Performance Review August 2018 Safety Overview As of August 31, - - PowerPoint PPT Presentation
Performance Review August 2018 Safety Overview As of August 31, - - PowerPoint PPT Presentation
Performance Review August 2018 Safety Overview As of August 31, 2018 WRPS Tank Operations Contract has worked 8,063,370 hours There were no Recordable (570 days) without a Lost Time Workday Injury cases in August 2018 and 630,308 hours (45
2
Safety Overview
Six First Aid cases in August:
- While riding in government
vehicle employee felt irritation to eye after taking off safety glasses.
- Two employee’s reported
headache from an odor while working by C-Farm
- While stepping over a tube
block employee tripped and fell causing an abrasion to hip.
- Employee closed fingers in
vehicle door causing an abrasion.
- When donning SCBA
employee felt bug fly in ear causing irritation to ear.
As of August 31, 2018 WRPS Tank Operations Contract has worked 8,063,370 hours (570 days) without a Lost Time Workday Injury and 630,308 hours (45 days) since the last Recordable case.
Total Recordable FY 2018 Cumulative Summary
October 1, 2017 through September 30, 2018
Days Away, Restricted Workdays
- r Transferred (DART)
FY 2018 Cumulative Summary
October 1, 2017 through September 30, 2018
0.00
12-month rolling rate: 0.00
DOE/EM Goal – 0.60
0.08
12-month rolling rate: 0.11
DOE/EM Goal – 1.10
There were no Recordable cases in August 2018 August 2018
Project Overview
3 August 2018
Operational Safety Enhancement Process/ETF
Performance Focus
WRPS Senior Management Changes
President’s Office Production Operations Engineering
WFD Progress Vapors Settlement FY19 Appropriations Contract Negotiations – FY19 Extension
Change Control
4 August 2018
Contract Budget Base
$5,461M
Authorized Unpriced Work Negotiated Contract Cost Distributed Budget Management Reserve Undistributed Budget
Total Allocated Budget
$5,461M Performance Measurement Baseline
$707,453
CM $52,876 CM -$203,511
$4,754,032 $9,338 $63,372 $5,388,776
CM $35,324 CM -$188,635 CM $2,675
BCR Impacts
Aug-18 Sep-18 FY 2019 Total DB Impacts
$10,232 $9,631 $15,461 $35,324
Performance Overview Current Month / Fiscal Year
5 August 2018 *OBS focus areas – detailed in subsequent slides Current Month Impact from SPA Change Control Actions Current Month Impact from VAPOR REI Implementation
Performance Overview Cumulative / At Complete
6 August 2018 *OBS focus areas – detailed in subsequent slides
Vapor REA Incorporated
Schedule and Cost Performance Forecast
7 August 2018
Management Forecast of Schedule Performance
Carryover Funds Support 23 Operational Days
$65-$75M
SV improves by $4,444k at Year-End
____________________________________________________________________________________________________,______________________________________2F SST Retrievals $3,051k 2T Chief Technology Office $1,008k 2L Production Ops $927k Largest Sep18 Schedule Recovery Scope A/AX Infrastructure Installation $2,478k Waste Management Program $926k DST Transfer Pump Replacements $792k Jul18 forecast for Aug18 SV was -$29,708k. Aug18 was -$28,623k; favorable by $1,085k
Project Focus Areas
8 August 2018
Action Status SV Improvement Focus
- Schedule opportunities being monitored and
tracked
- Overtime for High Priority Work
Non-labor effectiveness evaluations
- Critical Procurement Focus
- Implementation & Acceleration of FY19 Award
Resource availability
- Reprioritization of Critical Resources
- Posting of Critical Field Craft
Critical Spares Positioning project for proper material inventory at contract completion (SST, TFP, Production Ops) Vapor REA for $20M Complete: Implemented this period
Key Milestones
Complete To Go Will Miss At Risk Total MS % Complete % To Go August
122 38 1 1 162 75.30% 24.70%
Last Month
93 68 1 162 57.40% 42.60%
Risk Management Status (August)
Risk Program Health (August)
- Risk Management is averaging under 30 days for all 34+
register updates (time between register updates) (Figure 1)
- WRPS has maintained less than 21% total high risks
throughout FY18. Risk Management monitors the overall TOC risk profile to determine if risk mitigation strategies are effectively being developed for the highest level risks as a key component of improving the probability of mission success (Figure 2) Current new registers being developed:
- Maintenance Program Register
- AW-104 Pump and Jumper replacement
- AY-02A through line
- Leak Detector project
- Grab Sampling
Current Risk Management program priorities:
- During the month of August, Risk Management continued
to answer questions of DOE independent auditor team (CohnReznick) regarding the FY19 proposal.
