piner er s stad adium f fiel eld lights
play

Piner er S Stad adium F Fiel eld Lights Project Status Update - PowerPoint PPT Presentation

Piner er S Stad adium F Fiel eld Lights Project Status Update Backgr kgrou ound This project consists of: Stadium Lighting PA system and speakers Sound wall Required by Environmental Impact Report (EIR) Site


  1. Piner er S Stad adium F Fiel eld Lights Project Status Update

  2. Backgr kgrou ound  This project consists of:  Stadium Lighting  PA system and speakers  Sound wall – Required by Environmental Impact Report (EIR)  Site improvements:  Site Paving (ADA Requirements) and Landscaping  The project is partially Owner Furnished-Contractor Installed, which means that the District will direct purchase the lighting and appurtenant equipment and a contractor will install it.  The balance of the work; site work and landscaping, PA/speaker system and concrete sound wall will be included in the bidding contractor’s scope of work.

  3. Statu tus a s as of 5/ 5/10 10/1 /17  The Musco Lighting for this project was board approved.  The construction documents are 80% complete.  DSA submission scheduled for May 24, 2017  Tentative date range for DSA approval is July 12 – August 16.  Bidding schedule is as follows; ◦ 1 st Advertisement June 6 ◦ 2 nd Advertisement June 13 ◦ Pre-Bid Job Walk June 15 ◦ Contractor Q&A/Addenda June 15 – 20 ◦ Bids Due June 27

  4. Lightin ing (Example le)

  5. Pre reca cast st C Concrete Fe Fence  Required by Environmental Impact Report  Used to deflect sound from neighborhood homes  Average wall height 12’  Meets California Environmental Quality Act BASE SCOPE: 10-13 FT HIGH FENCE LOCATION (CEQA) requirements ADJACENT TO TRACK & FOOTBALL FIELD

  6. Prec ecas ast C Concrete F e Fence ( e (Exam ample) e) Samples – For Illustrative Purposes

  7. Mileston ones es Completion of Construction Documents May 23 DSA Submission May 24 Bidding Process June 6 – 22 Estimated DSA Approval July 12 – August 16 Board Approval for Contract Award TBD after DSA Approval Construction Timeframe 2-3 Months

Recommend


More recommend