second avenue subway
play

Second Avenue Subway Ph.D., P.E., President Ph.D., P.E., President - PowerPoint PPT Presentation

MTA Capital Construction MTA Capital Construction Michael Horodniceanu Horodniceanu, , Michael Second Avenue Subway Ph.D., P.E., President Ph.D., P.E., President Quarterly Public Workshop March 20, 2012 March 20, 2012 * *Licensed in


  1. MTA Capital Construction MTA Capital Construction Michael Horodniceanu Horodniceanu, , Michael Second Avenue Subway Ph.D., P.E., President Ph.D., P.E., President Quarterly Public Workshop March 20, 2012 March 20, 2012 * *Licensed in California

  2. Overview • November 30th Workshop Follow-Up • Actions Taken for Improved Livability • Construction Progress • SAS Phase 1 Completion: December 2016 2

  3. November 30, 2011 November 30, 2011 Workshop Follow- -Up Up Workshop Follow 3

  4. November 30, 2011 Workshop Follow-Up • Historic first MTA SAS Public Workshop • Attended by nearly 200 community members • Community input prompted physical site changes • Second Avenue Subway Public Workshop November 2011 Follow-Up Report o Hardcopies at workshop table o Available online mta.info 4

  5. MTA Actions for Improved Livability MTA Actions for Improved Livability SAS Community Tour SAS Community Tour 5

  6. MTA Actions for Improved Livability Community Outreach • Newsletters • Community tours • Bulletin board notices • Pre-blast and drill email notifications Communications Communications • 72 nd Street • 86 th Street (available soon) • Community liaison visibility on-site • Construction Advisory Committee (CAC) meetings • Monthly meetings with building management, condo/co-op boards, business owners, & residents living in buildings not represented by Visible Vests Visible Vests boards (63 rd , 72 nd , 86 th , 96 th ) 6

  7. MTA Actions for Improved Livability Environmental • Truck operations • Some progress on construction noise • Muck house improvements Second Avenue E. 72nd Street Second Avenue E. 72nd Street Truck Truck Muck House Muck House Operations Operations 7

  8. MTA Actions for Improved Livability Traffic/Pedestrian Safety • Improved sidewalk conditions • Installed new mid-block crosswalks and stop signs • Added pedestrian managers at 96 th and 93 rd streets • Increased Traffic Enforcement Agent presence at 73 rd and 70 th streets Mid- -block Crosswalk block Crosswalk Mid Pedestrian Pedestrian and Stop Signs and Stop Signs 8 Manager Manager

  9. MTA Actions for Improved Livability Survey: Community Outreach 9

  10. MTA Actions for Improved Livability Survey: Environmental 10

  11. MTA Actions for Improved Livability Survey: Traffic/Pedestrian Safety 11

  12. MTA Actions for Improved Livability Survey: 72nd Street Cavern Tour • 100% of respondents: • Described the MTACC staff as helpful and knowledgeable • Felt the time allotted for the tour was just right • Would schedule another tour in the future or recommend it to a friend 12

  13. MTA Actions for Improved Livability Survey: 96th Street Cavern Tour ( 7) ( 1 0) ( 3) ( 1) ( 1) • 100% of respondents: • Described the MTACC staff as very helpful and knowledgeable • Would schedule another tour in the future or recommend it to a friend 13

  14. MTA Actions for Improved Livability SAS Community Information Center Potential uses • Project-related community meetings • Project communications and information • Education programs • Rotating exhibits Survey • Available at each table • Submit with input 14

  15. SAS SAS Construction Progress Construction Progress Arch Form Used for Tunnel Concrete Operations Arch Form Used for Tunnel Concrete Operations Preparations for East Tunnel Preparations for East Tunnel 15

  16. East Tunnel Waterproofing East Tunnel Waterproofing

  17. Gantry Crane Used to Deliver Steel Gantry Crane Used to Deliver Steel Gantry Crane Used to Deliver Steel at the Lexington Av- -63rd St Station 63rd St Station at the Lexington Av at the Lexington Av-63rd St Station 17

  18. Lexington Av- -63rd Street Cavern 63rd Street Cavern Lexington Av Lexington Av-63rd Street Cavern Lower Platform Construction Lower Platform Construction Lower Platform Construction

  19. 72nd Street Cavern 72nd Street Cavern Entrance 2 Construction Entrance 2 Construction

  20. E. 83rd – E. 83rd – E. 84th Streets E. 84th Streets South Shaft Muck System South Shaft Muck System 20

  21. Demolition of Building on Northwest Demolition of Building on Northwest Corner of E. 83rd Street Corner of E. 83rd Street 21

  22. E. 86th Street SOE Wall and E. 86th Street SOE Wall and Utility Work Utility Work 22

  23. Work Zone Shift from West to East Side Work Zone Shift from West to East Side Between 95th and 97th Streets Between 95th and 97th Streets 23

  24. SAS SAS Phase 1 Completion: December 2016 Phase 1 Completion: December 2016 Lexington Av- Lexington Av -63rd Street Station 63rd Street Station 24

  25. Second Avenue at E. 63rd Street Second Avenue at E. 63rd Street Future Lexington Av- Future Lexington Av -63rd Street Station 63rd Street Station Entrance Entrance

  26. Second Avenue at E. 72nd Street Second Avenue at E. 72nd Street Future 72nd Street Station Entrance Future 72nd Street Station Entrance 26

  27. Second Avenue at E. 83rd Street Second Avenue at E. 83rd Street Future 86th Street Station Entrance Future 86th Street Station Entrance 27

  28. Second Avenue between E. 95th/96th Street Entrance Second Avenue between E. 95th/96th Street Entrance Future 96th Street Station Future 96th Street Station 28

  29. MTA Capital Construction MTA Capital Construction Michael Horodniceanu Horodniceanu, , Michael Ph.D., P.E., President Ph.D., P.E., President Thank you! March 20, 2012 March 20, 2012 * *Licensed in California

Recommend


More recommend