CERN TE-ABT-EC LIU-ABT systems: PSB BI.DIS10 controls • Agenda: https://indico.cern.ch/event/525232/ - Timing system (Christophe Chanavat) - Fast interlocks studies (Felipe Cordobes Dominguez) - IGBT’s R&D program (Tobias Stadlbauer & Luc Sermeus) - General controls (Roger Andrew Barlow) prepared by R.A.Barlow 12/05/2016 1
BI.DIS10 Generator prototype, Jura 6 Status of technical progress • Prototype BI.DIS10 controls completed with TECHNIX 10kV-1A power supply integration • Improved IGBT protection and triggering • Pulsed power system near completion (PFN & Magnet)....but issues with inductors... • Thermal studies & reliability runs have started (April 2016) up to 8kV...to go further...worst case not studied yet • Fast interlock system (early tests planned for April 2016)...? • Review of logical connection to BIS ongoing (1 channel Vs. 4 channels) …still to be discussed by MPE group. • Looking at current technology issues concerning PFN signal conditioning, to be determined trough tests !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! 2
BI.DIS10 Generator controls and production PLC controls production • 95% PLC modules ordered, arrived ! FSU jobs created for the following: • ABTECMAINT-48 Installation components BI.DIS10 in BCER (Linac4/LS2) • ABTECPROD-18 Cablage des 6 PFN pour le BI.DIS10 (Naked shells ready) • ABTECPROD-20 JURA6 BI.DIS10 patch traversant prototype (Change-over proto) • ABTECPROD-21 Pre-production series for PLC crates BI.DIS10 (Master, OP, GPC, EDS) FSU jobs created for the following: • ABTECPROD-22 Production of series PLC crates for BI.DIS10 (Outside ?) • ABTECPROD-25 Patch panel de series pour BI.DIS10 au BCER (Outside ?) • ABTECPROD-19 Cablage des unites casette IGBT pour le BI.DIS10 (Outside ?) Chassis drawings and cabling drawings started, aim to have all this ready by end of MAY-2016. PDC production envisage for September...
BI.DIS10 Budget • 1 .) Materials to be ordered for end 2016 delivery: • Major order placed for PLC components: 25kCHF – DONE-> (23kCHF) • FIS system: 90 kCHF • Timing KiT’s: 10 kCHF • PDC: 10kCHF • Other (AUE. Flashers, Scope, etc..): 10kCHF • TOTAL: 145kCHF • 2 .) FSU taskforce expenditure: • Pre-production crates: 3 man.week • Pre-production specialised cables: 1 man.week • Final specialised control cables + patches 6 generators: 5 man.week • PFN internal cabling (6 of): 6 man.week • IGBT cassette cabling (6 of): 4 man.week • TOTAL: 19 man.week / 30kCHF • 3 .) Equipment to be built by external companies: • PLC chassis: 40kCHF
BI.DIS10 Documentation PBU-MSMIA-ES-0001 - Functional Specification BI.DIS10 Controls (EDMS 1339372) Released PSB-MSMIA-ES-0008 - Engineering Specification BI.DIS10 controls (EDMS 1574218) Under approval PSB-MSMIA-ES-0006 - Engineering Specification, Beam Interlock Specification For Booster BI.DIS10 with linac4 (EDMS 1571034) In work PSB-MSMIA-ES-0004 - Functional Specification, BI.DIS10 Fast interlocks (EDMS 1537992) Engineering check PSB-MSMIA-ES-0005 - Engineering Specification, BI.DIS10 Fast interlocks (EDMS 1538154) In work and recently added ! PSB-MSMIA-ES-0007 - BI.DIS10 GENERATOR SPARE CONNECTION TO MAGNET PROCEDURE (EDMS 1571059) Under approval