com m ents on the muskrat falls reference
play

Com m ents on the Muskrat Falls Reference Presentation to the - PowerPoint PPT Presentation

www.centrehelios.org Com m ents on the Muskrat Falls Reference Presentation to the Public Utilities Board of Newfoundland and Labrador Newfoundland and Labrador Philip Raphals For Grand Riverkeeper Labrador Inc. F G d Ri k L b d I


  1. www.centrehelios.org Com m ents on the Muskrat Falls Reference Presentation to the Public Utilities Board of Newfoundland and Labrador Newfoundland and Labrador Philip Raphals For Grand Riverkeeper Labrador Inc. F G d Ri k L b d I February 23, 2012 1

  2. www. centrehelios.org O ti Optimality lit  « How did you ensure that  « How did you ensure that … you were you were dealing with the optimal scenario under each one? » > Technical optimization vs. planning processes > Iterative process seeking robust solutions > Real time (evolutive) versus planning exercise > Avoiding irrevocable choices that would turn out badly in certain possible futures out badly in certain possible futures > Scenario versus plan 2

  3. www. centrehelios.org PPA PPA payment options t ti  “Does the 2035 ratepayer have to pay  Does the 2035 ratepayer have to pay more so that the 2017 ratepayer can pay less?” less? > Nominal LUECs vs. escalating prices > Same present value, but different reality > Consumers unlikely to prefer escalating prices 3

  4. www. centrehelios.org PPA vs COS PPA COS  Simulate annual costs for Muskrat  Simulate annual costs for Muskrat Falls under COS > Higher than PPA in early years Hi h th PPA i l > Drastically lower in later years  Prices post 2067 > PPA: maintaining 2067 price levels ($400/MWh) ⇒ windfall profits $ > COS: continue to decline (< $20/MWh) 4

  5. www. centrehelios.org CDM CDM  MHI  MHI > model CDM like generation > End-use modelling  Nalcor’s approach > Integrate into load forecast through technological change variable > No mesure-by-mesure or program-by-program analysis  Objectives to date not met  Sensitivities > Far less than Marbek scenarios > At low demand (= high CDM) scenarios, ( g ) , CPW preference for Muskrat drastically reduced 5

  6. www. centrehelios.org 6 NWPPC fuel forecast 2009 Fuel price forecasts t f i l F

  7. www. centrehelios.org 7 EIA Retrospective Review i R ti EIA R t

  8. www. centrehelios.org Wi d Wind power assessment t  2004 NLH study  2004 NLH study > Sole source for Strategist inputs > 80 MW limits primarily economic > 80 MW limits primarily economic • Based on minimizing spill • Fails to take into account cost of wind, net of curtailment or spills curtailment or spills > « preliminary » > Government RFP shows that higher Go e e t s o s t at g e penetration remains an objective 8

  9. www. centrehelios.org C Conclusions l i  Reference question  Reference question > Verify that the costs attributed to each scenario are correct? > Verify that each scenario makes sense? V if th t h i k ?  Analyses of MHI and others > Results highly dependent on assumptions g y p p > Great uncertainties > Little confidence that the Isolated Island scenario would play out as defined play out as defined  If Muskrat Falls does not go forward > planning process will continue > May lead to solutions very different from IIS  Thus Reference Question largely academic 9

Recommend


More recommend