reservoir
play

RESERVOIR SEPTEMBER 2020 PROJECT OBJECTIVES A NEW RESERVOIR IS - PowerPoint PPT Presentation

HIGH SYSTEM RESERVOIR SEPTEMBER 2020 PROJECT OBJECTIVES A NEW RESERVOIR IS NEEDED IN THE HIGH SYSTEM PRESSURE ZONE: TO INCREASE SYSTEM RELIABILITY FIRE FLOW & PEAK DEMAND SUPPLY DURING THE SUMMER TO MEET WASHINGTON STATE


  1. HIGH SYSTEM RESERVOIR SEPTEMBER 2020

  2. PROJECT OBJECTIVES A NEW RESERVOIR IS NEEDED IN THE HIGH SYSTEM PRESSURE ZONE: • TO INCREASE SYSTEM RELIABILITY – FIRE FLOW & PEAK DEMAND SUPPLY DURING THE SUMMER • TO MEET WASHINGTON STATE DEPARTMENT OF HEALTH REQUIREMENTS (WSP) • AFFECTS ALL CITY WATER CUSTOMERS SOUTH OF 14 TH AVE.

  3. HIGH SYSTEM PRESSURE ZONE DOWNTOWN LOWER S. HILL 17 th Ave MID S. HILL (HIGH SYSTEM) Manito Blvd Freya Street 29 th Ave Ray Street Bernard Street 33 rd Ave UPPER S. HILL

  4. CURRENT RESERVOIRS IN THE HIGH SYSTEM PRESSURE ZONE 33 rd & Lamonte Garden Park at 37 th Avenue near Stone Street near Sacajawea

  5. WATER SYSTEM BASICS Upper Glennaire Browne’s Mtn Lower Southview Browne’s Mtn Upper South Hill Top System High System Mid South Hill Pumping Lower South Hill Intermediate Water is pumped to successively higher Downtown Low Pressure Zone reservoirs Wells

  6. LOCATION SELECTION CRITERIA • VACANT LAND (MIN 1 AC, IDEALLY 2 AC) AND IDEALLY CITY OWNED • CLOSE TO TRANSMISSION MAINS – WITHIN 5 OR 6 BLOCKS • NEAR THE CENTER OF THE PRESSURE ZONE • ELEVATION OF APPROX. 2380’ OR HIGHER TO KEEP RESERVOIR HEIGHT TO 100’ OR LESS • RELATIVELY FLAT • MAXIMIZE DISTANCE TO ADJACENT HOMES

  7. LOCATION SELECTION Near center of pressure zone

  8. LOCATION SELECTION Near center of pressure zone Close to transmission main

  9. LOCATION SELECTION Near center of pressure zone Close to transmission main Above about 2380 Note: land slopes downhill north of 29 th Ave and is therefore too low for a tank.

  10. LOCATION SELECTION Near center of pressure zone Close to transmission main Above about 2380 Meets all three criteria

  11. LOCATION SELECTION • Feasible area outlined green below • Feasible tank site must be: • Vacant and at least 1-2 acres • Relatively flat • Ideally city owned 29 th Ave. 29 th Ave. Arthur St Cook St

  12. 29 th Ave. Arthur St. Cook St. This is the feasible area circled green on the preceding exhibit Thurston Ave.

  13. 29 th Ave. Arthur St. Cook St. Feasible site within this area needs to be: • 1-2 acres Thurston Ave.

  14. 29 th Ave. 31 st & Napa SE Blvd Our Lady Of Fatima Arthur St. Garden Park Tank Cook St. Hamblen Park Feasible site within this area needs to be: Hamblen Elem • 1-2 acres Thurston Ave.

  15. 29 th Ave. 31 st & Napa SE Blvd Our Lady Of Fatima Arthur St. Garden Park Criteria to evaluate Tank Cook St. Close to existing t-main? Nr center of pressure zone? Hamblen Park At or above 2380’? Vacant land min 1 ac? Relatively flat? Hamblen Elem City owned? Thurston Ave. Distant from nearby homes?

