San Pedro Waterfront Berths 74-84 Promenade and Town Square June - PowerPoint PPT Presentation

San Pedro Waterfront Berths 74-84 Promenade and Town Square June 19, 2019 Agenda A. Overview B. Project Scope Demolition Promenade Town Square C. San Pedro Public Market D. Phasing E. Pedestrian Access/Parking F.


  1. San Pedro Waterfront Berths 74-84 Promenade and Town Square June 19, 2019

  2. Agenda A. Overview B. Project Scope Demolition  Promenade  Town Square  C. San Pedro Public Market D. Phasing E. Pedestrian Access/Parking F. Coordination G. Schedule H. Accomplishments and Next Steps

  3. Project Scope (Overview) • • • Drainage Hardscape/Landscape/Irrigation Museum Landing and • • Intersection Modifications Site Furnishings Overlook • • • Street/Parking Lot Site Removals Floating Dock 7 th Street Ramps • • • Striping Water/Fire Protection • • • Signage Lighting/Power/Security Grading

  4. Project Scope (Demolition) MARINA BLUE BUILDING RESTAURANT B83 Acapulco Site POC VILLAGE B79 Asian Village B78 Soil Remediation B76 - POC Restaurant

  5. Town Square Renderings

  6. Town Square Renderings

  7. Town Square Renderings

  8. Town Square Renderings

  9. Town Square Renderings

  10. Town Square Renderings

  11. Project Scope (Town Square)

  12. San Pedro Public Market

  13. San Pedro Public Market

  14. San Pedro Public Market

  15. San Pedro Public Market

  16. San Pedro Public Market

  17. Coordination Additional Contractors Existing Tenants – access must be • • maintained San Pedro Public Market • Harbor Blvd Extension • San Pedro Fish Market • Town Square Restroom • Café International • Jankovich • Crusty Crab • Utility Companies LA Harbor Sport Fishing • • Los Angeles Maritime Institute (LAMI) • DWP Water • Utro’s • DWP Power • SP Slip • Oil • Downtown Harbor • Future Tenants – San Pedro Public Market •

  18. Project Schedule Advertised: Construction (18 months) January 29, 2019 September 30, 2019 – March 30, 2021 San Pedro Public Market NTP Phase I March 2020 (12 months) Harbor Blvd Extension NTP March 2020 (9-12 months) Town Square Restroom NTP Spring 2020 (6 months) Promenade Phase II ( depends on completion of SPPM Phase I area ) NTP April 2021 (18 months)

  19. Accomplishments and Next Steps ACCOMPLISHMENTS Ports O’ Call Building Demolition • Chevron Remediation • Advertised Promenade and Town Square • Accepted Bids Promenade and Town Square • NEXT STEPS Addendum (March) • Contract Award (August) • Lease Amendment (August) • SPPM NTP (March 2020) • Town Square Restroom (in design) • Promenade – Phase II Project (continue design later this year) •

  20. Questions Questions?