harrisburg overpass construction update
play

Harrisburg Overpass Construction Update December 1, 2015 All - PowerPoint PPT Presentation

Harrisburg Overpass Construction Update December 1, 2015 All Utility Work East of Union Pacific Railroad Total % Completed Installed 2095 LF Utilities Completed 3,800 LF 55% Utilities Remaining to be Relocated East of Union Pacific


  1. Harrisburg Overpass Construction Update December 1, 2015

  2. All Utility Work East of Union Pacific Railroad Total % Completed Installed 2095 LF Utilities Completed 3,800 LF 55%

  3. Utilities Remaining to be Relocated East of Union Pacific Railroad

  4. Concrete Paving East of Union Pacific Railroad

  5. Current Sidewalk Detour Plan 5

  6. All Utility Work West of Union Pacific Railroad Total % Completed Installed Utilities Completed 3,210 LF 73% 4,150 LF

  7. Utilities Remaining to be Relocated West of Union Pacific Railroad

  8. Concrete Paving West of Union Pacific Railroad

  9. Progress and Planned Activities • Pavement Operations are beginning in the Northeast Quadrant • McCarthy will maintain driveways by adding crushed stone as required • Relocated Street Lighting during construction to be maintained and illuminate along new roadway • METRO/McCarthy are working to adjust schedule activities to keep the project on schedule • Select construction activities will be built concurrently with major bridge activities during the third phase of construction • McCarthy will be working extended hours to expedite completion of roadway pavement • The placing, finishing, curing, and saw cutting new pavement requires extended work hours • Utility crews started 12 hour days instead of 10 hours • To make up time due to rain, McCarthy chose to work on one Sunday in November • McCarthy plans to work extra shifts during the drilling of the 6 major bridge bents in Phase II of the project • Weather permitting, this work will begin in January 2016 9

  10. 30 Day Look Ahead West of UPRR  Complete 24” Storm east of Caylor  Water line and Sanitary Sewer Service Taps  Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place concrete, cure, and saw cut for new roadway, intersection and driveway pavement  Install curbs and sidewalks  Install underground conduit for bridge lighting  Install temporary asphalt transitions from existing roadway to new concrete pavement East of UPRR  Complete all storm sewer lines  Complete 8” waterlines  Complete Sanitary sewer lines  Wet connects for water services  Clear and grub right of way for new roadway pavement  Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place concrete, cure, and saw cut for new roadway, intersection and driveway pavement  Traffic control switch from south to north side of Harrisburg to complete utility work in southeast quadrant 10

  11. Marketing Update for East End Businesses • Collaborated with the EEMD, the EECOC, Business Owners, and Residential Stakeholders • Final Product is the East End Calendar of Events scheduled to start on Wednesday, December 2 • We have produced 5,000 flyers ( English/Spanish) • Posters printed and distributed • Banners – facilities will install • Radio Buys with Univision ( Estereo Latino) • Print ads with two week run of the front cover and two page spread due December 2 – (Que Onda) • Foam Arrows for business visibility • Individual Store flyers • Direct Mail/Door hangers 11

  12. Radio Spots 12

Recommend


More recommend