I-440 Reconstruction From I-40 to I-24
What is Design Build? A project delivery method that • combines all or some portions of the design and construction phases of a project into a single contract. TDOT clearly defines the • standards, scope, and specifications for a project, and the Design-Builder works to satisfy those requirements. 20 October 2017 2
Why Design-Build? Shortened completion time by • overlapping design and construction Construction can begin before • all design details are final. Reduced claims due to design • errors/ omissions because construction happens under same contract. Shortened project delivery • time which can reduce user costs. Single contact point for • quality, cost and schedule from design through construction. 3
I-440 Project Overview - Location Map Begin Project End Project 4
I-440 Project Overview Constructed in the early 80s • 7.8 miles+/- • I-440 serves as an urban interstate • facility linking I-40 in the west to I- 24/I-40 in the east. This facility also serves as a connection to I-65, which connects to Nashville to the north and to Brentwood/Franklin/Huntsville to the south. The existing concrete pavement on • I-440 is in substandard condition. The crash rates on I-440 are • approximately 1.8 times higher than the statewide average for urban interstate facilities. 5
I-440 ADT AADT • 2016 – 94,801 • 2021 – 102,968 • 2041 – 123,688 (Along the corridor) (Along the corridor) (Along the corridor) • Lowest between Murphy • Highest between Hillsboro Road and West End Road & I ‐ 65 • 7% Trucks - 85,890 (2021) - 115,740 (2021) - 104,360 (2041) - 138,400 (2041) 6
Existing Typical Section • Travel Lanes (TL) - 2 Lanes in each direction • 13 ‐ foot grass median • 8 ‐ foot inside shoulders with 2 ‐ foot curb • Total Median Width – 46 feet (TL to TL) • 12 ‐ foot outside shoulders 7
I-440 Proposed Improvements • Widening to the inside to provide a minimum of • Removing and replacing the existing six (6) travel lanes (3 in each direction) pavement throughout the corridor - Eastbound Reconstruction ends west of - Widening ends west of Nolensville Road Nolensville Road - 12 ‐ foot Travel Way - 11 ‐ foot +/ ‐ shoulder 8
Other Improvements • Other Improvements – New Noise walls – Repair/Replace Noise walls – Signing – ITS – Rockfall Mitigation
I-440 Slide 1 PROP. 51” MEDIAN BARRIER Charlotte Ave. BEGIN I ‐ 440 WIDENING LEGENDS NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE 10
I-440 Slide 2 PROP. 51” MEDIAN BARRIER PROP. NOISE BARRIER LEGENDS NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE 11
I-440 Slide 2 STA 1081+60 STA 1086+60 Barrier near ROW Barrier near ROW 12
I-440 Slide 3 PROP. 51” MEDIAN BARRIER LEGENDS NEW PAVEMENT REPLACE NEW SHOULDER REPLACE PROP. NOISE BARRIER MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE 13
I-440 Slide 3 STA 1105+07 STA 1110+40 Barrier Existing Barrier Replacement Barrier Replacement at Existing Location 14
I-440 Slide 4 Belmont Blvd. PROP. 51” MEDIAN BARRIER LEGENDS NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE 15
I-440 Slide 5 PROP. 51” MEDIAN BARRIER Lealand Ln. LEGENDS NEW PAVEMENT REPLACE PROP. NOISE BARRIER NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE BRIDGE WIDENING 16
I-440 Slide 5 Barrier Replacement at Existing Location STA 1203+60 (12’ Height) Existing Barrier Barrier Replacement at Existing Location (12’ Height) Existing Barrier STA 1217+60 17
I-440 Slide 6 U.S. 31 PROP. 51” MEDIAN BARRIER LEGENDS NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE BRIDGE WIDENING 18
I-440 Slide 7 PROP. 51” MEDIAN BARRIER LEGENDS NEW PAVEMENT REPLACE END I ‐ 440 WIDENING NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE 19
I-440 Slide 8 LEGENDS PROP. 51” MEDIAN BARRIER NEW PAVEMENT REPLACE PROP. NOISE BARRIER NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE 20
I-440 Slide 8 Replace New Existing Barrier Barrier on Berm Existing Barrier STA 1371+96 STA 1382+84 21
Maintenance of Traffic / Staging Full Depth Full Depth Build Outside 2 nd Phase Build Inside 1 st Phase Build Outside 2 nd Phase 22
Aggressive Schedule Statement of Complete Request for Qualifications Due Proposal/Preliminary October 13, 2017 Plans December 7, 2017 Request for Owners Award of DB Representative Contract June 16, 2017 Anticipated Completion of Technical Proposals May 4, 2018 NEPA October 30, 2017 Due March 9, 2018 JUNE ‘17 AUGUST ‘17 OCTOBER ‘17 NOVEMBER ‘17 DECEMBER ‘17 MARCH ‘18 APRIL ‘18 MAY ‘18 Final Selection for Release Request for Short-Listed Design Issue Request for Proposal to Price Proposals Owners Representative Qualifications for I-440 Builders Short-listed Design-Builders Due August 2, 2017 August 18, 2017 November 10, 2017 December 15, 2017 April 27, 2018 23
Community Outreach • Noise Wall Meeting • As –Needed Community Outreach • Maintenance Agreement for Landscaping
Q & A 25
Recommend
More recommend