presented by jeffrey r appelbaum
play

Presented by Jeffrey R. Appelbaum Pro roject Scope pe Buil - PowerPoint PPT Presentation

Presented by Jeffrey R. Appelbaum Pro roject Scope pe Buil ildin ing Siz ize -- -- 1,003, 03,000 s 000 sf Site e Area -- -- 14.6 14.6 A Acr cres Dev evelopme ment B Budget--$4 $465M 65M Const nstruc


  1. Presented by Jeffrey R. Appelbaum

  2.  Pro roject Scope pe Buil ildin ing Siz ize -- -- 1,003, 03,000 s 000 sf ◦ Site e Area -- -- 14.6 14.6 A Acr cres ◦ Dev evelopme ment B Budget--$4 $465M 65M ◦ Const nstruc uction n Sche hedul dule ◦ Const struction S Sta tart D t Date te– Januar uary 3 3, 2011 11  Substant antial al C Completion D n Date – Au August 3 31, 2 2013   Project C t Compone nents nts Conve nvent ntion n Center er – ◦ 767,000 7,000 sf unde der Mal alls B B an and C d C  230,000 sf high quality exhibit hall space  60,000 sf high tech, flexible meeting room space  31,000 sf column free ballroom space  Medi dical Mart ◦ 235,000 5,000 sf a at St. C . Clair a and O Ontario  100,000 sf permanent show room space  11,000 sf junior ballroom  2,000 sf retail  Mall B and d C Hardsc dscape ape and d Softsc scape pe ◦

  3.  Final G l Genera ral B l Build ildin ing Permit mit i issued by by City on on October 2 27, 2011  Final al design ap approval als g gran anted b by y Lan andmar arks, City P y Plan anning an and Design gn Revie iew—Onl nly o outsta tand nding ng approval re required is is fo for e r exterior sig signage.  MMP MMPI is finaliz lizin ing l lightin ing and i interio rior r alterna nates tes

  4.  On sch chedule le for r Augu gust 31, 31, 2013 2013 Substantia ial l Comple leti tion ◦ Why is is th this is re rema markable le?  Wet ettes est Y Yea ear r on R Rec ecord prio rior t to 2011 –-53. 53.83 83 inche ches of of rain in  Rain infall i ll in 2 2011– 65.32 32 inche ches—21% 21% greater t than n the prior r r record rd!!! !!!

  5.  Th Thro rough gh 12/ 12/31/ 31/2011, 2011, total pay applic licatio ions from m MMP MMPI = $ = $145. 145.7M 7M ◦ Incl cludes es $ $123. 123.5M 5M of of constru truction tion in place ( ($13. 13.6M 6M du durin ring mont nth h of of Decem ecember)  Pro roject ct is is 35% 35% co complete based on billin illings gs to dat date for Work in n Plac ace and and Stored d Mat Materials  53 of 54 Bid d pac packages have have be been sub ubmitted for appr approval  On sch chedule le to re rece ceiv ive LEED LEED Silv ilver r Ce Cert rtif ifica icatio ion

  6. Conventi ntion C on Cente nter N North o h of side Lakesi Structural Steel is complete. • Concrete slab on metal pan deck is • complete. Water-proofing installation started • over the Ballroom. The Loading Dock concrete apron • walls continue - 60% complete. MEP rough-in continues at the • Ballroom level. Water-proofing continues at the • exterior foundation walls, weather permitting. Block (masonry) work continues in • the Ballroom and Meetings rooms areas. Backfilling continues at the West wall • on both the North and South sides of Lakeside.

  7. Con onvention Center Sou South of of Lake keside Water proofing at the East Mall Drive • is over 95% complete, the concrete is curing a few areas. Ductwork installation is • approximately 60% complete on the East Concourse level. The main & branch sprinkler lines at • the East Concourse are approximately 75% complete. Steel erection continues at the West • Course level, they are currently working on two sequences the final sequence will be starting this week. Metal pan Stair No. 14 for sector K • (north end of the East Concourse) will be starting this week. The first sequences of Exhibit Hall • structural steel is scheduled to arrive this week - including tree columns. Site-work for East Mall Drive is • scheduled to start on next week.

  8. Note: Drive to be completed and turned over to City in March 2012!!

  9. Tree Column Fabrication

  10. Medic ical Mart ( t (West B t Block) Steel erection and • detailing continues on multiple levels, the final section of the middle Atrium truss was set last Friday. Concrete slab pour prep • continues, the balance of the 2 nd floor was poured last Friday. The next pour on the 3 rd floor is scheduled for this week. Fire-proofing structural • steel started on the 1 st floor. Metal pan Stair No. 29 • for the Northwest corner erection started last week.

  11. Public ic Audit itoriu ium Separation Work as follows: • • The 3 rd connector HVAC work is complete • The separation punch-list is complete. Restoration Work as follows: • • Interior door prep continues at the North & South entrances. The marble tile and granite has been approved and the order has been placed. The stone is scheduled to arrive next week. • Granite in-fill work and interior plaster restoration is scheduled to start in the next few weeks. West st Third d Bridg dge Const nstruc uction Wall restoration work continues, the final pour • was completed last week Friday. Sidewalks pours are scheduled for later this • week, weather permitting. The goal is the open the drive by the end of • February.

  12.  St. Clair Crack  West 3d Street Elevated Roadway

  13.  Temporary repairs completed on November 11, 2011  St. Clair reopened  Turner and City are discussing scope of final repair  No cost to County

  14.  Work commenced in November  Completion scheduled for 2/28/2012  Probable Cost -- $1.6 M  MMPI to fund out of its contingency; MMPI has withdrawn request for County funding subject to reservation of right

  15. CLEVELAND MEDICAL MART TIMELINE 2011 2012 2013 Q Q1 Q2 Q3 Q4 Q2 Q3 Q4 Q1 Q2 Q3 Q4 1 Demolition Deep Piles & Caisson Foundations Steel Erection Pouring of New Concrete Deck Begin Installation of Med Mart Façade Buildings Weather Enclosed Interior Build-Out Tenant Build-Out at Med Mart Grand Opening

  16.  To date…only 1 accident resulting in lost time.

  17. Contr ontract G Goa oal Actu tual to to Date te SBE 25% 32%* County Residency 40% 48% City Residency 20% 21% * Note: 138 SBE subcontractors of which 39 have been hired by their respective prime contractors for the first time. For period concluding 12/11/2011

  18.  Conventions and Meetings ◦ MMPI reports 35 letters of intent/contracts  Estimated impact-- $82,450,000 according to Positively Cleveland  Medical Mart ◦ 35 leases placed in the hands of Phase 1 and 2 LOI holders. As of today, 8 leases signed, others in negotiation.  Advisory Committee ◦ First Meeting- December 16, 2011 ◦ Next Meeting- February 29, 2012

  19.  Proposal: 3 way split (County, City and MMPI) of initial costs to preserve Group Plan opportunities (not to exceed $200k per party)  Original Budget--$507,300 Design Cost excluding $82,400 of physical work (sleeves and conduit)  Revised Budget--$243,690 excluding physical work  Proposed Funding Agreement has been prepared  Sleeve and Conduit Work must be authorized by 3/1/2012

Recommend


More recommend