’s instruction D39PZ: Procurement and Contracts 11

  12. D39PZ: Procurement and Contracts 12

  13. D39PZ: Procurement and Contracts 13

  14. • Contract Administrator’s role • Contract Administrator’s instructions • Instructions vs. Variations • Certification • Certificates governing money • Certificates noting events (or non-events) • Key events in project progression D39PZ: Procurement and Contracts 14

  15. CA’s instructions vs. Variations • The distinction between an instruction and a Variation is critical . • Some, but not all, CA instructions are also Variations  Variations change the Contract Documents  Variations, therefore, update the express agreement between Employer and Contractor. • Variations – clause 5.1.1 and 5.1.2 D39PZ: Procurement and Contracts 15

  16. CA’s instructions vs. Variations • A Variation results in a change to the Works or the conditions in which the Works are to be completed • Such instructions create an opportunity for the Contractor to recover the cost of this change work or change in the manner by which the work must be completed • Variations are generally required because:  Employer changes makes a design change during the construction phase of the work  If a mistake or omission is discovered in the Contract Documents  Overcome unforeseen problems D39PZ: Procurement and Contracts 16

  17. CA’s instructions vs. Variations • An instruction is used to communicate a Variation to the Contractor • Therefore, all Variations are formally documented as instructions but not all instructions are variations • Can the Contract Administrator issue an instruction requiring a Variation after the issue of the Practical Completion Certificate?  Clause 2.38 allows the Contract Administrator to issue Instructions for the rectification of materials and workmanship defects but is unclear on the rectification of design defects D39PZ: Procurement and Contracts 17

  18. • Contract Administrator’s role • Contract Administrator’s instructions • Instructions vs. Variations • Certification • Certificates governing money • Certificates noting events (or non-events) • Key events in project progression D39PZ: Procurement and Contracts 18

  19. Duties of certifiers • The certifier (i.e. CA) is a named individual or firm • The CA brings specific professional expertise to the situation • The CA cannot, therefore, sublet their role • The CA is an agent of the Employer  The CA must act fairly, independently, and honestly • In its certifying role, the CA issues certain Certificates in response to events  A Certificate is not the same as an instruction D39PZ: Procurement and Contracts 19

  20. Requirements of a certificate • Certificates document achievement or occurrence of key events in a project • Certificates must:  leave no doubt as to their content and consequences  be issued when required by the Contract  be issued in accordance with the procedure defined by the Contract  be issued by the correct party  be issued to the correct party • The CA must issue the Contractor all Certificates at the same time as they are being sent to the Employer ( cl. 1.8 ). D39PZ: Procurement and Contracts 20

  21. • Contract Administrator’s role • Contract Administrator’s instructions • Instructions vs. Variations • Certification • Certificates governing money • Certificates noting events (or non-events) • Key events in project progression D39PZ: Procurement and Contracts 21

  22. Interim Certificates • Create a payment mechanism that allows the Contractor to be paid for the Works as they progress  There is no equivalent under common law  It is therefore important that SBC/Q is properly executed • Issued by CA regularly as the Works are being constructed • Oblige the Employer to pay the Contractor for Works completed in the last valuation period • Interim Certificates are the mechanism used to regulate  the timing of interim payments (frequency of issue defined in Contract Particulars. Default is one Interim Certificate every month. Governed by Clause 4.9.1)  The amount of such interim or instalment payments (governed by Cl. 4.9.2). D39PZ: Procurement and Contracts 22

  23. Interim Certificates • Interim certificates are issued in accordance with clause 4.9.1, leading to payments to the Contractor  as valued by the Quantity Surveyor under clauses 4.9.2, 4.10.2, 4.12. 4.13  and/or as applied for by the Contractor under Clause 4.11.1 • The Contract Sum often requires to be changed during the progress of the Works  Cl. 4.4 governs how this is done  The current Contract Sum is defined in each Interim Certificate • Cl. 4.12.1 obliges the Employer to pay the Contractor the amount stated as due on each Interim Certificate within 14 days from its due date. D39PZ: Procurement and Contracts 23

Recommend


More recommend