tim hanley p e wisdot project manager daniel schave p e
play

Tim Hanley, P.E. WisDOT Project Manager Daniel Schave, P.E. WisDOT - PowerPoint PPT Presentation

Tim Hanley, P.E. WisDOT Project Manager Daniel Schave, P.E. WisDOT Project Leader May 16, 2017 Review purpose and needs for the project Identify alternatives (solutions) to address the needs Discuss next steps 2 3 Regional


  1. Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P.E.– WisDOT Project Leader May 16, 2017

  2.  Review purpose and needs for the project  Identify alternatives (solutions) to address the needs  Discuss next steps 2

  3. 3

  4.  Regional and local traffic  Approximately 3,700 vehicles per day  16% trucks  Constructed in 1998  Existing asphalt 8 inches thick asphalt  24 crashes in 5 year period  Run-off-the-road crashes present  Ice and snow primary factors 4

  5. Purpose  Maximize the life of the pavement  Improve safety Needs  Deteriorating pavement (cracking and rutting)  Four culvert pipes in poor condition  Deteriorating railroad crossing pavement 5

  6. 6

  7. 7

  8.  Four culverts are in poor condition  Proposing to replace three  Two by railroad in Oxford  One by 5 th Drive  Repair one  1 mile east of 5 th Drive  Size/location unchanged 8

  9. 9

  10. 10

  11.  Resurface  Recycle  Replacement  All alternatives include:  Culvert pipe repair  Railroad crossing surface replacement  Five-day detour required (WIS 13, WIS 21 and I-39)  Centerline rumble strips  Safety edge installation 11

  12. 12

  13.  Reduce head-on fatal/injury crashes by 44%  Increase “awareness”  Inattentive driving  Limited Visibility  Rain, snow or fog  Low installation cost  Not installed near intersections or commercial driveways 13

  14.  6% reduction in all crashes  Low cost of installation  Reduces hazard of low shoulders  Creates “smooth transition” back onto roadway Normal Edge Safety Edge 14

  15. Resurface  Mill (remove) 2 inches of pavement  Place 1.75 inches of new pavement  Temporarily eliminates rutting/cracking.  Underlying issues not addressed.  Limited traffic impacts (flagging operation, 5 day detour)  Cost = $1.5 million – $2 million 15

  16. Remove 2 inches of asphalt Place 1.75 inches of asphalt Install centerline rumble strips Lane and shoulder width unchanged 16

  17.  Recycle  Mill (remove) 2 inches of asphalt  Cold-in-place recycle 4 inches of asphalt  Place 1.75 inches of new asphalt  Addresses more of the rutting and cracking issues  Limited traffic impacts (flagging operation, five-day detour)  Cost = $2.4 million – $3 million 17

  18. Remove 2 inches of asphalt Recycle 4 inches of asphalt Place 1.75 inches of asphalt Install centerline rumble strips Lane and shoulder width unchanged 18

  19.  Replacement  Remove all pavement  Replace with new pavement  Removes pavement not past its useful life (wastes money)  Possible real estate impacts (slope widening)  Greater traffic impact (four-month detour)  Cost = $3.7 million – $4.5 million 19

  20. Remove all existing asphalt Replace with 6 inches of new asphalt Install centerline rumble strips Lane and shoulder width unchanged Slopes possibly widened 20

  21.  Five-day detour (Monday – Friday)  State signed detour route via WIS 13, WIS 21, I-39  Local access maintained at all times Closure V. Oxford 21

  22.  Meet with local officials: April 26, 2017  Public involvement meeting: May 16, 2017  Select preferred alternative: June 2017  Project design complete: August 2018  Construction currently scheduled: Summer 2019 22

  23.  Daniel Schave, P.E.  WisDOT Project Leader  715-421-8084  daniel.schave@dot.wi.gov 23

Recommend


More recommend