Tradebe Inutec Activities Presentation to WSSG – 3 November 2015
Current Area Leased by Tradebe Inutec
Licensing and Permitting Status Activity 2014 2015 2016 2017 Nuclear Site Licence Application Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Step 1 - Prepare to be a licensable site Step 2 - Collation of licence application dossier Step 3a - Initial licence application - ONR initial review and advise TI on revisions and timescales - TI revise and resubmit documentation pack Step 4a - ONR assesment of application Step 4b - Consultation by ONR - Finalisation of documentation for licence Step 5 - ONR grant Licence to Inutec Ltd Magnox Nuclear Site Licence Application for variation - Magnox Ltd (formerly RSRL) prepare and submitt Winfrith Relicensing - ONR assessment of submission - Finalisation of documentation for licence - Winfrith Relicensed to MXL excluding Inutec Ltd area
Freehold Acquisition Status Discussions progressing well with the NDA regarding the aquisition of the current area of land under tenant (leasing) arrangements and some additional land Further discussions have been held with the Home and Communities Agency (HCA) about securing long term vehicle access for Tradebe Inutec through the Dorset Green Site Programme remains on target to finalise the freehold contract in advance of the granting on the Nuclear Site Licence which is programmed for early 2017
Safety Performance 2015 We hold a 2015 RoSPA (Royal Society for the Prevention of Accidents) Presidents Award which recognises 12 consecutive years of RoSPA Gold Awards No RIDDOR reportable injuries or accidents for over 8 years One lost time accident (LTA) in 2015, one day due to a knee injury Staff minor injuries this year to date remains low, four in total We have recently made an appointed to a new post of Safety, Health, Environment and Quality Manager
Recommend
More recommend