  16. 29 th Ave. Our Lady Of Fatima Criteria Met Close to existing t-main yes Arthur St. Nr center of pressure zone yes At or above 2380 yes Cook St. Vacant land min 1 ac barely Relatively flat yes City owned no Distant from nearby homes no Other: tank would be large impact to this small area, no guarantee it could be acquired, very Thurston Ave. close to adjacent homes

  17. 29 th Ave. SE Blvd Criteria Met Close to existing t-main yes Nr center of pressure zone yes Arthur St. At or above 2380 yes Vacant land min 1 ac yes Cook St. Relatively flat no City owned no Distant from nearby homes no Other: steeply sloped small property would result in high construction costs, substantial rock removal, this property likely is best used as Thurston Ave. commercial, no guarantee it could be acquired

  18. 29 th Ave. 31 st & Napa Criteria Met Close to existing t-main yes Nr center of pressure zone yes Arthur St. At or above 2380 yes Vacant land min 1 ac barely Cook St. Relatively flat no City owned yes Distant from nearby homes no Other: steeply sloped small parcel would result in high construction costs, substantial rock removal, most highly visible alternative, very Thurston Ave. close to adjacent homes

  19. 29 th Ave. Criteria Met Close to existing t-main yes Arthur St. Nr center of pressure zone yes Garden Park At or above 2380 yes Tank Cook St. Vacant land min 1 ac no Relatively flat no City owned yes Distant from nearby homes no Other: due to small area, questionable construction feasibility, very close to adjacent Thurston Ave. homes

  20. 29 th Ave. Arthur St. Criteria Met Close to existing t-main yes Cook St. Nr center of pressure zone yes At or above 2380 yes Vacant land min 1 ac yes Relatively flat yes Hamblen Elem City owned no Distant from nearby homes yes Thurston Ave. Other: school district not supportive of this idea

  21. LOCATION SELECTION ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA Ferris HS • Relatively flat • Far from t-main – 3,500 add’l feet • 30’ lower results in 130’ tank height • Minimal available land, not city owned • Not near center of zone • Adds at least 50% to project cost 29 th Ave. Arthur St Cook St

  22. LOCATION SELECTION ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA Hazel’s Creek • City owned, relatively flat, plenty of area • Far from t-main – 4,000 add’l feet • 50’ lower results in 150’ tank height • Not near center of zone • Adds at least 50% to project cost 29 th Ave. Arthur St Cook St

  23. LOCATION SELECTION ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA South Complex/KXLY • City owned, relatively flat, plenty of area • Far from t-main – 5,000 add’l feet • 40’ lower results in 140’ tank height • Not near center of zone • Adds at least 50% to project cost 29 th Ave. Arthur St Cook St

  24. LOCATION SELECTION ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA Thorton Murhpy Park • City owned, relatively flat, plenty of area, on t-main route • 100’ lower results in 200’ tank height • Not feasible 29 th Ave. Arthur St Cook St

  25. LOCATION SELECTION ADDITIONAL SITES CONSIDERED OUTSIDE DESIRED AREA Lincoln Park • City owned, relatively flat, plenty of area, roughly the same elevation as Hamblen Park • Far from t-main – 4,000 add’l feet • Adds at least 50% to project cost 29 th Ave. Arthur St Cook St

  26. 29 th Ave. Arthur St. Criteria Met Close to existing t-main yes Cook St. Nr center of pressure zone yes Hamblen Park At or above 2380 yes Vacant land min 1 ac yes Relatively flat yes City owned yes Distant from nearby homes yes Thurston Ave. Other: only site to meet all criteria

  27. RESERVOIR DIMENSIONS • APPROX. 100’ TALL (AT HAMBLEN PARK – VARIES IN OTHER LOCATIONS) • APPROX. 2 MILLION GALLON CAPACITY • 50’ - 60’ DIAMETER AT ITS BASE (I.E., PEDESTAL DIAMETER) • 100’ TANK DIAMETER (I.E., TOP DIAMETER)

