9/13/2018 Liberty Square Drainage Improvements & Parking Lot Meeting September 12, 2018 www.walkbridgect.com www.walkbridgect.com Upcoming Construction Activities September October December November Iron Works/Lock Building Test Pits N. Water St. Test Pits Goldstein Place Drainage Liberty Square Parking Lot (City) Ann St. Ann St. Closure (Phase II) Closure Test Pile Program (11 Locations) Submarine Cable Installation (Tentative) www.walkbridgect.com 1
9/13/2018 Goldstein Place Drainage Liberty Square www.walkbridgect.com Goldstein Place Drainage • Work Started: September 10 th • Approx. 5 weeks total (lot work completed before October 1 st ) • 6:30 AM – 3:30 PM • Intermittent noise • Intermittent parking space impacts (for equipment) • Fort Point Street shoulder closure may occur • Local access maintained www.walkbridgect.com www.walkbridgect.com 2
9/13/2018 www.walkbridgect.com Goldstein Place Drainage Work Legend Drainage Work Intermittent Parking Impacts Fort Point Street shoulder www.walkbridgect.com www.walkbridgect.com closure 3
9/13/2018 Liberty Square Parking Improvements: • 58 Spaces Total Plus 3 handicap spaces • Repaving parking lots • Drainage • Additional Light Pole • Landscaping Schedule: • Tentative start date: Week of September 24 th , 2018. Drainage work may start earlier due to w eather and tide • Approximate 4 Week timeframe www.walkbridgect.com www.walkbridgect.com www.walkbridgect.com 4
9/13/2018 During Construction, parking w ill be relocated to Veteran’s Park www.walkbridgect.com www.walkbridgect.com www.walkbridgect.com 5