tdc council
play

TDC Council 25 June 2020 Waimea Water 25/06/2020 Waimea Water Ltd - PowerPoint PPT Presentation

Waimea Community Dam TDC Council 25 June 2020 Waimea Water 25/06/2020 Waimea Water Ltd 1 Agenda 1. Covid-19 impact 2. Funding and expenditure 3. Expenditure and progress 4. Safety 5. Environmental 6. Rockfill: The geology challenge 7.


  1. Waimea Community Dam TDC Council 25 June 2020 Waimea Water 25/06/2020 Waimea Water Ltd 1

  2. Agenda 1. Covid-19 impact 2. Funding and expenditure 3. Expenditure and progress 4. Safety 5. Environmental 6. Rockfill: The geology challenge 7. Design update 8. Construction update (video) 9. Questions 25/06/2020 Waimea Water Ltd 2

  3. Meet the WWL Team • Designer (PS-1, PS-4) Damwatch Engineering • Reviewer (PS-2) GHD Engineering • Engineer to Contract Stantec • Contractor (PS-3) Fulton Hogan Taylors • Quantity Surveyor Rawlinsons • Contract Law Anderson Lloyd • Programme CCCL • Safety Impac; Intesafety • Accountant Findex • Banker ANZ • Auditor Audit NZ 25/06/2020 Waimea Water Ltd 3

  4. COVID-19 ❖ WWL incurs cost of 5-week Suspension and further delay (no Force Majeure provision in NZ3910) ➢ Further week delay to remobilize and implement facilities ➢ Not covered by insurance ❖ Productivity impacted on resumption with level-3 / level-2 protocols ➢ NZ Construction Industry Standards ❖ Supply chain constrained and likely to slow project: Spares, parts, equipment ➢ Uncertain how international supply chain recovers ❖ Cost of suspension and recovery to yet be determined ➢ Looking to NZ Construction Industry. No precedents ➢ Impact of COVID-19 to be determined during 2020/21 year per Final SOI 25/06/2020 Waimea Water Ltd 4

  5. Funding and expenditure: 31 May 2020 Funding and Spend Forecast cost & schedule to complete 140 $129.4m Excludes Cost of COVID-19 120 August 2021 100 80 $ millions July 2020 60 $50.2m 40 20 - Dec-2018 Dec-2019 Dec-2020 Dec-2021 Budget New forecast (SoI) Actual 25/06/2020 Waimea Water Ltd 5

  6. Expenditure and progress Progress 16 months Months 37mths 40mths Excludes Cost of COVID-19 $ $50m Expenditure $104.4m $129.4m 0% 25% 50% 75% 100% ECI Costs During Construction Construction Variations Remain Original Budget Revised Forecast 25/06/2020 Waimea Water Ltd 6

  7. Context (SOI) Excludes Cost of COVID-19 25/06/2020 Waimea Water Ltd 7

  8. Programme: + 6 months = +1 season ❖ Currently expect 6 month delay to programme with further risk of slippage ❖ Exploring and pursuing recovery programme (shift work; defer works) 21/04/2020 Waimea Water Ltd 8

  9. Safety: No injuries to date Leading: Contractor Audit and Inspection 35 30 25 20 15 10 5 0 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Lead OFI Low Potential Med Potential High Potential Lagging: Accidents, Harm, HPI 5 1 LTI Number of incidents Incident Frequency ratios LTIFR / MTIFR / TRIFR 4 MTI 3 FAI HPI 2 Celebrating 500 days injury free MTIFR 1 TRIFR 0 0 25/06/2020 Waimea Water Ltd 9

  10. Environmental: Full compliance with consent Lead: Audit, Inspection and Water Quality monitoring 14 12 No. Audits per month 10 8 6 4 2 0 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 TDC Compliance Contractor Weekly Audit Contractor Monthly Audit FHTJV HO Env Visit Environmental Control Inspection Environmental Follow Up Audit Southern Skies ESC Inspection SLR Water Quality Visit #42 River Health Indicator: Quantitative Macroinvertebrate Community Index 8.5 • Approved 5 Environmental Management Plans QMCI Index (clipped to show QMCI Upstream 8 ✓ Verified 7.5 QMCI Downstream detail) 7 • Approved 9 SCEMPs 6.5 20% below average ✓ Verified pre-construction 6 U/S QMCI 5.5 Pre- Construction During Construction  All required plans for current works in place, 5 6/03/2017 22/09/2017 10/04/2018 27/10/2018 15/05/2019 1/12/2019 certified, verified and functioning 25/06/2020 Waimea Water Ltd 10

  11. Environmental: Full compliance with consent Independent ecologist #45 River Health Indicator: pH verifies river health indicators 12 10 8 pH Upstream pH 6 pH Downstream 4 Lower Limit 2 Upper Limit 0 #44 River Health Indicator: Deposited Fine Sediment 50 % of river bed with fine sediment 45 40 35 30 deposits 25 Upstream 20 Downstream 15 Downstream Threshold 10 5 0 25/06/2020 Waimea Water Ltd 11

