montlake project monthly construction update
play

Montlake Project Monthly Construction Update April 8, 2020 1 of 12 - PowerPoint PPT Presentation

Montlake Project Monthly Construction Update April 8, 2020 1 of 12 Ho How to w to par participa ticipate in the w te in the webinar binar All attendees are muted. Please use the To adjust your audio settings Q&A window to ask


  1. Montlake Project Monthly Construction Update April 8, 2020 1 of 12

  2. Ho How to w to par participa ticipate in the w te in the webinar binar All attendees are muted. Please use the To adjust your audio settings Q&A window to ask during the meeting, click on questions or offer Audio Settings. comments. CHAT is disabled during the presentation. Please communicate with the team through the Q&A window . 2 of 12

  3. Agenda Agenda • Project summary and design update • Construction progress to date • What’s to come • How to stay informed • Comments and questions The blue gantry crane will allow crews to remove the old eastbound bridge and construct a new one. 3 of 12

  4. Pr Project summar oject summary The Montlake Project will improve multimodal transportation for both motorized and nonmotorized travel along the corridor. Elements include: • A new eastbound bridge – extending two general-purpose lanes • Pedestrian land bridge – connecting the Arboretum with East and one transit/HOV lane from Montlake to the new floating bridge. Montlake Park and the University District through a shared-use pedestrian land bridge. • Montlake lid – improving the Montlake Boulevard/SR 520 interchange by providing open space, a transit plaza, direct-access ramps for buses and HOV, and multimodal connections. Montlake area before construction. Montlake area after completion. 4 of 12

  5. Pr Project sc oject schedule hedule Subject to change 5 of 12

  6. New pa New path und th under SR 520 o er SR 520 opened pened Mar March 9 h 9 6 of 12

  7. Constr Construction pr uction prog ogress in Mar ess in March Iron workers Crews building the working vertical support near the walls for the westbound Montlake lid. Montlake Boulevard off-ramp in the water line access pit. New flashing Crews crosswalk at installing in- East Lake water bridge Washington support piles Boulevard and from the East Roanoke temporary Street. work trestle. 7 of 12

  8. Cons Constr truction uction p prog ogress i ess in Mar n March Construction Construction camera 1 camera 3 (looking west). (looking west). Construction Construction camera 2 camera 4 (looking east). (looking east). 8 of 12

  9. Construction Constr uction look look-ahead ahead When construction resumes, elements of work include: • Demolition and debris removal of the Montlake Market and gas station. • Closures on Montlake Boulevard to move an underground water line. • Continued work near the north and south access pits for the 54-inch water line. • Daytime pile driving in Lake Washington. • Saw cutting to remove the old eastbound bridge. • Montlake lid construction. 9 of 12

  10. Wha hat to e t to expect xpect: : noise and vibration • • Different types of equipment result in different levels and Crews may work 24 hours a day, seven days a week kinds of noise and vibration. throughout construction. • • Electronic noise and vibration meters record levels Typical work hours for the loudest work: throughout the project area. – 7 a.m. to 10 p.m. weekdays – 9 a.m. to 10 p.m. weekends and holidays • Vibration monitors will collect data in the field and – Impact pile driving has stricter work hours and will immediately alert the project team when readings are occur: outside the set tolerances. • 8 a.m. to 5 p.m. weekdays • Nighttime construction has stricter rules for noise levels • 9 a.m. to 5 p.m. weekends and equipment use. • Independent noise monitors will be present for night work • We’ve received a Major Public Project Construction Noise to ensure compliance with specified noise levels. Variance, which allows higher decibel levels than normally allowed by city ordinance for noise between 10 p.m. and 7 a.m. Our 24-hour hotline, 206-775-8885 , is the best way to report noise and vibration concerns and to have questions addressed in the moment. Weekly noise reports are posted on the SR 520 Construction Corner: www.sr520construction.com/ManagingConstructionEffects 10 of 12

  11. How to s Ho w to stay inf tay infor ormed med Stay tuned for our online • Call our 24-hour hotline: 206-775-8885 spring events: • Email us with questions : • May 6 online monthly sr520bridge@wsdot.wa.gov construction update meeting • Visit the Montlake Project website: • May online open house www.wsdot.wa.gov/projects/sr520/montlake • Visit the SR 520 Construction Corner to learn more about upcoming construction: www.sr520construction.com • Follow us on Twitter : @wsdot_520 • Sign up for our email updates by emailing us at sr520bridge@wsdot.wa.gov • Participate in our online meetings and events 11 of 12

  12. Comments and questions? 12 of 12

Recommend


More recommend