lake worth projects update december 19 2013
play

Lake Worth Projects Update December 19, 2013 Paul Bounds, - PowerPoint PPT Presentation

Lake Worth Projects Update December 19, 2013 Paul Bounds, Regulatory and Environmental Coordinator Fort Worth Water Department 1 Dredging 2,046,617 cubic yards dredged through November 30, 2013 Total remaining 89,808 cubic yards


  1. Lake Worth Projects Update December 19, 2013 Paul Bounds, Regulatory and Environmental Coordinator Fort Worth Water Department 1

  2. Dredging • 2,046,617 cubic yards dredged through November 30, 2013 • Total remaining –89,808 cubic yards • 96% complete • Currently working at Casino Beach and cove in Area H • Scheduled to complete by 12/31/13 • Demobilization to be complete by 2/28/13 2

  3. DREDGING SCHEDLUE Final Design COMPLETED COMPLETED 12/31/2013 COMPLETED COMPLETED 12/31/2013 COMPLETED 3 3

  4. Stump and Hazard Removal Review Plan • Compile maps of current and previous stump removal projects • Identify remaining hazards for physical verification • Locate and mark verified hazards • Issue field order to Great Lakes for removal of verified hazards 4

  5. 5

  6. 6

  7. Watercress/ Casino Beach Water and Sewer Improvements • Phase 1 – Water and Sewer service for Casino Beach – Water service along Watercress – A lift station located on the west side of the Jacksboro Highway Bridge – Sanitary sewer force main crossing the lake • Phase 2 – 24” Water across the lake to Casino Beach • Phase 3 – Sewer Service along Watercress – Alterations to Jenkins Heights and Meadow Lake lift stations as required

  8. Watercress/Casino Beach Phase 1 8

  9. Watercress/Casino Beach Phase 1 Schedule • Award of Contract Nov. 5, 201 North Texas Contracting $5,188,315.00 • Notice to Proceed Dec. 3, 2013 • Public Meeting Dec. 3, 2013 • Construction Start Dec.16, 2013 • Complete Construction Aug. 31, 2014 9

  10. 24” Water Main Lake Crossing 24” Water Main 8” Water Main

  11. Watercress/Casino Beach Phase2 • Award of Design Contract Sept. 23, 2013 • Request for Change Order Nov. 26, 2013 • Award of Change Order Jan. 28, 2014 • Notice to Proceed Feb 11, 2014 • Complete Installation Mar. 31, 2014 11

  12. LWCIIP Funding • Projects will be funded with gas lease or lease sale revenues • Cash financing only. • Gas market fluctuations make it difficult to accurately project revenues. 12

  13. LWCIIP Future Projects • Live Oak Cree and Silver Creek Watershed Management Study Design 2014 • Phase I Trail System Under design (Phase 1 and 2) Construction 2015 • Love Circle Water and Sewer Design 2014 Construction 2015 • Phase II Watercress Water and Sewer Design 2016 Construction 2017 • Phase II Trail System Construction 2018 13

  14. 14

  15. 15

  16. QUESTIONS? 16

Recommend


More recommend