- The Mission level risk register is currently being updated
and reviewed by ORP.
- TBI register has incorporated all deep dive comments
and the register continues to be updated monthly.
- The Schedule Risk Analysis has finished for Waste Feed
Delivery
- Risk Management continues to hold smaller group
training classes for the EROMS database to assist and train risk owners, project managers, subject matter experts and project controls members on the use and application of the system. Risks of Near Term Concern:
- DST Transfers - Four DST transfers which were
previously scheduled in FY19 to support EC-11 and EC- 12, will be rescheduled pending resolution of schedule dates for TBI and P-B-1 pump repair (or replacement).
- 222-S – Contract Transition Delays Upgrades
- 222-S – Lab Rad analysis resource availability
Figure 2 Figure 1
Objective Measure
90 90 90 90 90 90 90 90 90 90 90 90 90 60 60 60 60 60 60 60 60 60 60 60 60 60
Performance Thresholds
45 45 45 45 45 45 45 45 45 45 45 45 45 25 15 15 45 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Goal 28 36 29 32 37 28 29 28 29 28 28 30 Declining Meets Exceeds To demonstrate the health of the risk program, the average age of project and program level risk registers are monitored as a guage of overall risk program activity and effectiveness. This metric helps ensure that the Risk Registers for TOC managed projects and programs are up-to-date. The Enterprise Risk and Opportunity Management procedure, TFC- PRJ-PC-C-13, requires that Program and Project Risk and Opportunity Registers be updated at least every 90 days. The average age in days of risk register from last update to the current date (end of calendar month) >90 Adverse ≤45
Performance Data
- Avg. Age in Days of Risk Register
>45 and ≤60 >60 and ≤90 10 20 30 40 50 60 70 80 90 100 Average Age in Days
- Avg. Age in Days of Risk Register
Objective Measure
0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.45 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35
Performance Thresholds
0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.45 0.1 0.05 0.3 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Goal 124 126 133 138 130 139 146 148 152 150 148 147 680 688 689 726 734 743 756 745 778 729 721 698 18% 18% 19% 19% 18% 19% 19% 20% 20% 21% 21% 21% Declining Meets Exceeds Percentage of High Risks (Month) Number of Open Risks To monitor the overall TOC risk profile to determine if risk mitigation strategies are effectively being developed for the highest level risks as a key component of improving the probability of mission success. The percentage of currently characterized High Risks
- Vs. the Total number of Risks as a percentage.
