CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Central Yavapai Metropolitan Planning Organization Regional Public Open House Transportation Plan March 28, 2012 2011 Update
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE CYMPO developed the Long Range Transportation Plan (LRTP) in 2006. FHWA regulation requires all MPO to update the LRTP every 5 years, if data is available Jurisdictional General Land Use plans currently under revision/ update Economic uncertainty and fiscal accountability Conditions conducive only to verify or re-prioritize the adopted LRTP improvements to fulfill FHWA requirements
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE CYMPO population growth from 2000 to 2010 shows increases varying from 14 % to 65 % by jurisdiction 2010 Census Data will be used to establish a new population forecast baseline Review the programmed short-term (2-5 years) improvements identified in the CYMPO LRTP and verify they are still viable and needed Identify usage of the limited funds for the maximum benefit of the region
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE The Plan so far…. 2006 CYMPO LRTP ( 2006-2011) Projects Status to date State Route 69 (ADOT) Several 6-lanes Segments were completed SR 69/SR 89 Interchange (ADOT) Completed State Route 89A (ADOT) Completed - TI at Viwepoint Drive and Granite Dell Parkway SR 89A/SR 89 Interchange (ADOT) Completed State Route 89 (ADOT) Completed - Reconstructed as four-lane from milepost 324.3 to Center St. Fain Rd (ADOT) Under Construction - Completion early 2013 Great Western Blvd (Yavapai County) Study Completed - Great Western/Glassford Hill Extension Study (SR 89A to SR89 only) Williamson Valley Rd (Yavapai County) Portions Complete Pioneer Pkwy to north of Shadow Valley Ranch Rd: 4-lanes North of Sidewinder Rd to Ironsprings Rd: 4-lanes Pioneer Pkway to 0.25 miles north of Pioneer Pkwy: 4-lanes Tribal Connector (Yavapai Apache Nation) Completed Side Rd (Prescott) Completed - 0.12 miles north of Centerpoint East Dr: Paved, 2-lanes Sundog Connector (Prescott) In Progress - Corridor Study New Facility from SR 169 to Lakeshore Dr Study Completed - SR 169 to Fain Rd Planning Study (Yavapai County) Chino Valley Bypass (Chino Valley) Study Completed - Chino Valley Extension Airport Loop Rd (Prescott) Study completed - Airport Area Transportation Plan Corridor Studies In Progress I-17 to Fain Rd Connector (Schedule to be completed Spring 2012) Willow Creek Rd/SR 89 Intersection Redesign State Route 89 (ADOT) Not Completed - Widen to 4-lanes from milepost 324.3 to SR 89A
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Analyze 2010 Census population and household data Identify current needs Identify new 2030 population thresholds Identify regional employment growth and magnitude Identify needs and deficiencies using the new We Are Here 2030 projections Verify if adopted LRTP improvements address the new 2030 demand Review projects priorities
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Year 2010 Census Prescott 39,843 Prescott Valley 38,822 Dewey-Humboldt 3,894 Chino Valley 10,817 Williamson CDP 5,438 CYMPO Planning Area 121,783 Total Influence Area 131,406
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Severely congested roadways SR 89 - SR 89A to Outer Loop Rd Moderately congested roadways Portions of SR 69 from Robert Rd to SR 89
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Year 2010 Year 2030 2030 Growth Census CYMPO AZDoA Rate Prescott 39,843 62,245 68,099 2.81% Prescott Valley 38,822 64,703 70,739 3.33% Dewey-Humboldt 3,894 5,161 4,295 1.63% Chino Valley 10,817 19,038 30,286 3.80% Williamson CDP 5,438 9,640 9,814 3.86% CYMPO Planning Area 121,783 205,935 3.45% Total Influence Area 131,406 225,998 3.60% Population estimates from the Arizona Department of Administration (AZDoA) 80,000 70,000 60,000 50,000 40,000 30,000 20,000 10,000 0 Prescott Prescott Dewey- Chino Williamson Valley Humboldt Valley CDP 2010 Census 2030 CYMPO 2030 AZDoA
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Severely congested roadways SR 89 – Willow Lake Rd to Outer Loop Rd Williamson Valley Rd – Pioneer Pkwy to Outer Loop Rd Outer Loop Rd - Williamson Valley Rd to SR 89 SR 69 – Glassford Hill to Prescott Lakes Pkwy SR 89A – Glassford Hill Rd to SR 89 Glassford Hill Rd – Lakeshore Dr to SR 89A Viewpoint Dr – north of SR 89A Willow Creek Rd – Willow Lake Rd to SR 89 Moderately congested roadways SR 169 – I-17 to SR 69 Portions of SR 69 from Robert Rd to SR 89 Willow Creek Rd – Willow Lake Rd to SR 89 Willow Lake Rd – from Willow Creek Rd to SR 89 Pioneer Pkwy – Williamson Valley rd to Willow Creek Rd Prescott Lakes Pkwy – SR 69 to SR 89
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Project number does not signify priority. It is used only as identifier between the list and the map
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Assess the improvements needed to address current and future deficiencies Verify if the 2012-2020 LRTP improvements are still valid and needed Review and re-prioritize projects based on regional impact and funding availability Present findings to the public Finalize project list by June 2012
CYMPO REGIONAL TRANSPORTATION PLAN 2011 UPDATE Questions ? nswers