injectors lhc report
play

Injectors & LHC report S. Baird and M. Bernardini on behalf of - PowerPoint PPT Presentation

Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 16/08/2013 LSC - S. Baird, M. Bernardini 1 AD EN/EL : cabling AD-target : pulling completed and connections in progress. Some tests remains TE/VSC :


  1. Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 16/08/2013 LSC - S. Baird, M. Bernardini 1

  2. AD EN/EL : cabling AD-target : • pulling completed and connections in progress. Some tests remains – TE/VSC : • Cryo pumps and sensors are now installed on UHM3107 and UVM3207 – tanks. Some tests still to be realized. Ion pump change is almost finished in sector 2. Some delay on other – places as extremely delicate manipulations. Gauges upgrade progresses well. – BE/BI + TE/VSC : • Ion pump installation none of the MTV screen was replaced, as degasing test slows down the – planning (and there are some problems with the test bench). But not critical for the moment. BHN06: new CERN visit to manufacturer for first coil test. Decision • will be taken by end next week. A plan-B is going to be considered as well in case of further delay. TE/ABT : 1 month additional delay announced for the 2 KFI tanks • (installation postponed at the end of October). Girder line 7000: good progress by design office • 16/08/2013 2 LSC - S. Baird, M. Bernardini

  3. LEIR EN/EL : • cabling FO (fibres optiques) for PSS project is completed and – tested. Other cables (BIW + stopper) are installed. To be tested. – TE/MSC + TE/VSC : • removal of DHV12 on 1/8 was successful. Excellent support – from EN/HE as well. (see picture) BE/BI : • MTV screens are ready, then degasing tests. – Should all be fine for the installation scheduled early October. Removal DHV12 PSS : New access point waiting to be put in service • BE/BI : • last-minutes request to intervene on the 2 BIPM (Beam – Ionisation Profile Monitor) on vacuum sector 5. We plan therefore to open this sector week 35. In preparation. 16/08/2013 LSC - S. Baird, M. Bernardini 3

  4. PS Done • CV Consolidation program: the last Asbestos part removed Zone 12 - – final elbow and valves in PS (Chilled water program) is completed In Progress • CV Consolidation program: cabling started, racks delivered – PS PSS Safety and Access System Installation – Installation of sector zone is progressing. • New access doors will be put in service from week 34 to week 36 • Valves installation on chilled water The Septum 16 External Shielding program: – The earth work is completed, and 2 weeks of Stand-by done • The work of 29 stakes installations is starting. 2 seismograph have been placed • in the PS ring Forecast • EN-EL cabling campaign will start week 34 – Ready for starting the installation of stakes 16/08/2013 LSC - S. Baird, M. Bernardini 4

  5. PSB In progress • Beam Dump Replacement: – Extraction & Disposal of Dump C ore + Beam Pipe → • Done Week 32 Preparation + Test of the Extraction & Disposal of • S hielding → Ongoing Week 33 Extraction & Disposal of S hielding → foreseen end of • Week 33 and Week 34 CV consolidation and maintenance of CV, kickers, – Septa, vacuum beam instrumentation, Magnet and Beam Dump automatic cutting machine Beam stopper, cabling campaign Unexpected Failure • Ring2: Pick-Up Wide Band (BR2.WCM8L1) Vacuum – Leak → 29/07/13 Vacuum Display Leak not repairable (→ due to Titanium-Inox brazing) • New Vacuum Chamber to manufacture + new design • Recovery expected for March/April 2014 • Vacuum Leak 16/08/2013 LSC - S. Baird, M. Bernardini 5

  6. SPS EL cabling works in progress • All transformers are replaced • between BA3 and CCC. MKP disconnected and pumped out, All new transformers in place to prepare the irradiated cable campaign All other works progressing on • schedule. Everything is removed in • LSS1 for the irradiated cabling campaign but 2 shielding and the MAL. Transport and Handling • need to be more studied before intervention. 16/08/2013 LSC - S. Baird, M. Bernardini 6

  7. TT10 Civil Engineering Works Beamline and general services cleared where • necessary and tunnel ready for consolidation works to begin. Support beams already delivered to CERN. • End plates foreseen 20th August. • Chosen contractor (Concrete Repairs Ltd) • preparing teams, training courses, etc. GS-SE preparing planning and method statements • in accordance with tests performed. Installation of beams to commence beginning of • Support delivered September (estimated ~4 weeks work). 16/08/2013 LSC - S. Baird, M. Bernardini 7

