replacement multiple locations
play

Replacement Multiple locations Project ID : MED625 Entire Project - PowerPoint PPT Presentation

Distribution Water Main Extension and Replacement Multiple locations Project ID : MED625 Entire Project duration: 2015-2017 Engineering Firm: KS Engineers, PC Contractor: Judlau Contracting, Inc. Project Name: Distribution of Water Main


  1. Distribution Water Main Extension and Replacement – Multiple locations Project ID : MED625 Entire Project duration: 2015-2017 Engineering Firm: KS Engineers, PC Contractor: Judlau Contracting, Inc. Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 1

  2. Project Intent & Purpose: Intent: • Upgrade existing water mains (newer & bigger) Purpose:  Increased population (demand)  Aging infrastructure (increase the useful life) Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 2

  3. Scope of Work Water Main Extension & Replacement  Extension & Replacement of Existing 12” & 20” Distribution Water Mains.  Roadway Restoration.  Installation of Catch Basins and Basin Connections Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 3

  4. Project Duration May 2015 – August 2015 • Delancey Street (between Columbia Street and Pitt Street) • Pitt Street (between Delancey Street and East Houston Street) • Rivington Street (between Pitt Street and Clinton Street) August 2015 – April 2016 • Bowery (between Canal Street and East 4th Street) • First and Second Streets (between Bowery and Second Avenue) • Second Avenue (between East 2 nd Street and East Houston Street ) Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 4

  5. Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 5

  6. Allowable Work Days/Hours: (as per NYC DOT Stipulations)  7:00AM-6:00PM: Monday-Friday (Weekend Work as Needed) • Bowery and auxiliary blocks between Spring Street and East 4th Street  10:00PM-6:00AM: Monday- Friday (Weekend Work as Needed) • Bowery between Canal Street and Spring Street  TBD • Delancey Street between Columbia Street and Pitt Street • Pitt Street between Delancey Street and East Houston Street • Rivington Street between Pitt Street and Clinton Street Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 6

  7. New York City DOT Traffic Stipulations During Construction on Bowery between Canal Street & Spring Street • Night Work 10PM-6AM • 5ft pedestrian walkways • Two 12ft wide Northbound lanes • One 12ft wide Southbound lane • No construction materials on Bowery • 50ft X 8ft of curb lane on one-way streets for enclosed storage of materials • On Delancey Street – Two 11ft wide Eastbound Lanes & Two 11ft wide Westbound Lanes • At other cross streets- One 10ft wide lane on one-way streets, Two 10ft wide lanes on two way streets Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 7

  8. New York City DOT Traffic Stipulations During Construction on Bowery between Spring Street & East 4 th Street • Day Work 7AM-6PM • 5ft pedestrian walkways • Will not impact Northbound and Southbound traffic at the same time. • One 12ft wide Southbound lane • One 12ft wide Northbound lane • No construction materials on Bowery • 50ft X 8ft of curb lane on one-way streets for enclosed storage of materials • At Cross Streets – 11ft wide lanes for one-way traffic & Two 10ft wide lanes for two-way traffic Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 8

  9. COMMUNITY IMPACTS & WHAT TO EXPECT Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 9

  10. COMMUNITY IMPACTS • Pedestrian access will be maintained at all times • Intermittent street closures and/or limited access may be necessary • Bus routes affected by the project: • Bowery (Canal St. – E. 4th St.) – M103 • DDC will monitor operation and work within DEP Noise Code regulations • Sidewalk and/or loading dock access from the curb may be temporarily restricted while work is conducted (coordination will be arranged on a case by case basis) • Parking may be temporarily restricted during construction Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 10

  11. Water Service Interruptions: Water service disruption planned • Typically 8hrs (not consecutive) • 72 hour advance notice will be provided • Specific instruction will be provided prior to water shutoff • If your water service is not restored within 3 hours of the indicated on the Shutoff notice, please contact the community construction Liaison (CCL) or 311 if after hours. Special Needs: • Individuals with special needs should contact the CCL • DDC field staff will work specially with those individuals to minimize certain inconveniences Rodent Control: • A rodent survey will be performed prior to construction • Rodent Control Stations will be installed by a professional rodent control contractor Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 11

  12. Keeping You Informed Office of Community Outreach & Notification, DDC • DDC has assigned Amanda Girgis of KS Engineers, PC as the Community Construction Liaison (CCL). She will keep the community informed by: • Being the first point of contact between the project and the community • Identifying, addressing and/or resolving field inquiries & issues as well as any coordination between the project and needs of the affected stakeholders • Providing regular updates/advisories for the community to better plan around construction activities • CCL contact information: • Name: Amanda Girgis • Email: MED625CCL@gmail.com • Field Office: 84 Bowery, 6th Floor, New York NY 10013 • Telephone : (646)-723-9925 • DDC Website: www.nyc.gov/ddc • DDC Video: www.nyc.gov/webuild • During Non-Working hours, please call 311 and give the Project ID: MED625 Project Name: Distribution of Water Main Extension and Replacement Project ID: MED 625 04/07/15 Slide 12

Recommend


More recommend