orc power plant neustadt glewe operational experience
play

ORC Power Plant Neustadt - Glewe Operational Experience Since 2004 - PowerPoint PPT Presentation

ORC Power Plant Neustadt - Glewe Operational Experience Since 2004 Electricity generation, combined heat and power Strasbourg, September, 15 th - 2006 Thomas Funke Erdwrme Kraft GbR - Berlin Dr. Silke Khler Geoforschungszentrum - Potsdam


  1. ORC Power Plant Neustadt - Glewe Operational Experience Since 2004 Electricity generation, combined heat and power Strasbourg, September, 15 th - 2006 Thomas Funke Erdwärme Kraft GbR - Berlin Dr. Silke Köhler Geoforschungszentrum - Potsdam

  2. Location of Neustadt - Glewe Neustadt – Glewe is located in the Northeast of Germany (North German Basin) Land Mecklenburg-Vorpommern The existing heating station is in operation since 1994 Less demand of heat during the summer gives the chance to produce electricity The complete plant is a combination of heat and electricity production - CHP Neustadt - Glewe 2 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  3. Heating Station since 1994 Two Wells (production & reinjection) ~ 2250 m deep ca. 1400 customers Installed capacity: 16.4 MW th geothermal part : 6.5 MW th Geothermal supplies 95 % of the total produced heat Very little heat demand during the summer months 3 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  4. Geothermal Power Plant since 2003 First geothermal power plant in Germany Geothermal facility with very low brine temperature (~97° C) for an electric power station Gross capacity of 200 kW 4 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  5. Thermal water (brine) circuit net capacity Overall mass flow rate of brine 110 m³/h, to grid divided in two streams, one for the heating station and one for the power plant power plant gross capacity T The partial flow to the power plant is 200 kW el 70° C cooled down in a heat exchanger (evaporator) to a temperature of ~70° C brine Afterwards the cooled brine is mixed with s 98° C the main brine stream and is transported 110 m³/h to the heating station (500m) heating station For the production of district heating the 6 MW geothermal brine is finally cooled down to ~50° C th 11 MW total ~ 50° C th Production of heat has the priority. Only the heat not needed by the heating station can be used in the power plant. heat to district full load during summertime � heating system out of service during wintertime � 5 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  6. ORC - Process (Organic Rankine Cycle) Synthetic organic fluid ( Perfluoropentane, C 5 F 12 ) with Turbine a boiling point of ~30° C Evaporator Generator Superheater This fluid is preheated and Condenser / evaporated before the steam Cooling Tower expands in the turbine Fluid Pump After the turbine the steam is condensed in the condenser. The condenser is fed by cooling water which is cooled down in two cooling towers. Production Injection To close the cycle the working fluid is pumped back to the boiler and evaporates again like in any other common power plant process. 6 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  7. Geothermal power plant Neustadt-Glewe Chemical ORC-Container Cooling towers Water treatment The unit is installed in a 12 m container close to the production well The electric switching station is installed on the same site. It connects the plant to the 20 kV grid. The power plant runs automatically with checks every three days. Starts and unplanned stops were supported manually. 7 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  8. Technical data ORC - Thermal Heat Power Plant Electrical output 200 kW (installed) Electrical production 1.400 – 1.600 MWh/a max. theoretical (annual demand of ~ 500 households) ORC-Turbine axial inflow, single stage with three nozzles Turbine efficiency, 70 % Preheater and evaporator made out of titanium Live steam temperature ~ 75 ° C, pressure ~ 4 bar Pressure condenser ca. 1 bar Total efficiency ~ 7.4 % Total investment costs ~ 950,000 € 8 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  9. The Story of Neustadt - Glewe 1. Technical and organizational preparations 2002 – 2003 2. Start up Nov 2003 3. First modifications Mar 2004 4. Start continuous production Aug 2004 5. First winter shut down Nov 2004 – Mar 2005 6. Bearing damage – generator Apr – May 2005 7. Leakage – ORC valves Jun – Aug 2005 8. Damage brine pump Oct – Nov 2005 9. In operation with unsatisfying load since Apr 2006 generator capacity (kW) 200 1 2 3 4 5 6 7 8 9 100 0 01.01.2003 01.01.2004 01.01.2005 01.01.2006 time 9 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  10. Problems to Solve Since the first start up the plant doesn’t reach the full load Investigations were started – in close cooperation with GFZ Possible reasons are numerous (heat exchange – feed pump – turbine) We expect first results and improvements this autumn Depending on the investment costs we will try to modify some components Less output affects also the economics. The revenues are much smaller than planned Although the price of the produced electricity is government-funded under the so-called Renewable Energies Act the situation is unsatisfying: Only the combined production of heat and electricity will allow successful operation! 10 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  11. Summary The geothermal power plant of Neustadt – Glewe is an important project to gain experiences under the special geologic conditions of Germany (low temperatures). It supports the next project of GFZ-Potsdam and Vattenfall in Groß Schönebeck. The technique on the surface is not so easy as it might look like although we’ve heard different things yesterday More experiences in low-temperature power plant operation are necessary. With better thermal conditions the efficiency of new projects will increase – but: Without the combination of heat production (CHP process) it would be difficult to operate a power plant for electricity production with success. 11 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  12. Thank you for your attention 12 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  13. Pictures Pieces of rubber found in turbine Valve with damaged rubber lining 13 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  14. Charts I Electricitiy Generation (MWh) 2004 - 2006 90 80 70 60 50 40 30 20 10 0 Jan 04 Apr 04 Jul 04 Okt 04 Jan 05 Apr 05 Jul 05 Okt 05 Jan 06 Apr 06 Jul 06 Okt 06 14 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

  15. Charts II Electric Output / Brine 1,0 0,9 0,8 0,7 P Gen /P Gen,max 0,6 0,5 0,4 Electric generation 0,3 decreased within the last 2004 0,2 years 2005 0,1 2006 0,0 0,0 0,2 0,4 0,6 0,8 1,0 V Brine /V Brine,max 15 Erdwärme Kraft GbR, Hr. Funke 15.09.2006 GFZ, Dr. Köhler

Recommend


More recommend