IBL - LAPP Cooling lines 1. Design and production status 2. Installation 3. Schedule LAPP team Jacky Ballansat, Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque, Sabine Elles, Nicolas Massol, Thibaut Rambure, Theodore


  1. IBL - LAPP Cooling lines 1. Design and production status 2. Installation 3. Schedule LAPP team Jacky Ballansat, Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque, Sabine Elles, Nicolas Massol, Thibaut Rambure, Theodore Todorov, Tamer Yildizkaya 1 2014-02-06 Pierre Delebecque

  2. Design and production status 2 2014-02-06 Pierre Delebecque

  3. Design and production status PP1 region 3 2014-02-06 Pierre Delebecque

  4. Design and production status PP1 region 4 2014-02-06 Pierre Delebecque

  5. Design and production status Splitting box region 5 2014-02-06 Pierre Delebecque

  6. Design and production status Splitting box region 6 2014-02-06 Pierre Delebecque

  7. Design and production status Stainless steel cooling lines production  Production tooling (bending) under construction  First final lines to be tested on the mockup Bending system for the PP1 region First bent samples 7 2014-02-06 Pierre Delebecque

  8. Design and production status Isolators Production  Metallic sleeves delivered to Microcertec  Bent Pipes delivered to Microcertec  Isolator should be delivered before end of february.  Last EB qualification : Leak tests are OK, CO2 cycling is in work, metalurgical analysis is in work , final welding planned begining of march.  Setups for tests are almost ready 8 2014-02-06 Pierre Delebecque

  9. Installation 9 2014-02-06 Pierre Delebecque

  10. Installation – Transportation and assembly  « Ambroise » mockup was tested in the pit  Installation tests to be carried on begining of march 10 2014-02-06 Pierre Delebecque

  11. Schedule  February :  Isolator production / brazing  Final bending tools developments and first lines tested on the mockup  Installation tools final design and orders  March  Last isolator EB welding  Final bending of the 28 cooling lines and tests  Installation tools mounting and tests  April  Lines assembly on the installation tools and first orbital welding tests  Final orbital welding at CERN and test  May  Begining of may : sets ready for installation  Installation in the pit official date may 29 th 11 2014-02-06 Pierre Delebecque