  8. LHC - P1  P2 R2E – Pt1: • Left: Piping finalized and cabling started, 3 – weeks ahead of schedule Right: piping just started, 1 week delay, will – be recovered, no impact on end task date UL14 – piping LSS1: • 600A upgrade completed – Survey HLS maintenance in progress – DFBX: consolidation of current leads – AIV magnet test in progress Start of the survey smoothing soon – Arc 12: • Exchange of cryo-magnets in progress – all are connected, electrical tests done; • IC W openings in progress – 16/08/2013 LSC - S. Baird, M. Bernardini 8

  9. LHC - P2  P3 Point 2 • Cooling tower maintenance in progress – Cryogenic maintenance in progress – AUG test realized with positive result – LSS2 • Completion of the cabling campaign – Arc 23 • Preparation for the modification of the HRL valves (UJ32) – Cryogenics consolidation in progress – Vacuum consolidation in progress – Magnet reconnection in progress: all new magnets installed – DN200: partial opening and installation in progress – LSS3 • End of cable pulling to P3.2 – Preparation for the cable campaign: installation of the cable trays – DFBA: Intervention on the Thermoswitch ongoing – Water cooled cables of the DFBAE dismounted – Opening of the vacuum sub-sector for the future new passive absorbers (TCAP) – 16/08/2013 LSC - S. Baird, M. Bernardini 9

  10. LHC - P3  P5 Arc 34 • QRL– compensator removed – Optical fiber replaced – Magnet replacement in progress  Quadrupoles out – QRL compensator from P4 and dipoles from PMI2 removal Vacuum consolidation activities in progress – VSC beam vacuum blowing activities in progress – Walkway installation in progress – LSS4 & P4 • Flexwell campaign complete in underground – Completion of the cabling campaign 22R4, header C – Water cooled cables consolidation in progress – RF maintenance and upgrade – Arc 45 • Magnet exchange in progress, all magnets removed, last – magnet will be installed next week QRL X ray campaign in progress (header C, all QRL) – new – deformed, not leaky compensator on header C Test for MAFI passage through P5 and P3 realised – on 9 th august -->  16/08/2013 LSC - S. Baird, M. Bernardini 10 Passage MAFI P5

  11. LHC – P5  P6 LSS5: • Modification of the cabling for TOTEM ongoing – Completion of the DFBAJ consolidation – R2E – P5 • UJ56/machine side – 6 ducts − Safe-room structure done − Drilling: all ducts are drilled, smoothing in progress − Civil engineering: 1w ahead of schedule UL55 – safe room Arc 56 • QRL xray campaign in progress, all headers, H vacuum SS – SMACC – DFBAK  deformed compensator  2 month delay • Compensator deformed DFBAK M weld in progress (~80%) • W closure will start next week: 2weeks ahead of schedule • Vacuum leak test in progress • Diodes in progress • LSS6 & P6 • Maintenance of cooling tower in progress – MKD-MKB tests on going on beam1 – Cabling campaign started on right side – Consolidation of the DFBA ongoing – 16/08/2013 LSC - S. Baird, M. Bernardini 11

  12. LHC – P6  P7 Arc 67 • SMACC in progress: – 80% shunt installed • DFBA consolidation – TZ76 – Fire Detection equipment supports R2E – P7: • TZ76 – vault painting done – Cable trays installed and rack installation just started – Smoke detector in RR installed, and in progress in TZ76 – LSS7 • Vacuum sectors ready for the new doors project: – 4x collimators and 2x correctors magnet removed Consolidation of the DFBA ongoing – 13kA & 600A upgrade will start soon – LSS 7: Magnet removal 16/08/2013 LSC - S. Baird, M. Bernardini 12

  13. LHC - P7  P1 Arc 78 • DN200 – finished – M opening finished – Desoldering BB started – DFBAN consolidation in progress – LSS8 &P8 • Consolidation of the DFBA ongoing – R2E @P8 • Ventilation control cabinet to be – rescheduled Cryo activities ahead of schedule – Arc 81 • - DFBAP consolidation in progress - Cryo module consolidation in progress - M opening in progress: IC train started - DN200 installation in progress 16/08/2013 LSC - S. Baird, M. Bernardini 13

  14. General infrastructures Sunrise upgrade postponed in Sept 2013 • Demineralised water available: work is being • finalized 400kV & 66kV maintenance and • consolidation – Maintenance finished, no more power limitation: some additional tests will be performed in sept, no impact. Fire safety wall – RTE auto-transfert test postponed in September (before Open days) – Meyrin site powered off during 10’ 66kV maintenance 16/08/2013 LSC - S. Baird, M. Bernardini 14

  15. Overall progress Injectors: on schedule, but to follow • AD – BHN06 coil manufacturing – LHC on schedule • R2E - On schedule – SMACC – to follow – Good progress M line welding • DFBA schedule • General infrastructures: good progress • Impact of summer holidays will be assessed in September • 16/08/2013 LSC - S. Baird, M. Bernardini 15

Recommend


More recommend