NORTHBOUND NORTHWESTERN HWY SERVICE DRIVE ROAD REHABILITATION SOUTHFIELD RD TO LAHSER RD March 26, 2018
PROJECT LIMITS EAST OF LAHSER RD WEST OF SOUTHIELD RD
NB NORTHWESTERN HWY SERVICE DRIVE Overview • Concrete patching with asphalt overlay • Reconstruction of the following intersections Mt Vernon and NB Northwestern Hwy Service Drive • Evergreen Rd and NB Northwestern Hwy Service Drive • NB Northestern Hwy Service Drive north of Civic Center Dr • • New traffic signals at: Mt Vernon St • Evergreen Rd (mast arms) • Civic Center Dr • • Bike lane between Mt Vernon and Civic Center • Sidewalk and driveway improvements • One to two lanes traffic maintained throughout construction • Funding from both Federal ($1.74M) & City’s Road Bond Construction fund ($5.84M) w/ CCAB $50k
NB NORTHWESTERN HWY SERVICE DRIVE REHABILITATION Sidewalk Improvements FILL SIDEWALK GAP EVERGREEN 10 MILE SIDEWALK CROSSING 10 MILE BRIDGE SIDEWALK TO SIDEWALK CROSSING MT VERNON BRIDGE EVERGREEN BRIDGE
NB NORTHWESTERN HWY SERVICE DRIVE REHABILITATION Sidewalk Improvements FILL SIDEWALK GAP 25800 NORTHWESTERN 2000 TOWN CENTER
NB NORTHWESTERN HWY SERVICE DRIVE REHABILITATION Sidewalk Improvements CONTINUE NEW 10’ PATHWAY FROM THE SOUTH TO LAHSER CORPORATE DR LAHSER RD
NB NORTHWESTERN HWY SERVICE DRIVE REHABILITATION Mt Vernon Detour (Phase I – 2018 Construction) 10 MILE RD MT VERNON 9 MILE RD