Presented by Jeffrey R. Appelbaum
Pro roject Scope pe Buil ildin ing Siz ize -- -- 1,003, 03,000 s 000 sf ◦ Site e Area -- -- 14.6 14.6 A Acr cres ◦ Dev evelopme ment B Budget--$4 $465M 65M ◦ Const nstruc uction n Sche hedul dule ◦ Const struction S Sta tart D t Date te– Januar uary 3 3, 2011 11 Substant antial al C Completion D n Date – Au August 3 31, 2 2013 Project C t Compone nents nts Conve nvent ntion n Center er – ◦ 767,000 7,000 sf unde der Mal alls B B an and C d C 230,000 sf high quality exhibit hall space 60,000 sf high tech, flexible meeting room space 31,000 sf column free ballroom space Medi dical Mart ◦ 235,000 5,000 sf a at St. C . Clair a and O Ontario 100,000 sf permanent show room space 11,000 sf junior ballroom 2,000 sf retail Mall B and d C Hardsc dscape ape and d Softsc scape pe ◦
Final G l Genera ral B l Build ildin ing Permit mit i issued by by City on on October 2 27, 2011 Final al design ap approval als g gran anted b by y Lan andmar arks, City P y Plan anning an and Design gn Revie iew—Onl nly o outsta tand nding ng approval re required is is fo for e r exterior sig signage. MMP MMPI is finaliz lizin ing l lightin ing and i interio rior r alterna nates tes
On sch chedule le for r Augu gust 31, 31, 2013 2013 Substantia ial l Comple leti tion ◦ Why is is th this is re rema markable le? Wet ettes est Y Yea ear r on R Rec ecord prio rior t to 2011 –-53. 53.83 83 inche ches of of rain in Rain infall i ll in 2 2011– 65.32 32 inche ches—21% 21% greater t than n the prior r r record rd!!! !!!
Th Thro rough gh 12/ 12/31/ 31/2011, 2011, total pay applic licatio ions from m MMP MMPI = $ = $145. 145.7M 7M ◦ Incl cludes es $ $123. 123.5M 5M of of constru truction tion in place ( ($13. 13.6M 6M du durin ring mont nth h of of Decem ecember) Pro roject ct is is 35% 35% co complete based on billin illings gs to dat date for Work in n Plac ace and and Stored d Mat Materials 53 of 54 Bid d pac packages have have be been sub ubmitted for appr approval On sch chedule le to re rece ceiv ive LEED LEED Silv ilver r Ce Cert rtif ifica icatio ion
Conventi ntion C on Cente nter N North o h of side Lakesi Structural Steel is complete. • Concrete slab on metal pan deck is • complete. Water-proofing installation started • over the Ballroom. The Loading Dock concrete apron • walls continue - 60% complete. MEP rough-in continues at the • Ballroom level. Water-proofing continues at the • exterior foundation walls, weather permitting. Block (masonry) work continues in • the Ballroom and Meetings rooms areas. Backfilling continues at the West wall • on both the North and South sides of Lakeside.
Con onvention Center Sou South of of Lake keside Water proofing at the East Mall Drive • is over 95% complete, the concrete is curing a few areas. Ductwork installation is • approximately 60% complete on the East Concourse level. The main & branch sprinkler lines at • the East Concourse are approximately 75% complete. Steel erection continues at the West • Course level, they are currently working on two sequences the final sequence will be starting this week. Metal pan Stair No. 14 for sector K • (north end of the East Concourse) will be starting this week. The first sequences of Exhibit Hall • structural steel is scheduled to arrive this week - including tree columns. Site-work for East Mall Drive is • scheduled to start on next week.
Note: Drive to be completed and turned over to City in March 2012!!
Tree Column Fabrication
Medic ical Mart ( t (West B t Block) Steel erection and • detailing continues on multiple levels, the final section of the middle Atrium truss was set last Friday. Concrete slab pour prep • continues, the balance of the 2 nd floor was poured last Friday. The next pour on the 3 rd floor is scheduled for this week. Fire-proofing structural • steel started on the 1 st floor. Metal pan Stair No. 29 • for the Northwest corner erection started last week.
Public ic Audit itoriu ium Separation Work as follows: • • The 3 rd connector HVAC work is complete • The separation punch-list is complete. Restoration Work as follows: • • Interior door prep continues at the North & South entrances. The marble tile and granite has been approved and the order has been placed. The stone is scheduled to arrive next week. • Granite in-fill work and interior plaster restoration is scheduled to start in the next few weeks. West st Third d Bridg dge Const nstruc uction Wall restoration work continues, the final pour • was completed last week Friday. Sidewalks pours are scheduled for later this • week, weather permitting. The goal is the open the drive by the end of • February.
St. Clair Crack West 3d Street Elevated Roadway
Temporary repairs completed on November 11, 2011 St. Clair reopened Turner and City are discussing scope of final repair No cost to County
Work commenced in November Completion scheduled for 2/28/2012 Probable Cost -- $1.6 M MMPI to fund out of its contingency; MMPI has withdrawn request for County funding subject to reservation of right
CLEVELAND MEDICAL MART TIMELINE 2011 2012 2013 Q Q1 Q2 Q3 Q4 Q2 Q3 Q4 Q1 Q2 Q3 Q4 1 Demolition Deep Piles & Caisson Foundations Steel Erection Pouring of New Concrete Deck Begin Installation of Med Mart Façade Buildings Weather Enclosed Interior Build-Out Tenant Build-Out at Med Mart Grand Opening
To date…only 1 accident resulting in lost time.
Contr ontract G Goa oal Actu tual to to Date te SBE 25% 32%* County Residency 40% 48% City Residency 20% 21% * Note: 138 SBE subcontractors of which 39 have been hired by their respective prime contractors for the first time. For period concluding 12/11/2011
Conventions and Meetings ◦ MMPI reports 35 letters of intent/contracts Estimated impact-- $82,450,000 according to Positively Cleveland Medical Mart ◦ 35 leases placed in the hands of Phase 1 and 2 LOI holders. As of today, 8 leases signed, others in negotiation. Advisory Committee ◦ First Meeting- December 16, 2011 ◦ Next Meeting- February 29, 2012
Proposal: 3 way split (County, City and MMPI) of initial costs to preserve Group Plan opportunities (not to exceed $200k per party) Original Budget--$507,300 Design Cost excluding $82,400 of physical work (sleeves and conduit) Revised Budget--$243,690 excluding physical work Proposed Funding Agreement has been prepared Sleeve and Conduit Work must be authorized by 3/1/2012
Recommend
More recommend