Muskrat Falls Project: Organized for Success Gilbert Bennett, Vice - PowerPoint PPT Presentation

Muskrat Falls Project: Organized for Success Gilbert Bennett, Vice President, Lower Churchill Project Canadian Hydropower Association Forum, May 14, 2015 2 Muskrat Falls Project Focus is on providing the greatest long-term value to NL


  1. Muskrat Falls Project: Organized for Success Gilbert Bennett, Vice President, Lower Churchill Project Canadian Hydropower Association Forum, May 14, 2015

  2. 2

  3. Muskrat Falls Project Focus is on providing the greatest • long-term value to NL Meeting our growing electricity needs • Enhanced system reliability • Providing long-term rate stability • Eliminating our reliance on foreign oil • for electricity Practically eliminating GHG emissions • from the NL electricity sector Employment and economic benefits • Significant, long-term revenue for NL • Controlling our energy future • 3

  4. 4

  5. Safety Management • Creating a safety culture with transient workforce, multiple contractors • Comprehensive health and safety plans – both LCP and contractors • Work closely with contractors to enable success – Approx. 25 H&S professionals on project team • Detailed reporting and auditing safety performance 5

  6. Building a Safety Culture • Key initiatives: – Safety Net and the Use of Predictive Solutions – Safety Incentive (recognition) program – Established safety absolutes for all LCP worksites – Safety training at all site operations – Contractor safety forums – Collaborative working relationship with OHS and integrated OHS committee – Sharing of incident notifications, lessons learned and incident summary reporting 6

  7. 7

  8. Managing Procurement • Many opportunities for businesses in NL, Canada and around the world • Approx. 200 contracts managed through LCP procurement team • 500+ direct and indirect contractors • To date approx. $800M invested in NL companies alone (over half to Innu-owned businesses/joint ventures) • Almost all contracts and PO’s issued for the project • Successful procurement/contract management to date 8

  9. Logistics Management Around the World • Materials shipped to rural/remote locations from around the world • LCP oversees material receipt, storage and control • Established marshalling yards in Labrador and on the island to hold and control delivery of transmission materials • As of December 2014: – > 45,000 MT shipped – 1,134 containers and 2,070 trucks • Logistics for large materials (ex. generators and turbines) require road/bridge closures for transport 10

  10. 11

  11. Ensuring High Quality • Oversight, construction and manufacturing audits • Review of management plans and processes, readiness reviews • Factory inspections • Quality assurance at various factories, plants, and testing and manufacturing facilities in 20 countries worldwide 12

  12. 13

  13. 14

  14. Technology & Working Remotely • Enable and enhance communication across remote locations • Actively used in the field (environment, lands, transmission clearing and construction crews) – LCP Powerline: GIS program is interactive, displays info specific to an inquiry, provides 62 map layers • Pronto Forms: allows field personnel to immediately submit reports via iPad app 15

  15. 16

  16. Organized for Success • Project Management Team ensures effective execution of the Muskrat Falls Project • Primary activities include oversight, project controls, audit integration, detailed engineering & design, project management, engineering, procurement, project services, and, and overall site and contractor management 17