stormwater management improvements
play

Stormwater Management Improvements Public Meeting March 13, 2013 - PowerPoint PPT Presentation

Stormwater Management Improvements Public Meeting March 13, 2013 Village Aerial Combined Sewer System Sewer Surcharging Sewer System Overview Estimated in 2001 that the Villages system has the capacity to handle a 2-3 year storm


  1. Stormwater Management Improvements Public Meeting March 13, 2013

  2. Village Aerial

  3. Combined Sewer System

  4. Sewer Surcharging

  5. Sewer System Overview  Estimated in 2001 that the Village’s system has the capacity to handle a 2-3 year storm (approximately 1.7 inches in 2 hours)  Periodic reports of sewers surcharging into basements and streets

  6. Flooding is Not a Recent Phenomenon  Significant storms have occurred in:  1956, 1962, 1969, 1972, 1981, 2001, 9/08, 6/09  Following the 1981 storms, Village begins installing surface storm sewer restrictors

  7. Curb Inlets Not Restricted Restricted

  8. Catch Basin Covers Restricted Unrestricted Approximately 70-75% of sewers are restricted within the Village

  9. Village Flood Survey  August 2, 2001 Storm  3” rain received in 2 hours  25 year rain event  The Village surveyed all residents to determine extent and type of flooding

  10. August 2, 2001 Flooding (35% response rate to survey)

  11. September 13 & 14 2008 Flooding Storm estimated to be a 3.5 year event, data based on 134 phone calls received.

  12. Sewage in Basement June 19, 2009 Storm Reports of Sewage in Basement 2-3 Year Event, 160 Phone Calls

  13. Incremental Village Actions  2004  Adopted a Stormwater Management Ordinance that requires new development to control water on-site  Bulk Regulations approved limiting the size of structures, which limits the amount of impervious surface on a lot

  14. Incremental Village Actions  Received a grant to assist homeowners install flood control devices (164 homes participated)  Northeast Parkway construction removed large portion of Business Park from combined sewer system  2010- Sewer User Fee created for infrastructure repairs/maintenance and upgrades  Crawford Avenue will be disconnected from sewer system

  15. Stormwater Management Plan  2007-the Ad-Hoc Sewer Committee recommended and the Village Board approved the following motion:  “The creation of a Stormwater Management Plan (SMP) that would handle a 10-year rain event (2.1” of rain per hour) with a goal of achieving such protection in 10 years.”

  16. Area Communities’ Stormwater Management Planning Goals Municipality Capacity Goal Cost Park Ridge 10-year storm $16 million Wilmette 10-year storm $35 million Skokie 10-year storm $80 million Evanston 10-year storm $200 million

  17. Stormwater Modeling Computer Model of Sewer System   Topography  Geographical Information Systems (GIS) Data  Manhole Locations  Pipe Sizes & Locations  Design Storms Two Main Components   Hydrologic  Watershed characteristics, imperviousness, topography, etc.  Hydraulic  Sewer size, slope, material, etc.

  18. Modeling Process  The Village identified a three-phase process:  Phase I - Pass/fail analysis: after model is prepared determine if the system can handle a 10-year rain event  Phase II – Calibrate the model, then identify system bottlenecks that are potentially causing problems. Identify system improvements to bring the system to the 10-year protection  Phase III - Design and construct the improvements

  19. Stormwater Study Results  Phase I  Computer generated model of sewer system indicates that the system fails, cannot handle a 10- year rain event  Phase II  Real data is used to update the computer model to evaluate the system, surface storage and underground storage of stormwater are recommended

  20. Phase II Model Results

  21. Surface Storage  What is surface storage?  The use of the street to store stormwater during and after a storm for a designated period of time  How does it work?  Berms (on the street) and restrictors (inside the sewer) are used to control the amount of water that enters the sewer so that it does not fill up too quickly  Water is stored on the street while waiting to enter the sewer  How much water will be on my street?  Max ponding depth at the center of the road: 6 inches  Max ponding depth at the curb: 9 inches  Max ponding width on the road: Back of sidewalk  Max ponding duration (after rain stops) for residential roads: 120 minutes

  22. Sub-Surface Restrictor in Catch Basin Storm water Enters the Catch Basin Stormwater Enters Sewer from Curb Drain Inlet Outlet Pipe to Combined Sewer Manhole

  23. Surface Storage

  24. Benefits of Surface Storage  The level of protection for the Village will be increased from a 2-3 year level of protection to a 4-5 year  55% reduction in the number of homes at-risk for flooding during a 10-year storm  Most cost effective means of large scale detention