>45% Adverse ≤30%
Performance Data
Number of High Risks >30 and ≤35% >35 and ≤45% 0% 10% 20% 30% 40% 50% 60% 70% 80% Percentage of High Risks Percentage of High Risks (Month)
WRPS Risk Management
9 August 2018
100 200 300 400 500 600 700
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Monthly Completed CMs & PMs
Plant Status – PMs & CMs
10 August 2018
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep FY Total Field Work Complete - CMs
40 43 32 46 39 60 48 39 31 31 45 454
Field Work Complete - PMs
589 628 473 554 653 645 566 511 426 516 612 6,173
Team Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept AN 6 4 3 5 5 6 7 6 6 4 4 AZ 7 8 9 9 7 7 8 9 9 8 8 FACILITIES 4 5 6 10 5 7 7 6 6 7 6 ETF 20 21 21 23 16 15 15 15 21 22 34 EV 7 5 1 2 2 2 2 1 LABS 19 19 21 23 21 23 26 27 27 31 30 Projects 2 2 1 1 1 1 2 2 2 2 4 WS R&C 3 3 3 4 6 8 9 10 9 8 10 ST 5 5 7 6 7 6 7 7 4 5 3 Transfer Totals 73 72 72 83 70 75 83 82 84 88 99
CM Backlog - FY2018
Team Oct Nov Dec Jan Feb Mar Apr May June July Aug Sept AN 2 AZ 8 5 1 1 1 1 2 1 FACILITIES 4 7 8 6 1 1 ETF 9 23 7 7 6 10 6 6 10 14 5 EV 26 23 17 9 3 10 4 6 6 3 4 LABS 10 2 5 4 3 3 12 6 17 12 8 Projects WS R&C 1 1 ST 2 3 2 11 16 5 11 Totals 59 66 40 27 24 40 24 19 40 41 17
Delinquent PMs - FY2018
Indirect Pools
August 2018 11
Fringe Rate (ABS & COS) ($0.9M) Over ABS (applied to Labor) ($0.1M) Over COS (applied to Labor) ($0.8M) Over COP Rate (applied to Labor) $2.5M Under G&A Rate (applied to Labor/Non-Labor) $5.0M Under
Total Net Debit to PMB $6.6M Under
FY18 (Over)/Under Forecast
(Over) = Credit to the Direct Field Work / Under = Cost Charge/Allocation to the Direct Field Work
(Over)/Under Summary: $6.6M Under August / $6.9M Under July
Current Month Impacts:
- Reduction in labor base and G&A pool.
Critical Needs List
12 August 2018
$1,647
- $4,989
$656
- $1,284
1.47 0.95 1.04 0.99 1.08 0.95
August 2018
LA LAWPS Performance Revie iew
(WBS 5. 5.5)
Schedule Cost
13 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$1,940 P - LAWPS-S - Design Project Support
- $1,288
Tank Side Cesium Removal System
- $577
P - LAWPS-S South - Design $382 Cost Variance FYTD: $1,432 CTD: -$6,636 P - LAWPS - Design
- $1,014
- $6,750
P - LAWPS - Design Project Support $368
- $2,332
P - LAWPS-S South - Design $1,626 $1,626
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
Biggest Threats/Risks Keys to Success
Spent IX Column interim storage package requirements. Continue evaluation of requirements and alternatives. Permitting strategy for interim storage pad. Continue evaluation of requirements and alternatives.
- Continued progress towards conducting Formal 45% Design Review on September
5th & 6th
- Received approval of SDS from ORP
- Commenced archival of “Optimized” LAWPS design media
- Conducted TSCR 30% Design Review
- Submitted TSCR SDS for Approval
- Issue LAWPS Permanent Facility Technology Maturation Plan
Biggest Threats/Risks Keys to Success
GFE doesn’t meet functional requirements CEES to perform simulant testing utilizing Laboratory validated simulant APT/WRPS/DOE integrated QA process and oversight during fabrication and FAT WIR Authorization is delayed HQ to remove public comment period from WIR reviews – or early public comment based on calculated DF values RCRA permit modification delay Temporary Authorization for early work 242-A Evaporator and/or associated infrastructure unavailable when TBI ready to
- perate
Perform transfer line testing prior to TBI installation. PM of Crane/Facility (complete). Ensure vent & balance performed. Partially loaded IX Columns cannot be stored at SWOC facility Develop contingency storage on-
- site. Draft waste profile early &
interface with DOE-RL/CH-PRC
Test Bed Initiative
14 August 2018
Key Points: Schedule Recovery:
- GFE will include the waste processing equipment, i.e. filtration and IX.