  12. Rockfill: The Geology Challenge ▪ Embankment trials late December 2019 and early January 2020 identified Rock degradation Discovered Expected and Needed Heavily broken down – Not free draining Less broken down – Free draining 25/06/2020 Waimea Water Ltd 12

  13. Rockfill: The Geology Challenge ▪ Discovering more argillite (mud / siltstone) (~70%) and less greywacke (sandstone) than expected ▪ Greywacke (sandstone) dispersed amongst predominant argillite. Difficult to salvage. (VIDEO) ▪ Fissile argillite showing tendency to break along insipient foliations ➢ Spillway Excavation: “May yield a minimum of 350,000 m3 of rock that will consist of slightly weathered to weathered (Class 1 & 2) greywacke.” (2014). Predominantly fissile argillite ➢ Need to find suitable drainage material from alternative sources (cost) 25/06/2020 Waimea Water Ltd 13

  14. Design: Rezoning embankment to manage geology ❖ Expect less harder class-1 material ❖ Testing in early 2020 identified breakdown on compaction  Increase drainage layers Free Draining  Alternatively source drainage rock Not Free Draining Drainage 25/06/2020 Waimea Water Ltd 14

  15. Design: Spillway modified for improved resilience Design modifications due to recent learnings from international spillway incidents (international standards)  Oroville (right) failure due to poor drainage and anchoring detailing (pressure beneath fn velocity)  Whaley Bridge (UK) no drainage and poor slab detailing combined with poor maintenance 2009: 5-9 Modifications for resilience (requested by CIIL): 2012: 10-14  Drainage reviewed and upgraded 2017: 15-17  Anchoring design reviewed and upgraded Additional modifications driven by topography and encountered geology. 25/06/2020 Waimea Water Ltd 15

  16. Design Update ✓ Spillway: ▪ Redesigned with vertical walls to mitigate topography / geology risks RHS ▪ Increased drainage per recent standard ▪ Completed and peer reviewed 25/06/2020 Waimea Water Ltd 16

  17. Design Update: Other items Mechanical and Electrical ❖ Not designed or priced at commencement of work  Provision Sum challenged  To be priced ~3 rd Quarter 2020 2009: 5-9 2012: 10-14 ▪ Progressing detailed design 2017: 15-17  Switch to single outlet pipe aiming to realise cost savings  Modifications for future hydropower installation 25/06/2020 Waimea Water Ltd 17

  18. Power Generation: Opportunity Enlarge Reservoir / Powergen ▪ Fuse Gate to utilise 2.3m / 5m of flood reservoir ▪ Activate in event of large flood say 1:10,000 yr AEP (55% - 70% of PMF 1094 m3/s) + 1.5Mm 3 storage to ~15Mm 3 (15%) ▪  Storage increases powergen utilisation  Increase resilience to droughts / growth / demand 25/06/2020 Waimea Water Ltd 18

  19. Agenda 1. Covid-19 impact 2. Funding and expenditure 3. Expenditure and progress 4. Safety 5. Environmental 6. Rockfill: The geology challenge 7. Design update 8. Construction update (video) 9. Questions 25/06/2020 Waimea Water Ltd 19

  20. Construction Update RHS Plinth Spillway Culvert LHS Plinth 25/06/2020 Waimea Water Ltd 20

  21. Diversion Culvert: ~80% complete ✓ Completed Floor ✓ 12/17 wall & roof sections completed ➢ Expect to complete by Aug and divert river September 2020 25/06/2020 Waimea Water Ltd 21

  22. Construction Update: Forming LHS Plinth ✓ Foundation treated and site blinding concrete complete ✓ Commenced forming plinth 25/06/2020 Waimea Water Ltd 22

  23. Construction Update: Preparing RHS Plinth ✓ Foundation treatment and treatment underway 25/06/2020 Waimea Water Ltd 23

  24. Construction Update: Spillway ▪ Spillway cut underway ➢ Exposed first 20 m section of foundation ❖ Uncovering significantly weathered foundation that will require treatment ▪ Close to cliff edge ✓ Supports change in design to self-supporting vertical walls, rather than a liner ▪ Will evaluate extent of any edge support 25/06/2020 Waimea Water Ltd 24

  25. Construction Issues: Unexpected Voids ❖ >1000 m3 concrete ✓ LHS & Culvert done ❖ RHS, Spillway and starter dam to do 21/04/2020 Waimea Water Ltd 25

  26. Closing: By the numbers Task Total Quantity Unit Vegetation Clearance 85 Hectare m 3 Excavation 633,000 m 3 Fill 430,000 m 3 Cut to Waste 311,000 m 3 Material Processing 120,000 m 3 Concrete 22,000 Reo Steel (bars) 3,900 t m 2 Reo Steel (mesh) 10,000 Anchors 4,200 No. m 2 Concrete Face 10,000 25/06/2020 Waimea Water Ltd 26

  27. More Information 25/06/2020 Waimea Water Ltd 27

  28. 17 Dec 2019: Rezoning embankment to manage geology ❖ Expect less harder class-1 material ❖ Experiencing more fines  Increase drainage layers with  Processed (screened) out fines 2009: 5-9 2012: 10-14 2017: 15-17 02/12/2019 Waimea Water Ltd 28

Recommend


More recommend