play

SH 358 IMPROVEMENTS Corpus Christi District Updated October 2018 - PowerPoint PPT Presentation

SH 358 IMPROVEMENTS Corpus Christi District Updated October 2018 SH 358 Improvements Corpus Christi District All dates & schedules are subject to change Updated October 2018 Project Overview Length: 15 miles Total cost: $49.96


  1. SH 358 IMPROVEMENTS Corpus Christi District Updated October 2018 SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018

  2. Project Overview  Length: 15 miles  Total cost: $49.96 million  Mainlane improvements from north of Leopard Street to east of Flour Bluff Drive: – Install new lighting – Install Intelligent Transportation Systems (ITS), including traffic cameras  Eastbound mainlane and frontage road improvements from Ayers Street to Nile Drive: – Reconstruct center median barrier – Widen freeway to improve capacity and mobility – Reverse ramps – Improve signal timing SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 2

  3. Project Phases and Timeline The project is being constructed in 10 phases*: Phase 1 January 2018 – June 2018 Phase 2 March 2018 – Spring 2019 Phase 3 Fall 2018 – Summer 2019 Phase 4 Spring 2019 – Summer 2020 Phase 5 Summer 2020 * This schedule is subject to change. Phase 6 Summer 2020 – Spring 2021 ITS and eastbound frontage road signal improvements Phases 7-10 Spring 2021 – Fall 2021 from north of Leopard Street to east of Flour Bluff Drive will be made throughout project duration. SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 3

  4. Construction Sequencing – Phase 1 Overview  Construct new temporary mainlane center median barrier from Ayers Street to Airline Road  Widen eastbound frontage road and construct sidewalks between Ayers Street and Kostoryz Road Crews begin work to reconstruct the mainlane center median barrier. TxDOT Photo SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 4

  5. Phase 1 – Mainlanes Between Ayers Street and Airline Road  Remove existing center median barrier Off-peak lane closures are required as the existing center median barrier is replaced  Reconstruct inside shoulders and add with a temporary barrier and the inside temporary center median barrier shoulders are reconstructed.  Purpose: – Accommodate future eastbound mainlane traffic shifts and permanent center median barrier  Closures required: – Various off-peak eastbound and westbound mainlane closures SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 5

  6. Phase 1 – Eastbound Frontage Road near Richter Street  Widen eastbound frontage road near future Kostoryz Road/Carroll Lane off-ramp: – Add new sidewalks and curbs/gutters – Add 3rd eastbound lane on frontage road east of Richter Street  Purpose: – Accommodate future relocated off-ramp  Required closures: – Off-peak closures of outside eastbound frontage road lane – Temporary closures of Richter Street SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 6

  7. Construction Sequencing – Phase 2 Overview  Construct new eastbound off-ramp and remove existing off-ramp serving Kostoryz Road and Carroll Lane Relocated EB off-  Widen eastbound frontage road and ramp to Kostoryz Rd/ Carroll Ln construct sidewalks in segments: – Between Kostoryz Road and Weber Road – Between Weber Road and Everhart Road – Between Everhart Road and South Staples Street – Near Airline Road SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 7

  8. Phase 2 – Eastbound Off-Ramp to Kostoryz Road/Carroll Lane  Relocate eastbound off-ramp serving Kostoryz Road and Carroll Lane: – Build new off-ramp near Richter Street, west of existing off-ramp – Improve drainage along frontage road Existing Kostoryz Rd/ New Kostoryz Rd/ Carroll Ln off-ramp – Permanently close existing off-ramp Carroll Ln off-ramp to be built  Purpose: farther west – Improve safety and mobility for eastbound mainlane and frontage road drivers approaching the Kostoryz Road intersection.  Anticipated closures: – Off-peak closures of inside eastbound frontage road lane SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 8

