Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P.E.– WisDOT Project Leader May 16, 2017
Review purpose and needs for the project Identify alternatives (solutions) to address the needs Discuss next steps 2
3
Regional and local traffic Approximately 3,700 vehicles per day 16% trucks Constructed in 1998 Existing asphalt 8 inches thick asphalt 24 crashes in 5 year period Run-off-the-road crashes present Ice and snow primary factors 4
Purpose Maximize the life of the pavement Improve safety Needs Deteriorating pavement (cracking and rutting) Four culvert pipes in poor condition Deteriorating railroad crossing pavement 5
6
7
Four culverts are in poor condition Proposing to replace three Two by railroad in Oxford One by 5 th Drive Repair one 1 mile east of 5 th Drive Size/location unchanged 8
9
10
Resurface Recycle Replacement All alternatives include: Culvert pipe repair Railroad crossing surface replacement Five-day detour required (WIS 13, WIS 21 and I-39) Centerline rumble strips Safety edge installation 11
12
Reduce head-on fatal/injury crashes by 44% Increase “awareness” Inattentive driving Limited Visibility Rain, snow or fog Low installation cost Not installed near intersections or commercial driveways 13
6% reduction in all crashes Low cost of installation Reduces hazard of low shoulders Creates “smooth transition” back onto roadway Normal Edge Safety Edge 14
Resurface Mill (remove) 2 inches of pavement Place 1.75 inches of new pavement Temporarily eliminates rutting/cracking. Underlying issues not addressed. Limited traffic impacts (flagging operation, 5 day detour) Cost = $1.5 million – $2 million 15
Remove 2 inches of asphalt Place 1.75 inches of asphalt Install centerline rumble strips Lane and shoulder width unchanged 16
Recycle Mill (remove) 2 inches of asphalt Cold-in-place recycle 4 inches of asphalt Place 1.75 inches of new asphalt Addresses more of the rutting and cracking issues Limited traffic impacts (flagging operation, five-day detour) Cost = $2.4 million – $3 million 17
Remove 2 inches of asphalt Recycle 4 inches of asphalt Place 1.75 inches of asphalt Install centerline rumble strips Lane and shoulder width unchanged 18
Replacement Remove all pavement Replace with new pavement Removes pavement not past its useful life (wastes money) Possible real estate impacts (slope widening) Greater traffic impact (four-month detour) Cost = $3.7 million – $4.5 million 19
Remove all existing asphalt Replace with 6 inches of new asphalt Install centerline rumble strips Lane and shoulder width unchanged Slopes possibly widened 20
Five-day detour (Monday – Friday) State signed detour route via WIS 13, WIS 21, I-39 Local access maintained at all times Closure V. Oxford 21
Meet with local officials: April 26, 2017 Public involvement meeting: May 16, 2017 Select preferred alternative: June 2017 Project design complete: August 2018 Construction currently scheduled: Summer 2019 22
Daniel Schave, P.E. WisDOT Project Leader 715-421-8084 daniel.schave@dot.wi.gov 23
Recommend
More recommend