Madison Elementary School Project Overview TODAY AUG SEP OCT NOV DEC JAN FEB MAR JUL MOBILIZATION DEMO & SITEWORK 7/5 6/18 STEEL START BUILDING DRY IN LANDSCAPE START CONSTRUCTION 10/22 01/15 - East 03/28 8//2 Start Substantial Completion JULY 5, 2018 AUG 1, 2019
Madison Elementary School Project Milestones: DEC 28 Building Dry In (East) JAN 02 Drywall - Start JAN 10 Windows & Storefronts - Start JAN 24 Siding - Start FEB 5 Entire Building Dry In MAR 28 Landscaping – Start AUG 1 Substantial Completion
Madison Elementary School Project Stats: JUL - DEC 24,742 Man Hours – Field 0 Lost Time Accidents 284 Tons of Structural Steel 636 Steel Beams 136 Steel Columns 5,319 Bolted Steel Connections
Madison Elementary School
Madison Elementary School Concrete
Madison Elementary School Concrete
Madison Elementary School East Wing
Madison Elementary School East Wing
Madison Elementary School East Wing
Madison Elementary School West Wing
Madison Elementary School Project Challenges: PAST & CURRENT: FUTURE: • Additional Hazardous Materials • Landscaping Rebid • Local 302 Operating Engineers Strike • Unforseen Conditions: Additional Contaminated Soils • Underground Storage Tank(s) • Weather Impacts • Contaminated Soils - petroleum • Unsuitable Soils - structure
Madison Elementary School Contaminated Soils
Madison Elementary School Construction Financials: Total Earned as of 11/30/18 $ 8.19M Average Daily Burn Rate $ 71,250 OVERVIEW - Cost Impacts To Date: $ 10,000 Addt’l Hazardous Materials $ 67,000 Local 302 Strike Class II & III Contaminated Soils $ 215,000