- DOE is the DA for the GFE with WRPS support to the DA (Kris Thomas)
- WRPS has taken the lead in coordinating and organizing the multi-
performer / multi-contract project team through external IPT meetings and War Room efforts
- WRPS has completed numerous tasks including the following:
- Crane PMs and PB-1 pump relocation
- 2nd draft WIR evaluation
- Draft Air Permits
- Sampling and Analysis to support WIR, WAC, and Transportation
- Project critical path is typical through design, fabrication, installation,
- perations with permitting and NEPA actions on critical path as well.
- Aggressive but realistic schedule in place, which does not meet
12/31/2018 desired date.
- Working opportunities to gain schedule acceleration
2,000 Gallon Test Bed Initiative Gatepost Milestone Chart
2,000 Gallon Test Bed Initiative Milestones Responsible Party Forecast Finish WIR Evaluation Updated Based on AW-102 Sample Analytical Results WRPS 8/28/2018 A Final Design Complete APT 12/3/2018 Temporary Authorization Approved DOE 12/13/2018 WIR Evaluation Approved DOE 12/6/2018 WIR Determination Approved DOE 12/27/2018 Fabrication and Factory Acceptance Testing Complete APT 1/24/2019 Equipment Delivered to Evaporator APT 2/4/2019 Equipment Installation Complete WRPS 3/20/2019 NEPA Documentation Approved DOE 2/11/2019 Testing Complete WRPS 3/21/2019 Declaration of Readiness to Operate WRPS 3/29/2019 Start of Waste Processing WRPS 3/29/2019 End of Waste Processing WRPS 4/3/2019 Totes Shipped to PFNW WRPS 4/20/2019 Complete Treatment of Mixed Low Level Waste APT 5/2/2019 WCS Provides Waste Profile Approval APT 6/4/2019 Treated MLLW Arrives at WSC APT 6/13/2019 Waste Disposed at WSC APT 6/17/2019
Extracted from TBI Working Schedule (9/17/2018)
$952
August 2018
$14,166
- $4,056
CT CTO/Closure an and In Interim Meas asures Performance Revie iew
Schedule Cost
15 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$5,008 Direct Push Characterization & Sampling
- $1,823
Waste Mgt Area C Performance Assessments
- $667
RCRA Closure Plan Updates
- $475
Cost Variance FYTD: $1,137 CTD: $14,426 Technology Development $0 $3,177 Technology Maturation & Analysis $1,461 $2,985 RCRA Closure Plan Updates $79 $2,189
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today -$260
Key Points Schedule Recovery
- Finalizing ORP comments received during clearance review process for the Technology & Innovation
Roadmap; issuance of finalized Technology & Innovation Roadmap tracking for September 17.
- Issued Phase II testing report for Mechanical Waste Gathering System alternate retrieval technology
development, and submitted completion paperwork for PBI 42.0.9.
- Issued 100% design of the new sampling technique and began routing for approval in SPF.
- Finalized comment incorporation on testing reports from VSL, LANL, and RJ Lee supporting EMF
waste form testing in FY18.
- Design of the first of three panels for the TX Farm interim surface barrier is proceeding.
- Work is proceeding on Grout Testing and other WMA C closure activities.
- Developing responses to Ecology comments on the RCRA Tiers 2 and 3 Closure Plans.
- DOE O 435.1 WMA C WIR and PA public/NRC reviews are in progress.
- Regulatory Documentation schedule variance is due to Ecology comments that are
past due. Have started receiving and dispositioning the comments. Due to the significant number of comments, recovery is not expected this FY.
- ILAW Glass Testing is expected to recover a portion of lost schedule in the current
fiscal year, the remaining scope (Lysimeter studies) is expected to carryover to Q1
- f FY 2019.
Note: CTO related schedule is recovering as anticipated for the month and is expected to continue to recover most of the SV by the end of the FY18 Q4.
Biggest Threats / Risks Keys to Success
Path forward for Ecology review and finalization of WMA C closure documents is
- needed. A mutually acceptable regulatory
approach must be developed among Ecology, DOE, and WRPS to move forward with incremental closure of WMA C. Working with DOE and Ecology to develop acceptable path forward.