  25. Cost for Surface Storage  The total cost for maximizing street storage is approximately $5,592,060

  26. Conveyance and Detention  In order to obtain protection for the remaining areas at- risk during a 10-year event additional storage methods must be used  Nine projects are recommended that include:  Detention ponds  New storm sewers in various locations  Enlarging existing combined sewers

  27. Conveyance and Detention Projects  Project #1- Three alternatives:  Project #1.1 – Detention pond in Pohatan Park  Project #1.2 – In-line storage  Project #1.3 – Surface detention via detention storage  Project #2 – 2,600 feet of 8 inch to 36 inch storm sewer and North ComEd detention facility  Project #3 – 3,350 feet of 15 inch to 48 inch storm sewer and South ComEd detention facility  Project #4 – 3,020 feet of 36 inch storm sewer  Project #5 – 2,000 feet of 18 inch to 60 inch storm sewer to South North Shore Channel Outlet

  28. Conveyance and Detention Projects  Project #6 – 1,860 feet of 21 inch to 36 inch storm sewer and Central ComEd detention facility  Project #7 – Upsize 750-foot section of existing combined sewer to 24 inch to 36 inch sewer (this project has been eliminated by extending Project #2 to west of Cicero)  Project #8 – Upsize 1,000-foot section of combined sewer to 60 inch – 72 inch sewer

  29. Conveyance and Detention Projects  Project #9 – Three alternatives were given consideration as follows:  Project #9.1 – 11,400 feet of 24 inch to 60 inch storm sewer to North (Touhy) North Shore Channel outlet  Project #9.2 – Rather than construct a new storm sewer along Touhy to the North Shore Channel, direct storm runoff to in-line storage via twin 96 inch storm sewers under the abandoned Union Pacific ROW  Project #9.3 – Rather than construct a new storm sewer along Touhy to the North Shore Channel, direct storm runoff to a detention pond along the abandoned Union Pacific ROW

  30. Recommended Conveyance and Detention Projects

  31. Engineer’s Project Priority Recommendations Homes Cost per Cost Description Priority Project # Protected Home Alternative Flow restrictors & containment berms 1 $ 5,592,060 1,700 $ 3,289 1 2 5 New North Shore Chanel Storm Outlet $ 1,335,398 210 $ 6,359 Storm sewer & ComEd Central detention 3 6 $ 1,710,210 152 $ 11,251 pond Storm sewer & ComEd South detention 4 3 $ 2,843,679 145 $ 19,612 pond 8,000 feet of 24 inch to 60 inch storm 5 9.3 sewer & abandoned Union Pacific ROW $ 9,427,386 detention 345 $ 34,269 3,020 feet of 36 inch storm sewer 6 4 $ 2,395,478 Storm sewer & ComEd North detention 7 2 $ 2,137,650 44 $ 48,583 pond Upsize 1,000-foot section of combined 8 8 sewer to 60 inch - 72 inch sewer along $ 1,933,168 Pratt Storm sewer & Polatan Park detention 154 $ 53,178 9 1.1 $ 3,908,687 pond 10 1.3 Detention Storage (3 sites) $ 2,347,500 Upsize 750-foot section of existing 11 7 combined sewer to 24 inch to 36 inch sewer (Merged with Project #2) Grand Total $ 33,631,216

  32. Cost for Conveyance and Detention  $28,039,156 to implement the nine recommended projects  Protection will be provided to the remaining 43% of the area still at-risk during a 10-year storm once street storage is provided

  33. Summary of Improvements Street Storage Only  152 berms and 3,981 hanging trap inlet restrictors  Provides 4-5 year storm protection during 10-year storm  Protection is provided to approximately 55% of the area  Approximately $5,592,060 Conveyance and Detention  10-year level of protection for entire Village  9 projects which include storm water conveyance and detention  Approximately $28,039,156 Total estimated cost for 10-year level of protection $33,631,216

  34. Ad Hoc Sewer Committee’s Recommendation  Ad Hoc Sewer Committee recommends to move forward with street storage within 15-20% of the Village as a pilot program and that project #5-2,000 feet of 18 inch to 60 inch storm sewer to South North Shore Channel Outlet be advanced to 30% design state so that grant funding may be applied for the project

  35. Recommended Phase III Pilot Area

  36. Funding Options  Low interest loans from the Illinois Environmental Protection Agency (payable from the sewer user charge)  Grants  Multi-year capital improvement program

  37. Questions?

Recommend


More recommend