LIU-ABT systems: PSB BI.DIS10 controls Agenda: - PowerPoint PPT Presentation

CERN TE-ABT-EC LIU-ABT systems: PSB BI.DIS10 controls Agenda: https://indico.cern.ch/event/539274/ General controls (Roger Andrew Barlow) Timing system ( Christophe Chanavat ) IGBTs R&D program (Tobias Stadlbauer &


  1. CERN TE-ABT-EC LIU-ABT systems: PSB BI.DIS10 controls • Agenda: https://indico.cern.ch/event/539274/ • General controls (Roger Andrew Barlow) • Timing system ( Christophe Chanavat ) • IGBT’s R&D program (Tobias Stadlbauer & Luc Sermeus) • Fast interlocks studies (Felipe Cordobes Dominguez) prepared by R.A.Barlow 30/056/2016 1

  2. BI.DIS10 Generator prototype, Jura 6 Status of technical progress • PLC program improvement • Recipe's added for settings • Some functionalities sill to be implement • New TIA library item for automated state machine control (in SCL) • To be desired in nearby future: • Integration of the triggering optical module inside the PFN • Optimization of capacitive dividers pickups • Fast interlocks integration • Review of logical connection to BIS ongoing (1 channel Vs. 4 channels) …still to be discussed by MPE group, now this looks more like 1 BIS system ! 2

  3. BI.DIS10 Slow control and cabling production PLC controls production • 95% PLC modules ordered, arrived ! + a few extra’s ... FSU jobs created for the following: • ABTECMAINT-48 Installation components BI.DIS10 in BCER (Linac4/LS2) • ABTECPROD-18 Cablage des 6 PFN pour le BI.DIS10 (Naked shells ready) – September 2016 ? • ABTECPROD-20 JURA6 BI.DIS10 patch traversant prototype (Change-over proto) – HW done • ABTECPROD-21 Pre-production series for PLC crates BI.DIS10 (Master, OP, GPC, EDS) – on-going FSU jobs created for the full production: • ABTECPROD-22 Production of series PLC crates for BI.DIS10 (Outside) • ABTECPROD-25 Patch panel de series pour BI.DIS10 au BCER (Outside) • ABTECPROD-19 Cablage des unites casette IGBT pour le BI.DIS10 (CERN?) Chassis drawings and cabling drawings done, aim to have all this ready by end of MAY-2016 (on-time). PDC production envisaged for September..., however and due to CL workload this will probably be realised in December 2016

  4. BI.DIS10 PP prototype design for generator changeover PP for generator changeover strategy J c 1 6 J a J a 7 1 1 1 2 2 2 Fr eew eel h de i o d shu nt Dum p de d i o I GBT 1 GBT I 2 T3 B G I B S -4 F B -5 F S B S -5 F I B G T1 at st us C on t r c abl ol e pat ch -1 cab V H l e t c pa h-1 H ng t i ar ef r er ence or f ase b un i t : 09 -14 -02 4- 03 03 J 14 J 12 4 J P FN T C P FN vo l t age 1 2 3 BNC -Tr 1 C B N 2 -Tr B N a1 t -S C B N C -S t a2 N B C T C agne m t S w i t c h/D B S r F -4 i v er 1 B S F 12 s Fan S B F peed -8 P 10x T 2 ar t i H ng r ef er ence f or b un ase i t : 09 -14 -01 6- 13 03 11 J J 2 J 6 3 3 4 ar 0V 23 H /ac ng t i H 23 0V ar /ac t i ng w er po Fan 1 er w po Fan 2 B S F 8 P FN P FN M anu al E S D F S B t c i w S hes 8 S B 4 F E S ar t hi t c i w hes ng Fi yst r e s em t i ar H r ng ef er ence f b or un ase : 09 i t -14 -01 6- S B D E F S 7 13 03 age t ol V Status of technical progress • PP prototype cut out done ‘old’ MEAS BCER.306 MY06 • Improvement for coaxial Technix MY01 feedthroughs, new inserts PLC MY02 supports 5mm coax, improved PFN Trig/ attenuation factor, lower risk of MY03 Vac reflections... FSC MY04 Lambda • Still to be carried out, modification PDC MY05 to JURA6 cage to adapt switch- Magnet over strategy.

  5. BI.DIS10 JURA6 HW status JU6 H/W for Timing and FSC KiT’s timing system ‘old’ MEAS BCER.306 MY06 FSC system Technix MY01 PLC MY02 PFN Trig/ MY03 Vac FSC MY04 Lambda Status of technical progress PDC MY05 • KiT’s Identified rack space for Magnet system and FSC • Removal of old manual earthing switch • Technix PS to be lowered • New Ethernet connections demands

  6. BI.DIS10 PFN ‘shells cabling’ PFN shells cabling Status of technical progress • Empty PFN shells, to be taken advantage for cabling (prior to coil assembly) • ‘new’ Needs all fans + fan assembly • Have all the PT100 ’s • To be cabled as per new drawings

  7. BI.DIS10 DIC/DEC and UPS systems DIC/DEC issues Status of technical progress • DIC completed (99.9%), sent to EN/EL • Nearly 600 cables ! (guestimate on-par) • DEC to be finalized, pre inspection of number of cables in existing BI.DIS + campaign during EYETS to mark cables to be removed and file into a DEC. • UPS systems RA302 UPS + standard outlet RA303 UPS + standard outlet RA304 UPS + standard outlet RA305 UPS + standard outlet RA306 UPS + standard outlet RA435 UPS + standard outlet RA301 UPS + standard outlet RA329 UPS + standard outlet RA328 Standard outlet

  8. BI.DIS10 Planning review

  9. BI.DIS10 Documentation PBU-MSMIA-ES-0001 - Functional Specification BI.DIS10 Controls (EDMS 1339372) Released PSB-MSMIA-ES-0008 - Engineering Specification BI.DIS10 controls (EDMS 1574218) Under approval/In Work PSB-MSMIA-ES-0006 - Engineering Specification, Beam Interlock Specification For Booster BI.DIS10 with linac4 (EDMS 1571034) In work PSB-MSMIA-ES-0004 - Functional Specification, BI.DIS10 Fast interlocks (EDMS 1537992) Engineering check PSB-MSMIA-ES-0005 - Engineering Specification, BI.DIS10 Fast interlocks (EDMS 1538154) In work PSB-MSMIA-ES-0007 - BI.DIS10 GENERATOR SPARE CONNECTION TO MAGNET PROCEDURE (EDMS 1571059) Under approval PSB-EQCOD-XX-XXX – Functional Specification, Operational requirements for the controls of the new distributor BI.DIS10 – EDMS ??? – In Work