harrisburg overpass construction update
play

Harrisburg Overpass Construction Update September 1, 2015 Safety - PowerPoint PPT Presentation

Harrisburg Overpass Construction Update September 1, 2015 Safety First 10,700 Man hours worked to date No lost time accidents to date No recordable accidents to date West Bound Phase I Traffic Control Traffic Plan Phase 1A East Bound


  1. Harrisburg Overpass Construction Update September 1, 2015

  2. Safety First 10,700 Man hours worked to date • No lost time accidents to date • No recordable accidents to date

  3. West Bound Phase I Traffic Control

  4. Traffic Plan Phase 1A

  5. East Bound Phase I Traffic Control Safety First

  6. Safety First

  7. School began August 24 th Speed limit 20 MPH LOOK OUT FOR THE KIDS!

  8. Phase 1 – May ay 20 2015 15 to o November r 20 2015 15 Construction Activities Traffic Control • New waterlines, storm sewers, • Traffic moved to middle of Harrisburg sanitary sewers (1 lane each way) • Access from Harrisburg: • New private driveways, curbs • Side streets maintain access • New sidewalks • Some weekend and night intersection • New landscape closures for utility work • New roadways • Advanced coordination with property owners for new driveway construction Union NE NW Pacific SW SE

  9. Project Phase 1 NW NE Water Line: 900 LF Water Line: 900 LF Storm Line: 1100 LF Storm Line: 750 LF San. Line: 0 LF San. Line: 130 Union Pacific Job Limit Job Limit SW SE Water Line: 950 LF Water Line: 950 LF Storm Line: 1200 LF Storm Line: 700 LF San. Line: 0 LF San. Line: 370 LF

  10. West Side Phase 1 Work SW Quadrant + NW Quadrant Unexpected/Unknown Underground encounters so far: 31

  11. Barziza St. & Harrisburg Blvd. Caylor St. & Harrisburg Blvd. Gas Lines Unexpected Water Line

  12. North West Quadrant Total Installed % Completed 0 LF 0% Storm Sewer 1100 LF Water Line 0 LF 0% 900 LF Existing Lines Union Linwood St. Caylor St. Pacific Lot Vacant Dorsey Warehouse Demolition Abandoned and Field Office Lot Ware- Vacant Dental Lot House House Strip Mall Bent 1 Bent 2 Bent 5 Bent 3 Bent 4 Bent 6

  13. South West Quadrant Total Installed % Completed 71% 850 LF Storm Sewer 1200 LF 100% (Service Taps Remaining) Water Line 950 LF 950 LF Existing Lines Union Linwood St. Linwood St. Caylor St. Pacific Bent 1 Bent 2 Bent 3 Bent 5 Bent 4 Bent 6 Key Station C&R Houston Armature Auto Sales Gameroom Warehouse #93

  14. East Side Phase 1 Work NE Quadrant + SE Quadrant Unexpected/Unknown Underground encounters so far: 59

  15. In front of Tornado Bus Working under existing power lines In front of Value Village

  16. North East Quadrant Installed Total % Completed Storm Sewer 750 LF 550 LF 73 % Water Line 900 LF 900 LF 100 % (Service Taps Remaining) Sanitary Line 130 LF 110 LF 85 % Existing Lines Cesar 66 th ST. Chavez 65 th ST. Blvd. Union Pacific Popeye’s, Value Village Tornado Hendrick Vacant Gas Station, Storage Grain Co. Bus Co. Washateria Yard Lot 8 7 9 10 5 6 Cesar Hughes 66 th ST. 65 th ST. Chavez ST. Blvd.

  17. South East Quadrant Installed Total % Completed 0 LF Storm Sewer 750 LF 0 % Water Line 30 LF 900 LF 1 % Sanitary Line 0 LF 240 LF 0% Existing Lines Cesar 66 th ST. Chavez 65 th ST. Blvd. Union Pacific 9 8 10 7 6 5 Pegasso Marbella Texas Guanajuato Vacant Jorge’s Car Chonchino Family Taqueria Banquet Lot Cesar Bus 65 th ST. 66 th ST. Barber Auto Sales Belting and Truck Tierra Dollar Hall Shop #2 Tours Chavez Caliente #2 Store Blvd.

  18. Paving Phase 1 West Side Fast Track Paving for Intersections Phase 1 Access Roads Sidewalks Asphalt

  19. Paving Phase 1 East Side Fast Track Paving for Intersections Phase 1 Access Roads Sidewalks Asphalt

  20. MSE Wall Mock-Up

  21. Thank you See you in November