tailings storage and heap leaching in a combined facility
play

Tailings Storage and Heap Leaching in a Combined Facility A First - PowerPoint PPT Presentation

Tailings Storage and Heap Leaching in a Combined Facility A First for the Mining Industry Thomas F. Kerr, P.E., Knight Pisold and Co. Michael G. Skurski, P.E., Newmont Mining Co. Peter D. Duryea, Ph.D., P.E., Knight Pisold and


  1. “Tailings Storage and Heap Leaching in a Combined Facility – A First for the Mining Industry” Thomas F. Kerr, P.E., Knight Piésold and Co. Michael G. Skurski, P.E., Newmont Mining Co. Peter D. Duryea, Ph.D., P.E., Knight Piésold and Co.

  2. Overview  New La Quinua gold mill at the Yanacocha Mine has a thickened tailings storage facility (TTSF) contained entirely within a large (530 Mt and 130 m high) active heap leach pad (HLP)  Unprecedented in the mining industry  Provides the operator with cost, land use and closure efficiencies  Constructed between 2006 and 2008 as part of the staged expansion of the La Quinua HLP – tailings deposition commenced in April 2008 2

  3. General Arrangement Plan 3

  4. Artificial Oblique View Looking North 4

  5. Aerial View Looking West During Construction 5

  6. Key Design Issue  Leach ore embankments retaining tailings needed to provide the high level of security required of other major tailings dams  However, the leach ore is placed in thick (16 m) uncompacted lifts to maintain adequate permeability for leaching and is irrigated with a high solution rate (10 L/hr/m 2 )  Loose structure made static and dynamic liquefaction a key issue 6

  7. Design Approach Keep the ore that becomes saturated or near saturated when under leach well-removed from the outer faces of the embankments and contained behind large unsaturated structural shells 7

  8. Design Solution Provide the embankments with wide cross sections  to support loading and leaching and thus wide shells Place the ore in coarser (lower) and finer (higher)  zones to promote vertical downward drainage and reduce lateral spread of flow Thicken the tailings to reduce the amount of water  entering the combined facility Use a rotational tailings deposition method from the  inside crests of the embankments to build drained and stable beaches against the embankments 8

  9. Wide Zoned Cross Sections 10

  10. Drained Beach Development 11

  11. Hydraulic Model Results Saturated zone is in center of embankment – flow vectors are vertically down – consistent with design objective 12

  12. Seismic Risk of the Site Maximum Design Earthquake (MDE) is equal to the Maximum Credible Earthquake (MCE) Deep intraplate event below the Andes Magnitude 8.0 Distance and depth 90 and 100 km, respectively Resulting peak horizontal ground acceleration at the site is 0.41 g 13

  13. Design Earthquake  Maximum Design Earthquake (MDE) is equal to the Maximum Credible Earthquake (MCE)  Deep intraplate event below the Andes  Magnitude 8.0  Distance and depth 90 and 100 km, respectively  Resulting peak horizontal ground acceleration at the site is 0.41 g 14

  14. Dynamic Stability Model Results Shear bands from earthquake loading closely match the critical slip surfaces from static limit equilibrium analyses – along liner interface 15

  15. Dynamic Stability Model Results Contours of total deformation - Maximum horizontal 15 cm along liner - Maximum vertical 25 cm at crest 16

  16. Actual Leach Ore Placement  Sonic drill used to provide continuous samples of ore in the HLP  Not adequate differentiation of fines content in designated zones  Operation will put more emphasis on maintaining adequate unsaturated outer shells via controls on leach solution application and monitoring of instrumentation 17

  17. Heap Leach Ore Piezometer Results Section B MINERA YANACOCHA S.R.L. Figure A.20 MSSF - La Quinua Heap Leach Pad Stage 4&5 - Cross Section B' - Vibrating Wire Piezometers Data 3 LQMYVP07-04 LQMYVP07-05 LQMYVP08-02 LQMYVP08-03 LQMYVP08-04 2 LQMYVP08-06 Presure Head (meters of water) 1 0 -1 -2 -3 09-Oct-07 08-Nov-07 08-Dec-07 07-Jan-08 06-Feb-08 07-Mar-08 06-Apr-08 06-May-08 05-Jun-08 05-Jul-08 04-Aug-08 03-Sep-08 03-Oct-08 02-Nov-08 02-Dec-08 01-Jan-09 31-Jan-09 02-Mar-09 01-Apr-09 01-May-09 31-May-09 30-Jun-09 Date 19

  18. Tailings Facility Piezometer Results MINERA YANACOCHA S.R.L. Figure A.27 MSSF - La Quinua Heap Leach Pad Stage 5&6 - DAM - Vibrating Wire Piezometers Data 5 3600 LQMYVP07-06 LQMYVP07-07 LQMYVP07-08 LQMYVP07-09 LQMYVP07-10 LQMYVP07-11 3590 LQMYVP07-12 LQMYVP07-13 4 LQMYVP07-14 LQMYVP07-15 LQMYVP07-16 LQMYVP07-17 Avg Elevation of Mill 3580 3 3570 Presure Head (meters of water) Average elevation (m) 2 3560 Initial Discharge of Mill Sands 1 3550 3540 0 3530 -1 3520 -2 3510 -3 3500 10-Aug-07 09-Sep-07 09-Oct-07 08-Nov-07 08-Dec-07 07-Jan-08 06-Feb-08 07-Mar-08 06-Apr-08 06-May-08 05-Jun-08 05-Jul-08 04-Aug-08 03-Sep-08 03-Oct-08 02-Nov-08 02-Dec-08 01-Jan-09 31-Jan-09 02-Mar-09 01-Apr-09 01-May-09 31-May-09 30-Jun-09 Date 21

  19. Water Management System 23

  20. Tailings Deposition System 24

  21. Conclusions The La Quinua TTSF is unique  Contrary to standard tailings dam practice, it contains  embankments of leach ore placed in thick, uncompacted lifts that are subject to application of large quantities of leach solution and percolation flows Dynamic analyses have shown that there is the potential  for liquefaction or strain softening of saturated or near saturated internal zones but the overall predicted deformations are minimal Ultimate control on stability is by leach solution application  rate Operation to date is meeting design objectives  A comprehensive geotechnical investigation will be  completed with follow-up dynamic deformation analyses based on actual materials placed 25

Recommend


More recommend