presented by jeffrey r appelbaum
play

Presented by Jeffrey R. Appelbaum Pro roject Scope pe Buil - PowerPoint PPT Presentation

Presented by Jeffrey R. Appelbaum Pro roject Scope pe Buil ildin ing Siz ize -- -- 1,003, 03,000 s 000 sf Site e Area -- -- 14.6 14.6 A Acr cres Dev evelopme ment B Budget--$4 $465M 65M Const nstruc


  1. Presented by Jeffrey R. Appelbaum

  2.  Pro roject Scope pe Buil ildin ing Siz ize -- -- 1,003, 03,000 s 000 sf ◦ Site e Area -- -- 14.6 14.6 A Acr cres ◦ Dev evelopme ment B Budget--$4 $465M 65M ◦ Const nstruc uction n Sche hedul dule ◦ Const struction S Sta tart D t Date te– Januar uary 3 3, 2011 11  Substant antial al C Completion D n Date – Au August 3 31, 2 2013   Project C t Compone nents nts Conve nvent ntion n Center er – ◦ 767,000 7,000 sf unde der Mal alls B B an and C d C  230,000 sf high quality exhibit hall space  60,000 sf high tech, flexible meeting room space  31,000 sf column free ballroom space  Medi dical Mart ◦ 235,000 5,000 sf a at St. C . Clair a and O Ontario  100,000 sf permanent show room space  11,000 sf junior ballroom  2,000 sf retail  Mall B and d C Hardsc dscape ape and d Softsc scape pe ◦

  3.  75% Cons nstr truct uction D n Docum cument S ent Set Appro rove ved  100% 0% Cons nstruct uction D n Docum cumen ent Set et - Prepa pared t d to Recom ommend d for Con ondi diti tion onal Appr prov oval ◦ Ce Cert rtain in ele lements in in pro roce cess of fin inal l refineme ment

  4.  PMC ◦ Lead--Steve Zannoni  Conventional Wisdom ◦ Contract Amendment #3; Services for Remainder of Project

  5.  Unique and proprietary convention center knowledge  Consulted with the County since 2008  Drafted the County Program Requirements  County’s watchdog regarding operational and program requirements  Review and advice has assisted in causing developer to make major design modifications for benefit of County

  6.  Current Contract through Design Development Phase (did not receive full services contract at outset of Project); Contract Amount to date is $278,400  Amendment # 3 is for $270,000 (services for remainder of Project)  Amendment #3 Scope of Services are through construction and commissioning including: ◦ Program and Operational Milestone Reviews ◦ Construction Document Reviews ◦ Design revision Reviews ◦ Operational Scope and Budget Reviews ◦ Facility Commissioning

  7.  On sch chedule le for r Augu gust 31, 31, 2013 2013 Substantia ial l Comple leti tion  To To date, e, $71. 71.2M 2M of of co construct ction in in pla lace ce ($ ($8. 8.26M 26M durin ring g mon onth th of of August st). ).  Pro roject ct is is 20 20 % co comple lete based on billin illings gs to dat date for Work in n Plac ace and and Stored d Mat Materials  45 of 54 Bid d pac packages have have be been awar awarded  On sch chedule le to re rece ceiv ive LEED LEED Silv ilver r Ce Cert rtif ifica icatio ion

  8. .

  9.  8/26/11 -- East Convention Center Concourse (Formwork/Rebar Placement)

  10. 9/10/11– Pouring Final Caisson (66 Caissons—All accepted!)

  11. Pouring One of Three Mat Slabsr

  12. 9/20/2011 --Erecting Steel; Ballroom Pre- Function Area

  13. On-Site Ballroom Truss Assembly (120 ft -- 1 st of 30 trusses)

  14. Crane positioning for Truss pick

  15. Today—First Truss lifted in Place!

  16.  St. Clair Crack  Methane Collection  West 3d Street Elevated Roadway

  17.  Data Collection has been completed ◦ Soil borings, inclinometers, tilt meters, crack meters, Ground Penetrating Radar, video of existing sewer  No Material Impact to Project Construction/Schedule  Design/Builder Consultant’s Recommendations ◦ St.Clair can be temporarily patched and reopened immediately ◦ Long term resurfacing at conclusion of project  City has requested additional data– all data has been provided  Meeting scheduled to discuss reopening  Responsibility for costs

  18.  After installation of caissons and micropiles, low levels of methane gas continued to be observed  Design Builder engaged SCS Engineers to investigate; result is design and implementation of conventional gas collection and venting system  Cost-- $200k (to be covered by Developer’s Contingency)

  19.  Engineers have discovered severe deterioration of underside of existing elevated road structure  The “bridge deck” needs to be replaced  The new road must be operational by 3/1/11 in order to avoid cost and schedule impacts to the project GMP  Must start the new deck replacement design by no later than 10/7/11  Probable Cost -- $1.6M

  20. CLEVELAND MEDICAL MART TIMELINE 2011 2012 2013 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Demolition Deep Piles & Caisson Foundations Steel Erection Pouring of New Concrete Deck Begin Installation of Med Mart Façade Buildings Weather Enclosed Interior Build-Out Tenant Build-Out at Med Mart Grand Opening

  21. June 2011 Aug 2011 234 MM 234 MM May 2011 Summer 2012 185 MM 580MM +Fitout March 2011 145 MM

  22.  To date…only 1 accident resulting in lost time.

  23. Contr ontract G Goa oal Actu tual to to Date te SBE 25% 32%* County Residency 40% 47% City Residency 20% 22% *42 SBE subcontractors have been hired by their respective prime contractors for the first time. For period concluding 8/21/2011

  24.  We have agreed to identify all SBE contractors and post on County Website

  25.  We have agreed to post breakout hours expended by prime contractor, according to: ◦ Jurisdiction (City or County) ◦ Minority ◦ Female

  26.  Current project includes “Baseline” Mall Improvements  Group Plan Commission seeks enhancements; but certain design elements must be incorporated now to avoid foreclosing future opportunities  Design must also be sufficiently advanced to demonstrate possible enhancements

  27.  Phase One – Masterplan / CMMCC Baseline Update  Phase Two – Group Plan Component Confirmation and Infrastructure Incorporation in CMMCC Baseline Documents ◦ Incorporate the necessary utilities and infrastructure layout, connections, access, and routing path to allow the Group Plan Masterplan enhancements to be realized in subsequent phases. ◦ (Phase 2A)--Conceptual Work ◦ (Phase 2B)–- CD Revisions  Phase Three – Fund Raising Materials.

Recommend


More recommend