HOOVER, GREENE, & HILL PROJECT PUBLIC MEETING January 17, 2019 - PowerPoint PPT Presentation

HOOVER, GREENE, & HILL PROJECT PUBLIC MEETING January 17, 2019 Hill Street 2 Greene Street State Street N Project Lim imits 3 Project Criteria Road Improve road surface for traffic usage Cross-section 11 foot min.


  1. HOOVER, GREENE, & HILL PROJECT PUBLIC MEETING January 17, 2019

  2. Hill Street 2 Greene Street State Street N Project Lim imits

  3. 3 Project Criteria ▪ Road ✓ Improve road surface for traffic usage ✓ Cross-section – 11 foot min. travel lanes ✓ Bike lanes – 5 foot wide on Hoover ✓ ADA ramps – Update where needed ✓ Crosswalks – Update markings and signing ▪ Utilities ✓ Water main – Upgraded from 6-inch to 12-inch ✓ Storm sewer – Increase detention storage ✓ City Fiber Conduit

  4. 4 Project Im Improvements ▪ Hill (Adams to Fifth) ✓ Water main upgrade ✓ Road resurfacing ▪ Greene (Hill to Keech) ✓ Stormwater enhancements ✓ Road resurfacing ▪ Hoover (Main to State) ✓ Water main upgrade ✓ Stormwater enhancements ✓ Road resurfacing ▪ Selected sidewalk ramps/crosswalks improvements

  5. 5 Project Funding ▪ Part of Capital Improvement Plan (CIP) ▪ Funding Sources ✓ Water Funds ✓ Road Resurfacing Funds ✓ Allen Creek Storm Water Funds ✓ Possible U-M participation

  6. 6 Project Schedule ▪ March/April 2019 - Contractor selection ▪ Late April/Early May 2019 - Start work ▪ End August 2019 - Substantially complete

  7. 7 Proposed Uti tility Work – Hil ill Greene Street N

  8. 8 Proposed Road Work – Hill Greene Street N

  9. 9 Proposed Uti tility Work – Greene N

  10. 10 Proposed Road Work – Greene N

  11. 11 Proposed Uti tility Work – Greene & Keech N

  12. 12 Proposed Road Work – Greene & Keech N

  13. 13 Proposed Uti tility Work - Hoover N

  14. 14 Proposed Road Work - Hoover N

  15. 15 Proposed Uti tility Work - Hoover N

  16. 16 Proposed Road Work - Hoover N

  17. 17 Proposed Uti tility Work - Hoover N

  18. 18 Proposed Road Work - Hoover N

  19. 19 Maintenance of f Traffic – Primary ry Detours Estimated Duration: 4 months Traffic Detour for WB Hoover Traffic Detour for NB Greene/EB Keech Elbel IM Building Admin Serv Bldg Ferry Field SC36

  20. 20 Maintenance of f Traffic – Hoover Closure Estimated Duration: 4 Weeks Traffic Detour for Hoover Closure Traffic Detour for WB Hoover Traffic Detour for NB Greene/EB Keech Hoover Closure Elbel WB Hoover CLOSED Total Closure WB Hoover CLOSED IM Building EB Hoover OPEN Admin Serv Bldg Ferry Field SC36

  21. 21 Maintenance of f Traffic – Hill Closure Estimated Duration: 3 weeks Traffic Detour for EB Hill Traffic Detour for WB Hill Traffic Detour for WB Hoover Traffic Detour for NB Greene/EB Keech Total Hill Closure Closure Elbel Admi IM Building Admi n Serv n Serv Bldg Bldg Ferry Field SC36

  22. 22 Maintenance of f Traffic – Hill/Fifth Closure Estimated Duration: Weekend Traffic Detour for EB Hill Traffic Detour for WB Hill Traffic Detour for WB Hoover Traffic Detour for NB Greene/EB Keech Total Closure Hill Closure Elbel IM Building Admi Admi n Serv n Serv Bldg Bldg Ferry Field SC36

  23. 23 23 Questions & Contact Chris Wall, PE CWall@a2gov.org (734) 794-6000 ext. 43661