projects and choosing
play

Projects and Choosing the Best Project Delivery Method Ryan Toner - PowerPoint PPT Presentation

Session 4: Managing Projects and Choosing the Best Project Delivery Method Ryan Toner | Vice President | Dibble Engineering Renju Abraham, PE PM / Associate Engineer Burns & McDonnell Mike Smejkal, PE, AAE VP of Planning &


  1. Session 4: Managing Projects and Choosing the Best Project Delivery Method Ryan Toner | Vice President | Dibble Engineering

  2. Renju Abraham, PE PM / Associate Engineer Burns & McDonnell Mike Smejkal, PE, AAE VP of Planning & Engineering Tucson Airport Authority Sandy Kukla, AIA Executive Vice President DWL Architects + Planners Session Mike Hill Senior Project Manager Sundt Construction, Inc. Speakers Tim Morrison, PE, PMP Program/Project Manager FAA Phoenix ADO

  3. Current Trends in SWAAAE Construction 2019 Delivery Methods Renju Abraham, PE

  4. SWAAAE 2019 Various Project Delivery Methods • Design-Bid-Build Alternative • Design-Build Delivery • DBFOM, DBOO, DBOOM • Progressive D-B D-B-B Design-Build Design-Build-Operate-Maintain • CM at Risk CM at Risk • P3 CM/Agent Job Order Contracting • IPD P3 • Job Order Contracting • CM/Agent (Multi-Prime)

  5. SWAAAE 2019 What is the best construction delivery method? It depends on who you ask!

  6. SWAAAE 2019 The “ MacLeamy ” Curve

  7. Method #1 Traditional Design Design-Bid Bid- Build Build

  8. SWAAAE 2019 Design-Bid-Build Owner Competitive QBS Bids Designer Contractor The Lawsuit! Design Construction Design Bidding & Value Procurement Engineering

  9. Method #2 Design Design-Build Build

  10. SWAAAE 2019 Design-Build Owner Best Value Design-Builder A/E Time Saved Design Construction Design-Build Procurement

  11. SWAAAE 2019 Design-Build Flavors Sprinkle in: • Finance • Finance-Operate-Maintain (DBFOM) • Own-Operate (DBOO) • Own-Operate-Maintain (DBOOM) • Lease-Back

  12. SWAAAE 2019 Design- Build; Fast Track

  13. SWAAAE 2019 Why Design-Build? • Sing Single le Point oint Respo esponsibil nsibility ity & & Accounta Accountabil bility ity • The he Numbe Number r 1 F 1 Fac actor tor • Faster aster • Chea Cheaper per

  14. 2018 Study: 212 Projects Found that Design-Build had: 1. Lower overall cost growth 2. No schedule growth 3. Faster delivery speed

  15. Method #3 CM a CM at Ri t Risk sk

  16. SWAAAE 2019 CM @ Risk Trade Subs Owner Bonds Competitive QBS Bids Designer CM at Risk Bond QBS CM@R Hired Design Construction Design Trade Subs Procurement Hired

  17. SWAAAE 2019 CM@Risk • Normally involves hiring CM after design has started or in progress • CM does perform the work – guarantees price, schedule, and quality • Award usually made on a qualitative basis, and not strictly on price • On public work, CM bonds the entire contract

  18. SWAAAE 2019 CM@Risk • Special Legislation needed for public projects because… • CM hired on qualifications, not low bid • Violates competitive bidding laws • Award to CM prior to knowing the Subs • Violates “subcontractor listing laws” in some states

  19. Method # 4 Public Public-Priva Private te Par artner tnerships ships (P3) (P3)

  20. SWAAAE 2019 P3 • Used commonly outside of the U.S., especially in the U.K. • Not really alternative project delivery method, as much as an alternative project funding mechanism for public works projects • Financial difficulties in many public agencies limit the funds available for public projects • This makes P3 a more enticing option • −>“Buy Now, Pay Later”

  21. Method # 5 Job Or ob Order der Contr Contracting acting (JOC) (JOC)

  22. SWAAAE 2019 Job Order Contracting • Also called “IDIQ” • Indefinite Delivery, Indefinite Quantity • Common for recurring but (often) relatively minor design or construction work • Scope and timing difficult to know in advance • Often involves repair, remodeling, or repetitive work • Sometimes used for larger, new projects

  23. Method # 6 CM CM-Agent/ Agent/ Multi Multi-Prime Prime

  24. Bonds CM@Risk Trade Primes Owner Bid Negotiated QBS No Designer CM-Agent Bond Manage • No Guarantees on (Sometimes) Cost or Quality Time Saved Design Construction Design & CM Trade Contractor Procurement Procurement

  25. SWAAAE 2019 How do you select a method? • Owner shall determine the most important criteria/ objective of the project • Stakeholder/ community input is a key factor • Be considerate of funding sources and legislations • Flatwork versus vertical • Familiarity and past success at the airport may also be considered