0.95 1.07 1.04 0.90 1.07 0.98
- $694
- $6,012
- $3,023
- $10,183
0.95 0.99 0.99 0.99 1.09 2.52
August 2018
Tan ank Far arms Projects Performance Revie iew
Schedule Cost
16 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$7,160
Tank Chemistry and Integrity
- $3,451
Tank Farm Upgrade Projects
- $5,721
Vadose Zone/Interim Measures $4,428 DST Feed Delivery Projects
- $2,150
Cost Variance FYTD: -$851 CTD: -$5,318
Tank Chemistry and Integrity
- $215
$4,411 Effluent Treatment Facility (LERF Basin)
- $801
- $3,189
Tank Farm Upgrade Projects $5,335 $299 Vadose Zone /Interim Measures
- $6,020
- $5,888
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points •
Completed In-Pit heater installation AN and AW Farms (10 pits)
- AW-103 transfer pump removal and replacement
- Completed AZ-102 UT scans
- AW-03A pit NACE inspection
- Completed AY/AZ SS flow punch list items
- Completed wireless equipment installation and CAT AP and AN Farms
Biggest Threats / Risks Keys to Success
Construction and plant forces resource availability Weekly critical resource allocation reviews and prioritization. Impact of change in mission to include Tank Side Cesium Removal and Test Bed Initiative Integration and prioritization for allocation of key resources.
CVAP Performance Revie iew
(WBS BS 5.1.5.2.11 & 5.1.5.11)
Schedule Cost
17 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$5,088 Vapor Monitoring & Detection System Upgrades
- $2,355
Chemical Vapor Engineered Control Upgrades
- $1,200
Industrial Hygiene Trailer
- $926
Cost Variance FYTD: $728 CTD: $1,117 New Vapor Detection Technologies
- $744
- $1,901
Chemical Cartridge Evaluations $666 $1,187 Strobic Air Upgrade $1,128 $1,178
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
- PA System Field Work Terminations and speakers ready to test B
complex
- Received Vapor Stack Monitor units for AZ and AN Farms
and initiate installations
- Factory Acceptance testing two Vapor Stack Monitors AX Farm
- Received all ten sections of 10-wide IH Trailer, set and married up
exterior
- Completed design of SST Automation second farm T complex
Biggest Threats / Risks Keys to Success
Critical Resource Availability (Plant & Construction Forces) Integration & prioritization for allocation of key resources AW Stack Permitting Ecology Approval for Authorization Results of QRA may change boundaries Vapor Monitoring & Detection System equipment turnover to
- perations
August 2018
- $519
$598
$1,976
- $3,112
1.02 0.91 1.01 0.95 0.98 1.06
CVAP Da Dashboard
18 August 2018
$407
- $30,909
$3,051
- $3,356
0.97 1.04 0.99 0.99 0.91 0.94
August 2018
SST Retrie ievals ls Performance Review
Schedule Cost
19 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$6,407 C-Farm Retrievals
- $116
A/AX Farms Retrievals
- $5,896
AY-102 Retrieval
- $395
Cost Variance FYTD: -$602 CTD: -$31,316 C-Farm Retrievals $6,014
- $5,141
A/AX Retrievals
- $9,192
- $34,687
AY-102 Retrieval $2,552 $8,489
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
- Completed the final AX-102/AX-104 equipment removal (AX04 Pit A-
R5B Pump) (PBI-36.02.6)
- Completed 1st of 2 concrete pours for A-Farm Exhauster Pad
- Completed water rinse of AY-102
- Completed fieldwork to remove the C-Farm Retrieval HIHTL
- Opportunities/Issues
- Shortage of electricians
- Initiated A-104 and A-105 strategy discussions with Ecology
- Implementing APR in AX, AY & AZ in October
Biggest Threats / Risks Keys to Success
Schedule impacts due to several factors have resulted in retrieval legal milestones being in jeopardy: CD D-16B-2 (Complete 9 tanks by 31 March 2024) and TPA M-045-15 (Complete A-103 by 30 Sept. 2022)
- DOE notified the State of Washington that CD-D-16B-2 is in jeopardy due to
