Measure LL Facility Bond Mini Workshop August 13, 2020 Dr. Matt - PowerPoint PPT Presentation

Measure LL Facility Bond Mini Workshop August 13, 2020 Dr. Matt Doyle, Superintendent Ami Shackelford, Asst. Sup., Business Services John Wathen, Executive Director Facilities 1 Agenda Bond Construction Cost Running Total Bond Team


  1. Measure LL Facility Bond Mini Workshop August 13, 2020 Dr. Matt Doyle, Superintendent Ami Shackelford, Asst. Sup., Business Services John Wathen, Executive Director Facilities 1

  2. Agenda ● Bond Construction Cost Running Total ● Bond Team Restructure ● Completed Projects Update ● Projects Under Construction ● Projects In Planning and Design ● Discussion - Feedback and questions 2

  3. Bond Construction Costs Committed Total 3

  4. BOND TEAM RESTRUCTURE 4

  5. Bond Team Structure During Measure O in early 2000 ● Assistant Superintendent, Facilities Planning & Governmental Relations - Mike Vail ● Director of Construction ● 2 Facility Planners ● 2 Inspectors (District Employees) ● Bond Accountant ● 3 Secretaries (Asst. Sup., Dir. Const., Fac. Planners)

  6. Bond Team Structure Currently for Measure LL ● Assistant Superintendent, Business (CBO) - Ami Shackelford ● Executive Director - John Wathen ● Director of Construction - Kevin Waugh ( Prop LL funded ) ● Bond Accountant - Karen Riedel ( Prop LL funded ) ● Purchasing Manager - Kevin Lesko ● Contract Specialist - Barb Goya

  7. Various Bond Positions Used in Districts Program Management Firm - Manages the entire project in consultation with Superintendent and Board Liaison CFO - Chief Facilities officer, cash management strategies, oversight Bond Programmer - programming, long-term management, CBOC management, analysis, reporting and communications Facilities Director - coordinates projects with internal departments ensuring adherence to District standards and provide field support, review invoices and project processes Construction Director or Managers - manages all field activities, RFI review, oversight of architect, inspectors, laboratories, contractors, accessibility compliance, coordination with sites, attends all construction meetings, reviews all invoices and contracts Facility Coordinators - field support for Director, attends meetings, reviews RFI, AUR, CO, inspecting and monitoring, documenting and reporting Bond Accountant - manages bond funds, processing of PO’s, invoices, AUR’s, change orders, reconciliation, reporting and fiscal review Contract Specialist - manages all contracts, addenda, change orders, AUR’s, interprets contract language for project management 7

  8. Bond Team Restructure Considerations ● Measure LL Bond Projects to Increase Dramatically in Next 8 months ○ RBV Softball Field Project (Medium Scope) ○ VHS Softball Field Project (Medium Scope) ○ VHS Portable Classroom Replacement Project (Large Scope) ○ Beaumont Portable Classroom Replacement Project (Large Scope) ○ Bobier Portable Classroom Replacement Project (Large Scope) ○ VIDA Sewer Project (PLA) (Medium Scope) ○ RMMS Landscaping and Shade Project (PLA) (Medium Scope) ○ VMMS Front Facade Project (PLA) (Medium Scope) ○ Lake/Madison Pathway Project (PLA) (Medium Scope) ● Most Efficient Team Structure to Manage 9 Individual Construction Projects ● Experience and Expertise to Facilitate and Assure High Quality Product, On-Time Delivery, Meet On Budget Goals ● Impact on Effective Day to Day District Functions ● Provide High Quality Public Facing Communication and Engagement ● Keep Board Members Actively Engaged and Informed ● Keep CBOC Members Actively Engaged in Oversight 8

  9. COMPLETED PROJECTS UPDATE 9

  10. Rancho Buena Vista High School Gym Expansion ● Rancho Buena Vista High gymnasium expansion with new restrooms, food serving area, concessions and storage ● Project is complete ● Project actuals to date are $1,727,983 10

  11. Vista Magnet Middle School Pool Modernization ● Project is complete ● Project actuals to date are $2,511,721 11

  12. PROJECTS UNDER CONSTRUCTION 12

  13. VHS Softball Field and Athletic Field Project ● Hazmat abatement and building demolition are being completed at the Vista High Softball Field Project ● Heavy earthwork will be commencing next week as the existing fields are excavated and prepared for the next phases of construction 13

  14. RBV Softball Field Project ● Softball field fencing, dugouts and water lines being installed this week at RBV softball ● Spread-footing for posts that encountered rocks and prevented the full depth of the hole to be excavated 14

  15. Casita Elementary Restroom Modernization ● New parking lot curbing modifications for ADA accessibility compliance ● New wall finishes are now starting to be installed in the restrooms ● Polished concrete floors are completed 15

  16. California Avenue Restroom Modernization ● New tile and fixtures being installed in the restrooms ● The refurbished restrooms will now have plenty of storage everywhere ● Project is on schedule and estimated completion for August 24th 16

  17. Projects In Planning and Design Projects In Planning and Design 17

  18. Beaumont Elementary Updated ROM for 3 buildings $9,409,850, removal of building #3 could save between $720K to $1M, reducing the current ROM to $8,689,850 18

  19. Office Modernization: Option #1 ● Expansion occurs behind existing offices (blue), and reuses the existing office footprint (tan) ● New larger health area with restroom, staff workroom, staff lounge, new student, staff and gender-neutral restrooms, larger admin. and waiting areas ● ROM estimate office Option #1 - $1,224,401 ● Total ROM including classrooms estimate $9,915,251 19

  20. Office Modernization: Option #2 ● Expansion occurs towards the MPR (blue), reuses the existing office (tan) ● New larger health area with restroom, staff workroom, staff lounge, new student, staff and gender-neutral restrooms, larger admin. and waiting areas ● ROM estimate office option #2 - $1,648,803 ● ROM estimate total with classrooms and office option #2 - $10,338,653 20

  21. Office Replacement: Option #3 ● New building and demolition ● ROM estimate office of existing option #3 - $1,976,015 ● Removes covered walkway, provides the greatest facelift for school entry, private lunch court, larger health area, staff workroom & lounge, student, staff and gender-neutral restrooms, larger admin. and waiting areas ● ROM estimate total with classrooms and office option #3 - $10,665,865 21

  22. VHS New Classroom Buildings Overview Building 200 facing the campus core. This is a 3-story building with student, staff and gender-neutral restrooms located on the 2nd and 3rd floors, roll up doors on the 1st floor for JROTC and athletics, ten science classrooms, ten general education classrooms, one large flex-suite, and staff workrooms 22

  23. VHS New Classroom Buildings Overview Building 100 facing from Bobier Drive. This is a 2-story building with student, staff and gender-neutral restrooms located on the 1st and 2nd floors, 18 general education classrooms, one large flex-suite on the 2nd floor, and staff workroom on the 2nd floor 23

  24. Other Projects In Planning and Design ● Lake & Madison - Pedestrian Pathway (PLA) ● Rancho Minerva - Shade, Landscaping & Fencing (PLA) ● Vista Magnet - Gym Wall Repair, Front Entry Modification & Landscaping (PLA) ● Bobier Elementary School ○ new classroom buildings & portable demolition ○ Meeting is scheduled with the principal, executive director, WLC architect and Erickson Hall construction manager to refine project ○ Office modernization options will be evaluated for safety, accessibility, and the improved flow of students, staff and parents ○ Front of campus treatments to be included for curb appeal 24

  25. Discussion and Feedback Budget Construction Cost Status ● Bond Team Restructure ● Current Projects ● Beaumont Office Proposal ● 25