  26. Owner’s SWAAAE Perspective 2019 Mike Smejkal, PE, AAE

  27. SWAAAE 2019 Owner’s Perspective Design Bid Build Design Bid Build • Easily Defined Phasing & Scope • Mill & Overlay

  28. SWAAAE 2019 Owner’s Perspective CMAR Sample Projects • Terminal Apron Reconstruction Project (AIP Funded) • Complicated Phasing • Multiple Grant Years w/ complex systems (400 Hz & Fueling System) • FAA reviews design (for standards/eligibility) prior to GMP development • Terminal Optimization Project (PFC Funded) • Complicated Phasing • Complicated cutover of critical systems. Scoring CMAR • Approach to Teaming, Describe competitive proposal process • AZ – Fee not allowed in

  29. SWAAAE 2019 Owner’s Perspective CMAR • 2 Gates Closed at a time New 16” PCC on Recycled PCC Base • • Started August 2013 New Trench Drain System • • 18-20 month total duration Hydrant Fueling & 400 Hz Modifications • • $45-50M Budget

  30. SWAAAE 2019 Owner’s Perspective CMAR - Relocate/Expand Security Checkpoints - Expand Concession Opportunities - Upgrade 50 year old building infrastructure

  31. SWAAAE 2019 Owner’s Perspective Design Build Design Build • TAA’s Solar Phase 1 (AIP Funded) • No FAA Standards to follow • Basic Requirements (1MW of Power) over area in parking lot (min. # of stalls must be maintained) • Need a detailed requirements document for RFP Scoring • SOQ – Shortlist • Technical Proposal Scored based on shortlist • Teaming & Approach is heavily weighted • After Technical Proposal is scored open sealed costs

  32. SWAAAE 2019 Owner’s Perspective Design Build

  33. SWAAAE 2019 Owner’s Perspective Summary • Choose Best Method for each project • Relationship is different with A/E & Contractor for each method • Clearly communicate with FAA & State (FSL or SL) on signoffs • Airfield Civil/AIP funded – CMAR better than Design Build

  34. Consultant’s SWAAAE Perspective 2019 Sandy Kukla, AIA

  35. SWAAAE 2019 Consultant’s Perspective PHX Sky Harbor International Airport Terminal 3 Modernization Design/Build PHX Terminal 3 Modernization CMAR/Design-Bid-Build/JOC TUS Terminal Optimization Project AZA West Terminal Expansion Lessons Learned

  36. SWAAAE 2019 Consultant Perspective - Design/Build PHX Sky Harbor International Airport Terminal 3 Modernization 25 Gates $590 M Total Project 3 1.9 M Square Feet 11.2 Million Annual Pax 1 2

  37. SWAAAE 2019 Consultant Perspective - Design/Build PHX Sky Harbor International Airport Terminal 3 Modernization

  38. SWAAAE 2019 Consultant Perspective - Design/Build PHX Sky Harbor International Airport Terminal 3 Modernization Complex Project • Scale • Active Campus • Toughest Part Came First • Phasing – Funding and Constructability • Multiple Stakeholders - 10 Airlines • Unique Design

  39. SWAAAE 2019 Consultant Perspective - Design/Build PHX Sky Harbor International Airport Terminal 3 Modernization D/B Considerations • Is a Project Definition Manual Required? • How does communication occur between the owner and designer? • Who is the client?

  40. SWAAAE 2019 Consultant Perspective – CMAR/DDB/JOC Tucson International Airport Terminal Optimization Project JOC / Design-Bid-Build CMAR

  41. SWAAAE 2019 Consultant Perspective – CMAR/DDB/JOC Phoenix-Mesa Gateway Airport Design/Bid/Build CMAR JOC

  42. SWAAAE 2019 Consultant Perspective – DBB Phoenix-Mesa Gateway Airport • Dependent on market • Phasing by Designer • Defined Scope • Detailed documents • Contractor input is voluntary • Based on Bid – Who is your Contractor? • Phasing by Designer

  43. SWAAAE 2019 Consultant Perspective – DBB/JOC/CMAR Comparison of CMAR to DBB Comparison of CMAR to JOC

  44. SWAAAE 2019 Consultant Perspective – JOC Tucson International Airport Authority Department Relocations (Demo) • Small Scale • Demolition/Unknown Conditions • On-call Contractor • Minimal Documents • Reduced Permit Requirements • Contractor may be unfamiliar with typical process

  45. SWAAAE 2019 Consultant Perspective – CMAR Tucson International Airport Terminal Optimization Project • Continuous Operations • Complex Phasing • Early Document Packages • Time between Design Phases for CMAR Review • Time for Value Engineering/ Scope Reduction

  46. SWAAAE 2019 Consultant Perspective – CMAR Phoenix-Mesa Gateway Airport • CMAR Selection Process • Better Construction Staffing • CMAR Design Assist • Project Start Preparation • Team Project Goals • Quality

  47. SWAAAE 2019 Consultant Perspective – Lessons Learned Laughlin/Bullhead Int’l Airport Aircraft Rescue Fire Fighting Station 1. Do an analysis 3. Understand your organization’s 2. Establish your project criteria, characteristics. vision and goals. 4. No One-size fits all 5. Set up your project for Success.

Recommend


More recommend