  28. HAMBLEN PARK 37 TH AVE. 625’ 625’ NAPA ST. CRESTLINE ST. HAMBLEN ELEMENTARY

  29. HAMBLEN PARK 37 TH AVE. 625’ PARK AREA = 9 AC TANK FOOTPRINT = 0.08 AC <1% OF PARK AREA 625’ NAPA ST. CRESTLINE ST. HAMBLEN ELEMENTARY

  30. HAMBLEN PARK 37 TH AVE. 625’ 200’ 325’ NAPA ST. CRESTLINE ST. Undisturbed To nearest tree buffer home HAMBLEN ELEMENTARY

  31. AVAILABLE RESERVOIR TYPES Hydropillar Water spheroid Standpipe

  32. POST FALLS, ID

  33. MITIGATION MEASURES IF TANK IS LOCATED IN HAMBLEN PARK • START WITH HAMBLEN PARK, POSSIBLY INCLUDE OTHER PARKS • THREE PARKS IN SOUTHGATE NEIGHBORHOOD – HAMBLEN, SOUTH COMPLEX, BEN BURR • ACQUISITION OF CONSERVATION LAND

  34. PROJECT SCHEDULE & NEXT STEPS ✓ PRESENT PROJECT TO SOUTHGATE AND LINCOLN HEIGHTS NEIGHBORHOOD MEETINGS ✓ HOLD COMMUNITY MEETING ADVERTISED TO ALL RESIDENTS WITHIN A SEVERAL BLOCK RADIUS (MID SEPTEMBER)

  35. PROJECT SCHEDULE & NEXT STEPS ✓ PRESENT PROJECT TO SOUTHGATE AND LINCOLN HEIGHTS NEIGHBORHOOD MEETINGS ✓ HOLD COMMUNITY MEETING ADVERTISED TO ALL RESIDENTS WITHIN A SEVERAL BLOCK RADIUS (MID SEPTEMBER) • EVALUATE & INCORPORATE COMMUNITY INPUT & SURVEY RESULTS (FALL 2020) • SELECT TANK SITE AND BEGIN PERMITTING (WINTER 2020)

  36. PROJECT SCHEDULE & NEXT STEPS ✓ PRESENT PROJECT TO SOUTHGATE AND LINCOLN HEIGHTS NEIGHBORHOOD MEETINGS ✓ HOLD COMMUNITY MEETING ADVERTISED TO ALL RESIDENTS WITHIN A SEVERAL BLOCK RADIUS (MID SEPTEMBER) • EVALUATE & INCORPORATE COMMUNITY INPUT & SURVEY RESULTS (FALL 2020) • SELECT TANK SITE AND BEGIN PERMITTING (WINTER 2020) • ANOTHER PUBLIC MEETING (ASSOCIATED WITH PERMITTING, WINTER 2020/21) • INCORPORATE ADD’L COMMUNITY INPUT, FINALIZE PERMITTING (WINTER 2020/21)

  37. PROJECT SCHEDULE & NEXT STEPS ✓ PRESENT PROJECT TO SOUTHGATE AND LINCOLN HEIGHTS NEIGHBORHOOD MEETINGS ✓ HOLD COMMUNITY MEETING ADVERTISED TO ALL RESIDENTS WITHIN A SEVERAL BLOCK RADIUS (MID SEPTEMBER) • EVALUATE & INCORPORATE COMMUNITY INPUT & SURVEY RESULTS (FALL 2020) • SELECT TANK SITE AND BEGIN PERMITTING (WINTER 2020) • ANOTHER PUBLIC MEETING (ASSOCIATED WITH PERMITTING, WINTER 2020/21) • INCORPORATE ADD’L COMMUNITY INPUT, FINALIZE PERMITTING (WINTER 2020/21) • PROJECT DESIGN (WINTER/SPRING 2021) • CONSTRUCTION (2021-2022)

  38. CONCLUDING THOUGHTS • THIS TANK IS AN IMPROVEMENT THE CITY HAS TO MAKE • IF YOU LIVE ANYWHERE SOUTH OF 14 TH AVE., YOU BENEFIT

Recommend


More recommend