Harrisburg Overpass Construction Update December 1, 2015
All Utility Work East of Union Pacific Railroad Total % Completed Installed 2095 LF Utilities Completed 3,800 LF 55%
Utilities Remaining to be Relocated East of Union Pacific Railroad
Concrete Paving East of Union Pacific Railroad
Current Sidewalk Detour Plan 5
All Utility Work West of Union Pacific Railroad Total % Completed Installed Utilities Completed 3,210 LF 73% 4,150 LF
Utilities Remaining to be Relocated West of Union Pacific Railroad
Concrete Paving West of Union Pacific Railroad
Progress and Planned Activities • Pavement Operations are beginning in the Northeast Quadrant • McCarthy will maintain driveways by adding crushed stone as required • Relocated Street Lighting during construction to be maintained and illuminate along new roadway • METRO/McCarthy are working to adjust schedule activities to keep the project on schedule • Select construction activities will be built concurrently with major bridge activities during the third phase of construction • McCarthy will be working extended hours to expedite completion of roadway pavement • The placing, finishing, curing, and saw cutting new pavement requires extended work hours • Utility crews started 12 hour days instead of 10 hours • To make up time due to rain, McCarthy chose to work on one Sunday in November • McCarthy plans to work extra shifts during the drilling of the 6 major bridge bents in Phase II of the project • Weather permitting, this work will begin in January 2016 9
30 Day Look Ahead West of UPRR Complete 24” Storm east of Caylor Water line and Sanitary Sewer Service Taps Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place concrete, cure, and saw cut for new roadway, intersection and driveway pavement Install curbs and sidewalks Install underground conduit for bridge lighting Install temporary asphalt transitions from existing roadway to new concrete pavement East of UPRR Complete all storm sewer lines Complete 8” waterlines Complete Sanitary sewer lines Wet connects for water services Clear and grub right of way for new roadway pavement Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place concrete, cure, and saw cut for new roadway, intersection and driveway pavement Traffic control switch from south to north side of Harrisburg to complete utility work in southeast quadrant 10
Marketing Update for East End Businesses • Collaborated with the EEMD, the EECOC, Business Owners, and Residential Stakeholders • Final Product is the East End Calendar of Events scheduled to start on Wednesday, December 2 • We have produced 5,000 flyers ( English/Spanish) • Posters printed and distributed • Banners – facilities will install • Radio Buys with Univision ( Estereo Latino) • Print ads with two week run of the front cover and two page spread due December 2 – (Que Onda) • Foam Arrows for business visibility • Individual Store flyers • Direct Mail/Door hangers 11
Radio Spots 12