vapor impacts
- Funding priority placed on A/AX construction
- Retaining core operations team proficiency for AX retrieval readiness
- Implementation of APR use in AX farm will significantly improve
efficiency/schedule performance Washington Department of Ecology’s recent interpretation on tank ventilation air permitting requirements cannot be met with the current generation of tank exhauster systems
- Request to revise the AX Farm air permit needed to support retrieval was
submitted to ECY February 23, 2016
- ECY’s position is closely associated with the tank vapor litigation
- Work closely with WRPS and DOE legal to negotiate solution
Costs of A/AX retrieval system construction have increased due to several factors
- Implementation of APR use in AX farm will significantly improve efficiency/cost
performance
- Redesign of waste retrieval systems to simplify construction and reduce costs
- Complete a cost growth drivers analysis
There is a shortage of key field labor (NCOs, HPTs, IHTs, construction crafts) due to attrition, site-wide bump-and-roll, regional competition for skilled labor
- Coordination with CHPRC to pick up labor from any future RIF
- Early forecasting of construction labor needs to support contractor recruiting
efforts
- Expedited worker training for field deployment
Deployment of new retrieval technologies to improve efficiency and strengthen DOE support for retrieval
- Coordination with CTO
- Tech transfer from SRR (crawlers, sampling systems, mixer pumps)
- Tech transfer from heavy construction/mining industry (dome coring,
mechanical waste gathering)
- $1,810
$19,985
$926
- $1,652
0.89 1.02 1.04 1.00 0.99 1.03
August 2018
Production Operations Performance Review
Schedule Cost
20 Dollars Represented in Thousands
FY TCPI FYTD CPI CTD SPI CTD CPI FYTD SPI CM SPI
CTD Schedule Variance Total: -$2,578 ETF/LERF/TEDF Operations & Maintenance - OP 2-3
- $1,412
Tank Waste Volume Management - OP 2-3
- $692
222-A Laboratory Facility Option Period 2-3
- $338
Cost Variance FYTD: $6,665 CTD: $21,795 Production Operations Support Services $1,678
- $12,358
Solid Waste Management
- $1,423
$5,966 Production Operations East Area Farms $3,126 $12,614
EOY Forecast SV
Delta From Today
EOY Forecast CV
Delta From Today
Key Points
- Implemented the Request for Equitable Adjustment (REA) for Vapor Impacts on
Double-Shell Tank DST Work Scope and Execution for contract modification 492 that addresses work planned for fiscal year (FY) 2016 through FY 2018. OBS “2L” received an adjustment value of $14,031k associated with Baseline Change Request RPP-18-172 incorporation.
Biggest Threats / Risks Keys to Success
Aging Equipment: ETF Systems, 242-A Systems, Transfer Pumps Adequate Spares, PMs, and Planned Upgrades PM/CM Backlog Reduction Adequate resource availability Adequate PMs, Spare Parts Inventory Critical Resource Review FY19/20 Planning Integration & prioritization for allocation of key resources Assess Skill Mix to FY19/FY20 Scope HAMTC MOA - Downgrade Respiratory Equip Requirement Field implementation of cartridges following 3rd Party Review PFP D&D boundary controls impact TOC execution Close coordination with CHPRC/DOE on response actions at PFP to minimize impacts 222-S and ETF Readiness to support DFLAW FY19/FY20 Proposal
- August Significant Accomplishments:
Transferred 566,815 gallons of waste from LERF Basin 43 in support of the third 1,000,000 Gallon LERF campaign. Completed removal of the spare PB-1 pump from the 242-A Evaporator onto a steel plate in the courtyard outside the evaporator in preparation for rebuild. Completed installation of the Gamma Energy Analyzer at the 222-S Laboratory in support of PBI-38.0.2.2.