  9. Phase 2 – Eastbound Frontage Road Between Kostoryz Road and Weber Road  Widen eastbound frontage road near existing ramps adjacent to Cosner Drive and Wilkinson Drive: – Add new sidewalks and curbs/gutters – Add 3rd eastbound lane on frontage road east of Wilkinson Drive  Purpose: Accommodate future ramp reversal and widened eastbound mainlanes  Anticipated closures: – Off-peak closures of outside eastbound frontage road lane – Potential temporary closures: • Cosner Drive and Wilkinson Drive • Driveways (e.g. Bethel, Sames) Existing ramps near Cosner Dr • Additional closures across eastbound frontage road and Wilkinson Dr near Wilkinson Drive for drainage pipe installation SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 9

  10. Phase 2 – Eastbound Frontage Road Between Weber Road and Everhart Road  Widen eastbound frontage road near existing ramps adjacent to Oakhurst Drive and Embassy Drive: – Add new sidewalks and curbs/gutters – Extend 3rd eastbound lane on frontage road to/from freeway ramps  Purpose: Accommodate future ramp reversal and widened eastbound mainlanes  Anticipated closures: – Off-peak closures of outside eastbound frontage road lane – Potential temporary closures: • Oakhurst Drive and Embassy Drive • Most driveways (e.g. La Playa, Cesar Chavez, Academy) Existing ramps • Some closures across eastbound frontage road near both Oakhurst Drive and Embassy Drive for drainage pipe near Oakhurst Dr installation and Embassy Dr – Permanent closure of one redundant driveway east of Embassy Drive SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 10

  11. Phase 2 – Eastbound Frontage Road Between Everhart and South Staples  Widen eastbound frontage road near existing ramps adjacent to the Academy store and Moore Plaza shopping center: – Add new sidewalks and curbs/gutters – Extend 3rd eastbound lane on frontage road to/from freeway ramps  Purpose: Accommodate future ramp reversal and widened eastbound mainlanes  Anticipated Closures: – Off-peak closures of outside eastbound frontage Existing ramps road lane as needed near the Academy store and Moore – Potential temporary closures: Plaza shopping • Blanche Moore Drive center • Driveways (e.g. On the Border, Romano’s) • Some closures across eastbound frontage road near both Blanche Moore Drive and the Academy store for drainage pipe installation SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 11

  12. Phase 2 – Eastbound Frontage Road near Airline Road  Widen and improve eastbound frontage road near existing Airline Road on-ramp: – Add new sidewalks and curbs/gutters – Add new inlets and pipe to improve drainage at Airline Road intersection  Purpose: Increase eastbound frontage road capacity and improve safety near Airline Road  Anticipated closures: – Off-peak closure of outside eastbound frontage road lane as needed – Potential temporary closures: • Across eastbound frontage road near Golden Corral restaurant for drainage pipe installation • Across all lanes of eastbound frontage road and Airline Road intersection SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 12

  13. Construction Sequencing – Phase 3 Overview  Widen eastbound mainlane bridges to four lanes at Kostoryz Road and Carroll Lane  Widen eastbound mainlanes and reconstruct median between the eastbound mainlanes and frontage road from Everhart Road to South Staples Street  Widen eastbound frontage road and construct sidewalks between South Staples Street and Airline Road SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 13

  14. Phase 3 – Eastbound Mainlane Bridge at Kostoryz Road  Widen eastbound mainlane bridge at An additional lane will be built Kostoryz Road on the eastbound mainlane bridges at Kostoryz, Carroll,  Purpose: Accommodate four mainlanes Weber, Everhart, and Staples.  Anticipated closures and detours: – Off-peak closures of Kostoryz Road intersection – Potential temporary closure of westbound-to- eastbound turnaround under bridge – Potential temporary detours of Kostoryz Road/frontage road traffic to adjacent intersections and turnarounds SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 14

  15. Phase 3 – Eastbound Mainlane Bridge at Carroll Lane  Widen eastbound mainlane bridge at Carroll Lane  Purpose: Accommodate four mainlanes and prepare for Weber Road off-ramp relocation  Anticipated closures and detours: – Potential off-peak closure of Carroll Lane intersection – Potential temporary closure of westbound-to- eastbound turnaround under bridge – Potential temporary detours of Carroll Lane/ frontage road traffic to adjacent intersections and turnarounds SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 15