Address elements of the project over next several Board of Education workshops • Origins of the project ‐ building condition survey • Plan for funding and timing of the project Nov 1st Dec 6th • High school and middle school maintenance issues* Jan 3rd • All elementary buildings maintenance issues* • Athletic fields, FEC, and transportation maintenance issues* Feb 7 th • Review entire proposition to go to the March 21st business meeting Mar 7 th *Actual pictures will be used to highlight specific concerns
Big Tree Elementary
Proposed Project by Building BIG TREE ELEMENTARY 1079 Roof replacement $ 2,009,500 1009 Replace catch basins $ 40,000 Gym wall pad replacement $ 16,900 1133 BIG TREE ELEMENTARY TOTAL $ 2,066,400
Big Tree Roof replacement (roof flashing) – record #1079
Big Tree Roof replacement – record #1079 Roof expansion joint
Big Tree Catch basin replacement – record #1009
Blasdell Elementary
Proposed Project by Building BLASDELL ELEMENTARY 2132 Air handling unit replacement $ 105,000 Ceramic wall tile removals $ 307,800 2169 Auditorium renovations $ 113,960 2018 Sidewalk replacements $ 17,010 2009 Replace catch basins $ 13,200 Gym wall pad replacement $ 20,150 2157 BLASDELL ELEMENTARY TOTAL $ 577,120
Blasdell Auditorium Air Handling Unit - record #2132
Blasdell Cafeteria Air Handling Unit – record #2132
Gym Air Handling Unit – record #2132 Blasdell
Auditorium Seating- record #2169 Blasdell
Blasdell Auditorium A.D.A. Seating- record #2169
Sidewalks - record #2018 Blasdell
Catch Basin - record #2009 Blasdell
Cloverbank Elementary
Proposed Project by Building CLOVERBANK ELEMENTARY 4131 Air handling unit replacement $ 105,000 Ceramic wall tile removals $ 248,800 4175 Auditorium renovations $ 113,960 4016 Parking lot replacements $ 825,000 4018 Sidewalk replacements $ 231,000 Replace catch basins $ 10,500 4009 CLOVERBANK ELEMENTARY TOTAL $ 1,534,260
Cloverbank Auditorium Air Handling Unit – record #4131
Cloverbank Gym Air Handling Unit – record #4131
Cloverbank Cafeteria Air Handling Unit - record #4131
Auditorium Seating – record #4175 Cloverbank
Parking lot – record #4016 Cloverbank
Sidewalks – record #4018 Cloverbank
Catch Basins– record #4009 Cloverbank
Pinehurst Elementary
Proposed Project by Building PINEHURST ELEMENTARY 8151 Emergency generator $ 86,000 8146 Update pneumatic controls $ 300,000 8171 Auditorium renovations $ 96,089 8172 Stage curtain and rigging replacements $ 25,000 8173 Theatrical lighting replacements $ 75,000 8009 Replace catch basins $ 3,000 PINEHURST ELEMENTARY TOTAL $ 585,089
Pneumatics - record #8146 Pinehurst
D.D.C. Controls - record #8146 Pinehurst
Auditorium Seating - record #8171 Pinehurst
Pinehurst Auditorium A.D.A. Seating - record #8171
Theatrical Lighting - record #8173 Pinehurst
Theatrical Lighting - record #8173 Pinehurst
Pinehurst Theatrical Lighting Board - record #8173
Catch Basin - record #8009 Pinehurst